Oklahoma County, Okla., funds by General Services Administration
Listing $4,643,208.84 in stimulus funds from General Services Administration for Oklahoma
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
OKLAHOMA ROOFING & SHEET METAL, LLC | $2,875,323 | Providing design build services for the Oklahoma Post Office and Federal Building roof replacement project. | Public Buildings Service | 3/09/2010 |
SCIENCE APPLICATIONS INTERNATIONAL CORPORATION | $922,042 |
Award executed to allow for accelerated deployment of the HIS Electrnic Dental Records System. Acceleration of the schedule will allow program to maintain more active teams in the field at the present time vice maintaining a much smaller complement of tea
This spending item is part of a $3,851,627 allocation.
See details
|
Office of the Federal Acquisition Service | 9/29/2009 |
Quality Plumbing Heating of Norman Inc | $285,000 |
Replace and relocate two mezzanine Air Handler Units in the Post Office Building, Oklahoma City, OK. Provide all design, management, labor, tools, material and supervision necessary to successfully complete the project.
This spending item is part of a $590,976 allocation.
See details
|
Public Buildings Service | 12/21/2009 |
CADDELL & CO LLC | $200,686 |
Replace and relocate two mezzanine Air Handler Units in the Post Office Building, Oklahoma City, OK. Provide all design, management, labor, tools, material and supervision necessary to successfully complete the project.
This spending item is part of a $590,976 allocation.
See details
|
Public Buildings Service | 12/21/2009 |
Jesco Electric Inc | $174,700 |
Install Exterior Lighting. Provide all management, labor, tools, materials, and supervision necessary to install exterior lighting at Post Office Building in accordance with approved design documents.
This spending item is part of a $252,617 allocation.
See details
|
Public Buildings Service | 9/16/2009 |
CADDELL & CO LLC | $77,917 |
Install Exterior Lighting. Provide all management, labor, tools, materials, and supervision necessary to install exterior lighting at Post Office Building in accordance with approved design documents.
This spending item is part of a $252,617 allocation.
See details
|
Public Buildings Service | 9/16/2009 |
AUTOMATED BUILDING SYSTEMS, INC. | $62,350 |
Replace and relocate two mezzanine Air Handler Units in the Post Office Building, Oklahoma City, OK. Provide all design, management, labor, tools, material and supervision necessary to successfully complete the project.
This spending item is part of a $590,976 allocation.
See details
|
Public Buildings Service | 12/21/2009 |
Jesco Electric Inc | $21,000 |
Replace and relocate two mezzanine Air Handler Units in the Post Office Building, Oklahoma City, OK. Provide all design, management, labor, tools, material and supervision necessary to successfully complete the project.
This spending item is part of a $590,976 allocation.
See details
|
Public Buildings Service | 12/21/2009 |
Woods Labor & Staffing | $13,112 |
Replace and relocate two mezzanine Air Handler Units in the Post Office Building, Oklahoma City, OK. Provide all design, management, labor, tools, material and supervision necessary to successfully complete the project.
This spending item is part of a $590,976 allocation.
See details
|
Public Buildings Service | 12/21/2009 |
BALDWIN ACOUSTICS & DRYWALL, INC | $6,500 |
Replace and relocate two mezzanine Air Handler Units in the Post Office Building, Oklahoma City, OK. Provide all design, management, labor, tools, material and supervision necessary to successfully complete the project.
This spending item is part of a $590,976 allocation.
See details
|
Public Buildings Service | 12/21/2009 |
Concrete Coring Co LLC | $2,328 |
Replace and relocate two mezzanine Air Handler Units in the Post Office Building, Oklahoma City, OK. Provide all design, management, labor, tools, material and supervision necessary to successfully complete the project.
This spending item is part of a $590,976 allocation.
See details
|
Public Buildings Service | 12/21/2009 |
AUTOMATED BUILDING SYSTEMS, INC. | $2,250 |
The award is to provide engineering and commissioning expertise to conduct re-commissioning / retro-commissioning planning, identify energy conservation measures, scoping, testing, investigation, evaluation, analysis, calculations, recommendations, and re
This spending item is part of a $291,882 allocation.
See details
|
Public Buildings Service | 8/27/2009 |