Stimulus Spot Check
To better understand the progress of stimulus transportation projects around the country, we drew a random sample of 520 of approximately 6,000 projects nationwide. In mid-July we asked our readers to help us track the status of these projects — whether the project had been started or has been completed, what company got the contract, and how many jobs the company says it retained or created for its stimulus contract.
"Our Stimulus Spot Check: Summer wave of projects nears crest" is the story that emerged from this study.
While not comprehensive, this chart provides a snapshot of what what was happening with a sample of projects last month. The chart does not include all information brought in by our volunteers. Information about individual projects may already be out-dated.
Want to participate in other projects like this? Sign up for ProPublica’s Reporting Network.
| State, County | Project Description | Project Status | Company Awarded Contract | # of Hours Worked/Month |
|---|---|---|---|---|
| Alabama, Baldwin | RESURFACING SR-3 (US-31) FROM 0.24 MILE NORTH OF SR-59 INTERSECTION IN STAPLETON TO BAY MINETTE SOUTH CITY LIMITS Funds Allocated: $2,886,968 |
Received Notice to Proceed 5/13/2009 (U.S. DOT, July 17, 2009) | ||
| Alabama, Butler | RESURFACE & 2' WIDENING ON SR-3 (US-31) FROM CONECUH COUNTY LINE TO 0.8 MILE NORTH PERSIMMON CREEK (FY2009 PHASE2) Funds Allocated: $2,335,367 |
Let to contract May 29, 2009. Notice to Proceed issued July 23, 2009. (Ronnie Baldwin, Alabama DOT) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Alabama, Elmore | RESURFACE SR-14 FROM SR-212 TO SR-9 AND RESURFACE SR-212 FROM SR-14 TO SR-111 Funds Allocated: $1,541,477 |
Let to contract May 29, 2009. Notice to Proceed issued July 30, 2009. (Ronnie Baldwin, Alabama DOT) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Alabama, Mobile | PAVEMENT WIDENING & RESURFACING ON SR-213 FROM SR-158 TO SR-13 (US-43) Funds Allocated: $691,974 |
Notice to Proceed issued July 22, 2009. (Ronnie Baldwin, Alabama DOT) | Hosea Weaver & Sons, Inc. | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Alabama, Chambers | FULL DEPTH RECLAMATION CR-267 FROM CR-222 IN FREDONIA TO SR-1 (US-431) SOUTH OF STROUD - CCP 09-09-01 Funds Allocated: $265,000 |
Notice to Proceed issued July 27, 2009. (Ronnie Baldwin, Alabama DOT) | Miller Group, Inc. | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Alabama, Chilton | PLANING, PAVEMENT WIDENING AND RESURFACING SR-155 FROM NEAR CR-33 TO SHELBY COUNTY LINE . FY2009 PHASE 2 Funds Allocated: $2,007,167 |
Let June 26, 2009. Project was awarded July 21, 2009. (Ronnie Baldwin, Alabama DOT) | Dunn Construction Company, Inc. | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Alabama, Tuscaloosa | RESURFACE SR-7 (US-11) FROM GREENE COUNTY LINE TO SOUTH END WARRIOR RIVER BRIDGE AT FOSTERS AND HOLLY SPRINGS ROAD FROM SR-7 (US-11) TO JUST SOUTH OF THE I-20/59 INTERCHANGE Funds Allocated: $4,415,517 |
Let July 31, 2009. (Ronnie Baldwin, Alabama DOT) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Alabama, Montgomery | RESURFACE & 2' WIDENING ON SR-97 FROM CRENSHAW COUNTY LINE TO NORTH OF JUNCTION OF SR-3 (US-31) (FY2009 PHASE2) Funds Allocated: $729,364 |
Let June 2009. Awarded. (Ronnie Baldwin, Alabama DOT) | APAC Mid-South Incorporated. | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Alabama, Cherokee | WIDENING & RESURFACING SR-273 FROM SR-68 IN LEESBURG TO AL-35 NEAR BLANCHE. FY 2009 PHASE 2 RESURFACING PROGRAM Funds Allocated: $5,743,428 |
Awarded. (Ronnie Baldwin, Alabama DOT) | Good Hope Contracting Company, Inc. | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Alaska, Valdez Cordova | Repave the bike path along the Richardson Highway from Egan Drive to Robe River Subdivision (7miles). The project will also rehabilitate and pave the access road to the Blueberry Lake Campground. Funds Allocated: $1,243,248 |
