Contract: EAGLE PEAK ROCK AND PAVING
Primary Recipient
EAGLE PEAK ROCK AND PAVING
Amount
$8,606,309.96
Award Date
5/19/2009
Administering Agency
Transportation, Department of / Federal Highway Administration
CDFA Number
CDFA Program Title
Description
Hot asphalt concrete pavement rehabilitaion, a concrete retaining wall, guardwall and drainage structures in Yosemite National Park.
Recipients Connected to Award
| Recipient | Role | Amount |
|---|---|---|
| EAGLE PEAK ROCK AND PAVING | Primary recipient | $5,577,460.35 |
| Gary Brown Electric, Inc. | Sub-recipient | $1,111,077.00 |
| Basco Concrete | Sub-recipient | $1,074,503.00 |
| Stoney Masonry, Inc. | Sub-recipient | $711,784.30 |
| MVE, INC. | Sub-recipient | $53,200.15 |
| Fonseca McElroy Grinding Co Inc | Sub-recipient | $51,606.00 |
| GROUND SERVICE TECHNOLOGY, INC. | Sub-recipient | $26,679.16 |