Recovery Tracker

How Much Stimulus Funding is Going to Your County?

Lee County, Fla., funds by U.S. Army Corps of Engineers

Listing $1,361,006.27 in stimulus funds from U.S. Army Corps of Engineers for Lee

Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.

Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.

Recipient Amount Description Federal Dept./Agency Date
Entrix, Inc. $667,675 Central and South Florida Site 1 Impoundment Project. Strengthen existing L40 Levee with borrow material and armor the top and banks with soil cement and turf reinforcement mat. Other activities include clearing and grubbing, borrow excavation site and
This spending item is part of a $44,125,000 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/24/2010
BIG TREE, INC. $462,472 Central and South Florida Site 1 Impoundment Project. Strengthen existing L40 Levee with borrow material and armor the top and banks with soil cement and turf reinforcement mat. Other activities include clearing and grubbing, borrow excavation site and
This spending item is part of a $44,125,000 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/24/2010
The Wackenhut Corporation $230,859 The Picayune Strand Restoration Project, Merritt Pump Station and Levees, Canals and Roads is part of the Comprehensive Everglades Restoration Plan (CERP). The project will help to restore the area known formerly as the Southern Golden Gate Estates to its
This spending item is part of a $39,752,000 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 10/30/2009