Advertised 6/09/09. Awarded 7/17/09. (AK DOT) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Harris Sand & Gravel, Inc. (AK DOT) | NA (AK DOT) |
| Arizona, Pima | Bridge Deck Rehab Funds Allocated: $191,204 |
Awarded (Laura Douglas, AZ Public Information Officer, August 3, 2009) Received Notice to Proceed 07/08/2009 (U.S. DOT, July 17, 2009) | Granite Construction Company (Laura Douglas, AZ Public Information Officer, August 3, 2009) | NA (Laura Douglas, AZ Public Information Officer, August 3, 2009) |
| Arizona, Statewide | Chip Seal Funds Allocated: $832,049 |
Estimated Construction Start Date: TBD Contract has not yet been executed. Actual Award Amount: $674,252. (Laura Douglas, AZ Public Information Officer, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Gradys Quality Excavating, Inc. (Laura Douglas, AZ Public Information Officer, August 3, 2009) | NA |
| Arizona, Maricopa | Widen Roadway Funds Allocated: $10,579,699
|
Project bids have just been received. Project has not been awarded. (Laura Douglas, AZ Public Information Officer, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009))(Laura Douglas, Public Information Officer, AZ DOT, July 31, 2009) | NA | |
| Arizona, Cochise | Replace Barb Wire Fence Funds Allocated: $807,612 |
Received Notice to Proceed 06/16/2009 (U.S. DOT, July 17, 2009) | D & O Contractors (Laura Douglas, AZ Public Information Officer, August 3, 2009) | |
| Arizona, Gila | Bridge Rehabilitation Funds Allocated: $20,000 |
Received Notice to Proceed 06/18/2009 (U.S. DOT, July 17, 2009) | URS Corporation (Laura Douglas, AZ Public Information Officer, August 3, 2009) | |
| Arizona, Maricopa | Design and Reconstruction of Pavement Funds Allocated: $20,000 |
This project is in the Preliminary Engineering Stage and will not be ready to advertise until all clearances are completed. The $20,000 is the amount of ARRA funds that are being used to get this project ready for construction. (Laura Douglas, AZ Public Information Officer, August 3, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) (Laura Douglas, Public Information Officer, AZ DOT, July 31, 2009) | |
| Arizona, Pima | Pavement Preservation Funds Allocated: $10,000 |
This project is in the Preliminary Engineering Stage and will not be ready to advertise until all the clearances are completed. The $10,000 is the amount of ARRA funds that are being used to get this project ready construction. (Laura Douglas, AZ Public Information Officer, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA (Laura Douglas, AZ Public Information Officer, August 3, 2009) | NA (Laura Douglas, AZ Public Information Officer, August 3, 2009) |
| Arizona, Maricopa | Design and Construct Signage Improvements Funds Allocated: $1,650 |
This project is pre-bid. [AZ DOT Laura Douglas July 31, 2009 & AZ DOT Web site] This project is in the Preliminary Engineering Stage and will not be ready to advertise until all the clearances are completed. The $1,650 is the amount of ARRA funds that are being used to get this project ready for construction. (Laura Douglas, AZ Public Information Officer, August 3, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009))(Laura Douglas, Public Information Officer, AZ DOT, July 31, 2009) | |
| Arkansas, Ouachita | ACHM REHABILITATION OF 2.59 MILES Funds Allocated: $1,077,056 |
Bids let 6/15/09. (Scott Bennett, Assistant Chief Engineer for Planning, Arkansas DOT) Received Notice to Proceed 06/03/2009 (U.S. DOT, July 17, 2009) | ||
| Arkansas, Little River | ACHM REHABILITATION OF 3.41 MILES Funds Allocated: $988,772
|
Construction started. (Scott Bennett, Assistant Chief Engineer for Planning, Arkansas DOT) Received Notice to Proceed 04/27/2009 (U.S. DOT, July 17, 2009) | R.K. Hall Construction, Paris, TX | |
