Contract: KIEWIT INFRASTRUCTURE WEST CO.
Primary Recipient
KIEWIT INFRASTRUCTURE WEST CO.
Amount
$17,480,694.08
Award Date
3/27/2010
Administering Agency
Interior, Department of / Bureau of Reclamation
CDFA Number
CDFA Program Title
Description
8 Radial tainter gate arm and trunnion reconstruction, pier passive tendon installation, pier reinforcing and pier bracing at existing concrete dam. Project expected duration is 2 years from NTP.
Recipients Connected to Award
| Recipient | Role | Amount |
|---|---|---|
| KIEWIT INFRASTRUCTURE WEST CO. | Primary recipient | $10,430,580.47 |
| STRONG STRUCTURAL STEEL, LTD. | Sub-recipient | $2,380,455.00 |
| JENSEN DRILLING COMPANY | Sub-recipient | $1,639,200.00 |
| WILLIAMS FORM ENGINEERING CORPORATION | Sub-recipient | $959,566.53 |
| F. D. THOMAS, INC. | Sub-recipient | $389,865.80 |
| FURMANITE AMERICA, INC. | Sub-recipient | $378,720.00 |
| METALTEK INTERNATIONAL, INC. | Sub-recipient | $328,000.00 |
| RBC LUBRON BEARING SYSTEMS, INC. | Sub-recipient | $195,640.00 |
| Del Secco Diamond Core & Saw, Inc. | Sub-recipient | $173,825.00 |
| East Coast Metrology, LLC | Sub-recipient | $116,960.00 |
| REY ENGINEERS | Sub-recipient | $102,513.00 |
| Bess Testlab, Inc. | Sub-recipient | $98,550.00 |
| MAXIM CRANE WORKS, L.P. | Sub-recipient | $88,221.00 |
| MATRISCOPE ENGINEERING LABORATORIES, INC | Sub-recipient | $87,032.00 |
| Commercial Metals Company | Sub-recipient | $81,643.00 |
| Syna-Flex Rubber Products Co Inc | Sub-recipient | $29,922.28 |