Contract: BALFOUR BEATTY CONSTRUCTION, LLC
Primary Recipient
BALFOUR BEATTY CONSTRUCTION, LLC
Amount
$42,532,835.00
Award Date
11/06/2009
Administering Agency
General Services Administration / Public Buildings Service
CDFA Number
CDFA Program Title
Description
Provide design phase services (preconstruction) and construction phase work for the Modernization Project at the Richard H Poff Federal Building in Roanoke, VA. Significant deliverables include: curtainwall; heating, ventilating, and air conditioning upg
Recipients Connected to Award
| Recipient | Role | Amount |
|---|---|---|
| SOUTHERN AIR, INCORPORATED | Sub-recipient | $13,103,719.00 |
| BALFOUR BEATTY CONSTRUCTION, LLC | Primary recipient | $11,258,411.00 |
| AMERICAN DOOR & GLASS - SOUTHWEST VIRGINIA, INC. | Sub-recipient | $10,079,490.00 |
| Baird Drywall and Acoustic, Inc. | Sub-recipient | $2,011,780.00 |
| ATHENA CONSTRUCTION GROUP, INC. | Sub-recipient | $1,933,184.00 |
| WESTAR ROOFING CORPORATION | Sub-recipient | $1,130,650.00 |
| SCAFFOLDING SOLUTIONS LLC | Sub-recipient | $543,745.00 |
| LVI ENVIRONMENTAL SERVICES INC. | Sub-recipient | $519,141.00 |
| Gibson Industrial, Inc. | Sub-recipient | $450,372.00 |
| VSC FIRE & SECURITY, INC. | Sub-recipient | $434,909.00 |
| BREAKELL, INC. | Sub-recipient | $420,408.00 |
| CURTAIN WALL DESIGN AND CONSULTING, INCORPORATED | Sub-recipient | $229,500.00 |
| Cleveland Concrete Construction, Inc. | Sub-recipient | $149,300.00 |
| Pro-Bel Enterprises Limited | Sub-recipient | $74,181.00 |
| CENTRE CARRIERS CORP. | Sub-recipient | $54,258.00 |
| E. LUKE GREENE COMPANY, INC. | Sub-recipient | $43,136.00 |
| Star City Masonry Inc | Sub-recipient | $33,500.00 |
| Project Management Service Bureau Inc | Sub-recipient | $31,834.00 |
| Building Specialists, Inc. | Sub-recipient | $31,317.00 |