| Arkansas, Lafayette | ACHM REHABILITATION OF 1.24 MILES Funds Allocated: $589,575 |
Construction started. 33% complete. (AR DOT) | R.D. Hall Construction, Paris, TX | |
| Arkansas, Crawford | ACHM REHABILITATION OF 2.00 MILES Funds Allocated: $501,865
|
Construction started. Project is 97% complete. (Carolyne Garcia). Received Notice to Proceed 04/20/2009 (U.S. DOT, July 17, 2009) The bid was advertised on 3/10/09 and awarded 4/10/09 and the notice to proceed was received on 4/20/09. (Arkansas Monthly Summary Report May) | Forsgren Construction | |
| Arkansas, Sevier | ACHM REHABILITATION OF 1.01 MILES Funds Allocated: $382,750
|
Contract awarded 7/17/09. (Scott Bennett, Assistant Chief Engineer for Planning, Arkansas DOT) Received Notice to Proceed 06/08/2009 (U.S. DOT, July 17, 2009) | R.K. Hall Construction, Paris, TX | |
| Arkansas, St Francis | ACHM REHABILITATION OF 4.30 MILES Funds Allocated: $1,663,847
|
Engineering work is complete, site work is expected to be complete by 9/1/09. (Scott Bennett, Assistant Chief Engineer for Planning, Arkansas DOT) Received Notice to Proceed 06/15/2009 (U.S. DOT, July 17, 2009) | Arkansas Highway Transportation Dept. | |
| California, Sutter | In Yuba City, from Plumas to Shasta, construct signal-phasing modifications, street reconstruction, pedestrian-scale street lighting, sidewalks and new pedestrian crossings as part of the city's downt Funds Allocated: $1,900,000 |
Advertised 05/11/2009. Awarded 06/10/2009 (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Granite Construction Company | NA |
| California, San Diego | From I-805 to Otay Mesa Port of Entry Funds Allocated: $78,336,000
|
Advertised 4/14/09, awarded 5/08/09, and issued Notice to Proceed 5/20/09. (CA Monthly Summary Employment Report, June) Received Notice to Proceed 05/20/2009 (U.S. DOT, July 17, 2009) | FlatIron West/Sukut Construction | |
| California, Orange | In Orange County in and near Laguna Beach, from Dana Point/Laguna Beach City limits to Aster Street, and from State Park to Newport Coast Drive. Funds Allocated: 040C203
|
Advertised 4/20/09. Awarded 6/0409. Issued Notice to Proceed 9/08/09. (CA Monthly Recipient Project Status Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | All American Asphalt (CA Monthly Recipient Project Status Report, June) | NA |
| California, Napa | In Napa County near Calistoga, from 0.2 miles north of Silverado Trail to Lake County line. Funds Allocated: $690,000 |
Advertised 5/18/09. Awarded 6/29/09. (CA Monthly Recipient Project Status Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Sonoma | In Sonoma County near Fort Ross, from 2.5 miles south of Fort Ross Road to Timber Cove Road, and near Gualala from Sea Walk Drive to Gualala River Bridge (# 10-181). Funds Allocated: $575,000
|
Advertised 5/26/09. (CA Monthly Recipient Project Status Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Santa Clara | In Santa Clara County near Los Gatos, from Black Road to the State Route 35 separation. Funds Allocated: $1,610,000 |
Advertised 5/26/09. (CA Monthly Recipient Project Status Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Monterey | Near Salinas, from Central Avenue to Gould Avenue at various locations Funds Allocated: $5,604,210 |
Advertised 6/01/09. (CA Monthly Recipient Project Status Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Santa Clara | Rehabilitate local street Funds Allocated: $316,000 |
Advertised 6/03/09 (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Los Angeles | VALLEY VIEW AV & MEYER ROAD N/O IMPERIAL HWY , PAVEMENT REHABILITATION Funds Allocated: $440,457
|
Advertised 6/09/09 (CA Monthly Recipient Project Status Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Los Angeles | CHERRY AVENUE REHABILITATION . , GRIND AND OVERLAY PAVEMENT . Funds Allocated: $500,000
|
Advertised 6/12/09 (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Los Angeles | TRAFFIC SIGNAL LED INDICATION AND MASS ARM STREET NAME SIGN UPGRADE - PHASE 2 Funds Allocated: $3,559,610
|
Advertised 6/16/09. (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, El Dorado | FORNI RD AND PONY EXPRESS ROAD SEE SCOMMENTS , REHABILITATION Funds Allocated: $822,435
|
Advertised 6/26/09 (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Orange | In Orange County in Laguna Niguel, Laguna Hills, Aliso Viejo, Laguna Beach and Irvine, from Interstate 5 to Ford Road undercrossing. Funds Allocated: $8,280,000
|
Awarded 6/25/09. (Earl Seaberg, CalTrans) Waiting for Notice to Proceed (Ryan Overman, Project Manager at R.J. Nobel) | R.J. Nobel Company (Earl Seaberg, CalTrans) | NA (Earl Seaberg, CalTrans) |
| California, Solano | In Fairfield, from 0.4 mile west of Route 12 to 0.8 mile east of Airbase Parkway. (FTIP Description: Suisun/Fairfield: From I-80/I680/SR12 (Redtop) to Putah Creek; construct HOV lanes and install Ramp Funds Allocated: $19,570,134
|
Awarded contract 4/21/09. Notice to Proceed issued 5/18/09. The project should finish in November of '09. (Earl Seaberg, CalTrans) Received Notice to Proceed 05/18/2009 (U.S. DOT, July 17, 2009) | Top Grade Construction (Earl Seaberg, CalTrans) | In May, 22 employees worked for a total of 595 hours. The state also worked on the project. According to its May Monthly Recipient Project Status Report 39 employees worked for a total of 706 hours. For June, the state/local government had 79 employees working for 2,055 hours. For June, Top Grade had 59 prime and subcontractors working for a total of 4,601 hours. Altogether 138 headcounts. (Earl Seaberg, CalTrans) |
| California, Los Angeles | SOUTH STREET IMPROVEMENTS FROM EAST CITY LIMIT TO LAKEWOOD BOULEVARD - RESURFACE PAVEMENT, CONCRETE REPAIRS, CURB RAMPS, TRAFFIC SIGNAL MODIFICATIONS, SIGNING AND STRIPING Funds Allocated: $1,545,000
|
Bid let 7/30/09. (Kimberly McManus, Administrative Clerk, Dept. of Public Works, City of Lakewood)NA (CA Monthly Recipient Project Status Report, June) | NA | NA |
| California, Ventura | In Ventura County in and near Camarillo, from Daily Drive to State Route 118. Funds Allocated: $1,736,500
|
Bid was let May 4th and contract awarded June 16 (Ray Zhang, project chief at the Division of Local Assistance at CalTrans). A Notice to Proceed was given 07/16/2009 (U.S. DOT, July 17, 2009) . Project manager at Security Paving says work will begin "in the next 30 days." (July 23, 2009) The project is affiliated with State Highways. All information about the project will be posted here. | Security Paving Company | NA |
| California, San Mateo | Rehabilitate local street Funds Allocated: $1,545,000
|
Contract bidding opened 6/23/2009. Winning bidder to be announced early August | NA | NA |
| California, Los Angeles | COLIMA RD, ET AL. - ROADWAY RESURFACING Funds Allocated: $3,000,340
|
NA (CA Monthly Recipient Project Status Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Los Angeles | Improvements in Somerset Boulevard from Orange Avenue to LA River and Orange Avenue from Alondra Boulevard to Jackson Street - resurface pavement, concrete repairs, curb ramps, signing and striping, t Funds Allocated: $250,000 |
NA (CA Monthly Recipient Project Status Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | -- | NA |
| California, Contra Costa | DIABLO RD. & GREEN VALLEY RD. , PAVEMENT OVERLAY Funds Allocated: $971,000
|
NA (CA Monthly Recipient Project Status Report, June) Project is currently let out to bid until September 1. | Not Awarded | NA |
| California, Los Angeles | NEW LANDSCAPE IMPROVEMENTS ADJACENT TO BALLONA CREEK BIKEWAY BETWEEN OVERLAND AVENUE AND PEDESTRIAN BRIDGE/OCEAN DRIVE. Funds Allocated: $476,174
|
NA (CA Monthly Recipient Project Status Report, June) Project undergoing review (LA County Trans.) | NA | NA |
| California, Orange | TAFT AVENUE FROM LEMON ST. TO CANNON ST. , RAISED LANDSCAPED MEDIANS Funds Allocated: $150,000 |
NA (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Los Angeles | GRAND AVENUE PAVING PROJECT FROM ARROW HIGHWAY TO FOOTHILL BOULEVARD. GRIND AND PAVE ASPHALT PAVEMENT, CONSTRUCT LOCAL REPAIRS, RECONSTRUCT DAMAGED CURB/GUTTER, SIDEWALK, CROSSGUTTER AND CURB RAMPS. Funds Allocated: $1,537,000
|
NA (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Los Angeles | MONTEREY ROAD NEW TRAFFIC SIGNALS. CONSTRUCT 3 NEW TRAFFIC SIGNALS AT MONTEREY RD./GENEVA ST., MONTEREY RD./JACKSON ST., MONTEREY RD./LOUISE ST. ALL 3 INTERSECTIONS SATISFY THE CALIFORNIA MUTCD WARRA Funds Allocated: $900,000
|
NA (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Butte | Reconstruct Interchange, improve operations Funds Allocated: $5,500,000 |
NA (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Butte | Roadway Overlay Funds Allocated: $620,000 |
NA (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Los Angeles | REHABILITATION OF ROADWAY, RESTORATION OF STREET SHOULDER, HAZARD ELIMINATION AND INCIDENTAL DRAINAGE IMPROVEMENT TO PROTECT STREET EROSION. HACIENDA ROAD FROM NORTH CITY LIMITS TO AVOCADO CREST; AND Funds Allocated: $500,000 |
NA (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, El Dorado | CARSON RD AND COLD SPRINGS RD ; SEE SCOMMENTS , REHABILITATION Funds Allocated: $650,000
|
NA (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Los Angeles | ATLANTIC AVE: FERNWOOD AVE TO MCMILAN AVE . , PAVEMENT REHABILITATION . Funds Allocated: $564,871
|
NA (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Los Angeles | MODERNIZE FOUR TRAFFIC SIGNALS ON BUENA VISTA STREET AND ON HOLLYWOOD WAY AND INSTALL FIBER OPTIC COMMUNICATIONS ON MAGNOLIA BOULEVARD Funds Allocated: $618,000 |
NA (CA Monthly Recipient Project Status Report, June)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| California, Los Angeles | MALIBU CANYON ROAD IMPROVEMENTS AND RECONSTRUCTION PROJECT; RECONSTRUCTION, SHOULDER IMPROVEMENTS, GUARDRAIL/SAFETY DEVICES AND OVERLAY ALONG MALIBU CANYON ROAD FROM PACIFIC COAST HIGHWAY TO CITY LIMI Funds Allocated: $500,000
|
Project obligated on 6/1. Advertisement/bid process phase in-progress. (Info was provided on 7/27 by Earl Seaberg, CalTrans, Director's of Transportation's Office, Economic Stimulus (Project/Team), per HR he's a Supervising Bridge Engineer.) | -- | NA |
| California, Ventura | Traffic Signal Improvements, various locations Funds Allocated: $740,000
|
This project has not been placed for bid as of yet but is expected to be listed sometime the week of August 3, 2009. (Oxnard Traffic Office, July 28, 2009) | NA | NA |
| California, Los Angeles | SUNSET BLVD FROM WEST CITY BOUNDARY (WEST OF CORY AVE) TO EAST CITY BOUNDARY (EAST OF HARPER AVE) GRIND AND OVERLAY ROADWAY PAVEMENT WITH RUBBERIZED ASPHALT; INSTALL BUS PADS; UPDATE ROADWAY MARKINGS Funds Allocated: $1,105,000
|
This project was just approved to go out to bid in early July. They expect work to begin on the project in October. (Sharon Perlstein, city engineer for the City of West Hollywood) | NA | NA |
| Colorado, Jefferson | SH 40 (COLFAX): KIPLING TO SHERIDAN, RESURFACING Funds Allocated: $3,337,195
|
Advertised 3/12/09. Awarded 4/8/09. Issued Notice to Proceed 5/1/09. (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) Received Notice to Proceed 05/01/2009 (U.S. DOT, July 17, 2009) | 35 employees, 610 hours worked through June 30, 2009 (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) | |
| Colorado, Chaffee | US24/285 JOHNSON VILLAGE NORTH, RESUFACING Funds Allocated: $5,064,720 |
Advertised 3/26/09. Awarded 5/6/09. Notice to Proceed issued 5/19/09. (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) Received Notice to Proceed 05/19/2009 (U.S. DOT, July 17, 2009) | Asphalt Paving, Co. | |
| Colorado, Summit | SH9: BRECKENRIDGE NORTH, WIDEN FROM 2 LANES TO 4, ADD CURB & GUTTER, STORM DRAIN Funds Allocated: $8,994,331 |
Advertised 4/9/09. Awarded 5/27/09. Notice to Proceed issued 6/4/09. (CO DOT, Stacey Stegman, June Monthly Summary Employment Report)Received Notice to Proceed 06/04/2009 (U.S. DOT, July 17, 2009) | Zak Dirt, Inc. (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) | 4 employees, 599 hours worked by state DOT employees through June 30, 2009 (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) |
| Colorado, Larimer | I-25 FROM CROSSROADS NORTH: RUBBILIZATION, RUBBILIZE EXISTING CONCRETE PAVEMENT AND OVERLAY W/ASPHALT Funds Allocated: $6,859,424 |
Advertised 5/14/09. Awarded 6/15/09. Notice to Proceed issued 7/1/09. (CO DOT, Stacey Stegman, June Monthly Summary Employment Report).Received Notice to Proceed 07/01/2009 (U.S. DOT, July 17, 2009) | Aggregate Industries-WCR | 2 employees, 32 hours worked through June 30, 2009 (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) |
| Colorado, Douglas | C-470: SANTA FE TO I-25 RESURFACING + C-470 BIKETRAIL, CPR/SMA OVERLAY FOR C-470 AND REHAB C-470 BIKE TRAIL Funds Allocated: $31,465,789
|
Construction started the weekend of July 11, 2009, according to the Colorado Department of Transportation (CDOT)) Received Notice to Proceed 06/16/2009 (U.S. DOT, July 17, 2009) | Castle Rock Construction Company of Centennial, Colo | The number of hours logged for this project is unavailable at this time. According to Stacey Stegman, public information director for CDOT, the contractors (in this case, Castle Rock Construction Company of Centennial, Colo.) are responsible for reporting hours, and are only obligated to do so every two months. Since the project began July 11, 2009, the numbers may not be available until Sept. 11, 2009. However, Stegman relayed the following direct information as relayed to her by Don Hanneman of Castle Rock Construction Company: For this specific project (C-470), Castle Rock Construction Company has already to date hired six new employees, and saved 135 positions, for a total of 250 employees working on this project at any given time. |
| Colorado, Jefferson | I-70: KIPLING TO WADSWORTH RESURFACING, CONCRETE SLAB REPAIR WITH JOINT SEAL AND CROSS STITCH Funds Allocated: $1,793,405
|
Construction started. Advertised 3/12/09. Awarded 4/8/09. Notice to Proceed issued 4/21/09. (CO DOT, Stacey Stegman, June Monthly Summary Employment Report)Received Notice to Proceed 04/21/2009 (U.S. DOT, July 17, 2009) | New Design Construction Company (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) | 46 employees, 1099 hours worked through June 30, 2009 (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) |
| Colorado, Adams | I-70 PENA BLVD TO TOWER RD, INSTALL MEDIAN CABLE BARRIER Funds Allocated: $328,632
|
Construction started. Advertised 4/30/09. Awarded 6/1/09. Notice to Proceed issued 6/22/09. (CO DOT, Stacey Stegman, June Monthly Summary Employment Report). Received Notice to Proceed 06/22/2009 (U.S. DOT, July 17, 2009) | Ideal Fencing Corporation. (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) | 1 employee, 2 hours worked through June 30, 2009 (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) |
| Colorado, Morgan | SOUTH SIDE OF THE RAINBOW ARCH BRIDGE IN FT.MORGAN, KIOSK AND PED ENHANCEMENTS Funds Allocated: $140,000 |
NA (CO DOT, Stacey Stegman, June Monthly Summary Employment Report). No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Colorado, Boulder | BIKE/PED INTERSECTION IMPROVEMENTS: SPRUCE TO FOLSOM ST, INTERSECTION IMPROVEMENTS Funds Allocated: $320,000
|
Went out to bid on 7/1/09. Awarded. Notice to Proceed should be issued in next couple of weeks (Peggy Silcox, City of Boulder Project Manager, 7/27/09) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Goodland Construction Company (Peggy Silcox, City of Boulder Project Manager, 7/27/09) | NA |
| Colorado, Adams | I-76/UPRR, I-76 SH 224, BRIDGE REPLACEMENT Funds Allocated: $10,876,514 |
Work started. Advertised 3/12/09. Awarded 5/12/09. Notice to Proceed issued 6/2/09. (CO DOT, Stacey Stegman, June Monthly Summary Employment Report)Received Notice to Proceed 06/02/2009 (U.S. DOT, July 17, 2009) | Sema Construction, Inc. (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) | 5 employees, 322 hours worked by state DOT employees through June 30, 2009 (CO DOT, Stacey Stegman, June Monthly Summary Employment Report) |
| Connecticut, Hartford | Rocky Hill; Mill and overlay from Glastonbury Avenue to 50 feet south of bridge over Goff Brook Funds Allocated: $1,952,000 |
Awarded. Construction is expected to begin by mid-August. (Judd Everhart, Public Informations Officer, CT DOT, July 31, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | J. Iapaluccio Inc. of Brookfield, CT (Judd Everhart, Public Informations Officer, CT DOT, July 31, 2009) | NA (Judd Everhart, Public Informations Officer, CT DOT, July 31, 2009) |
| Connecticut, Litchfield | Sue Grossman Stillwater Greenway in Torrington Funds Allocated: $900,000 |
Construction is underway. (Judd Everhart, Public Informations Officer, CT DOT, July 31, 2009) (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | Schultz Construction of Plymouth, CT (Judd Everhart, Public Informations Officer, CT DOT, July 31, 2009) | NA. (Judd Everhart, Public Informations Officer, CT DOT, July 31, 2009) |
| Delaware, Statewide | 2009 Traffic Signal Improvements, Statewide Funds Allocated: $1,554,381
|
9 intersections statewide will or have undergone signal upgrades. 4 intersections were completed as of July 8, 2009. 4 are under construction and 1 is ready for advertisement. (Source: Deldot Public Relations Director Darrel Cole, and Recovery.Delaware.Gov, which includes detailed descriptions of the work being done, and the locations of each of the 9 intersections. July 22, 2009) Received Notice to Proceed 04/21/2009 (U.S. DOT, July 17, 2009) | Byers Electrical, and subcontractor Kriss Contracting Inc | The May 2009 Monthly Summary Employment Report filed by Deldot indicates a total of 79 employees, 2187 hours worked, and a total of $46,244 spent. The June Monthly Summary Employment Report filed by DelDOT indicates a total of 26 employees, 840 hours worked in June. |
| Delaware, New Castle | NCC Mill Creek Greenway Funds Allocated: $79,033
|
Received Notice to Proceed 05/18/2009 (U.S. DOT, July 17, 2009) | McCormick Taylor, Inc. | The June Monthly Summary Employment Report filed by DelDOT indicates 7 a total of 7 employees, 113 hours worked in June. |
| Delaware, New Castle | Pavement & Rehabilitation, North XIV, Replacement of Concrete Median Barrier, I-95, 2009 Funds Allocated: $1,414,690
|
This project was put out to bid on July 21, 2009 (DelDot Public Relations Director Darrell Cole, July 15, 2009) | NA | |
| Florida, Hernando | CR 587(MARINER BLVD) FROM MADERIA ST TO AUGUSTINE RD;RESURFACING;CONSTRUCTION;LAP Funds Allocated: $1,186,900 |
Advertised in April 2009. Awarded in June 2009. Estimated beginning of construction July 2009. (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Hernando | SR 50 FROM E OF US 98/SR 700 TO CR 575;RESURFACING;CONSTRUCTION Funds Allocated: $1,212,200 |
Advertised in July 2009. (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Miami Dade | NE 87 STREET FROM NE 2 AVENUE TO NE 4 ROAD;RESURFACING;CONSTRUCTION Funds Allocated: $51,650 |
Advertised May 2009. Awarded July 2009. (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Santa Rosa | SR 281 AVALON BLVD FROM N OF CSX R/R BRIDGE TO S OF COMMERCE ROAD; AMERICAN RECOVERY & REINVESTMENT ACT (ARRA) Funds Allocated: $11,200,000 |
Awarded June 2009. (FL DOT Web site, August 3, 2009) Received Notice to Proceed 05/26/2009 (U.S. DOT, July 17, 2009) | ||
| Florida, Martin | INDIAN STREET BRIDGE FROM W. OF MAPP ROAD TO E. OF KANNER HIGHWAY;NEW BRIDGE CONSTRUCTION;CONSTRUCTION;DB Funds Allocated: $127,757,455
|
Awarded. No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | Archer Western. The company will be collaborating with Reynolds, Smith and Hills, who will handle the engineering. (Florida Department of Transportation Web site, July 31, 2009) | 0 hours worked on the project to date. They expect to be able to complete the project in about 3 years. (Florida Department of Transportation Web site, July 31, 2009) |
| Florida, Miami Dade | WEST FLAGLER STREET FROM WEST 92 AVENUE TO WEST 87 AVENUE;RESURFACING;CONSTRUCTION;LAP Funds Allocated: $260,000 |
Contract advertisement July 2009. Award scheduled for August 2009. (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Escambia | SR 95 (US 29) FROM SOUTH OF JACKSON ST TO NORTH OF COTTAGE ST;DRAINAGE IMPROVEMENTS;AMERICAN RECOVERY & REINVESTMENT ACT (ARRA) Funds Allocated: $500,000 |
NA (FL DOT Web site, August 3, 2009) Received Notice to Proceed 06/19/2009 (U.S. DOT, July 17, 2009) | ||
| Florida, Monroe | VIRGINA STREET FROM WINDSOR LANE TO JOSE MARTI DRIVE (ADA;SIDEWALK;CONSTRUCTION;LAP Funds Allocated: $212,500 |
NA (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Holmes | SR 79 FIRST AVENUE SIDEWALKS;DB; AMERICAN RECOVERY & REINVESTMENT ACT (ARRA) Funds Allocated: $110,000 |
NA (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Union | CR 231 FR: REGIONAL MEDICAL CEN TO: CR 231A;RESURFACING;CONSTRUCTION Funds Allocated: $573,600 |
NA. (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Monroe | TWELFTH STREET FROM FLAGLER AVENUE T K-MART/PATTERSON ST.(ADA;SIDEWALK;CONSTRUCTION;LAP Funds Allocated: $34,000 |
NA. (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Monroe | LEON STREET FROM CATHERINE STREET TO FLAGLER AVENUE (ADA;SIDEWALK;CONSTRUCTION;LAP Funds Allocated: $221,000 |
NA. (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Calhoun | CITY OF BLOUNTSTOWN PAVEMENT MARKINGS;SAFETY PROJECT;LAP; AMERICAN RECOVERY & REINVESTMENT (ARRA) Funds Allocated: $55,000 |
NA. (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Escambia | CR 95A OLD PALAFOX FROM E ROBERTS BLVD TO 9 MILE ROAD;LAP; AMERICAN RECOVERY & REINVESTMENT ACT (ARRA) Funds Allocated: $858,684 |
NA. (FL DOT Web site, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Florida, Jackson | MILTON AVENUE FROM BALTZELL TO SR 10 (US 90);RESURFACING;LAP; AMERICAN RECOVERY & REINVESTMENT ACT (ARRA) Funds Allocated: $306,898 |
No Notice to Proceed issued yet (U.S. DOT, July 24, 2009) | NA | |
| Georgia, Haralson | Will involve the construction of sidewalks, curb and gutter, seatwalls, lighting, street furniture and landscaping around the historic Old Haralson County Courthouse. Phase one included improvements o Funds Allocated: $438,000
|
Has not been let. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | -- (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, Rockdale | This project is the resurfacing of SR 20. This section of SR 20 needs resurfacing because the existing pavement is deteriorating. SR 20 was last resurfaced in 1990. Funds Allocated: $2,188,101
|
Let in July. Awarded. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | Pittman Construction. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, Wilkinson | This project is the construction of the North Gordon Bypass from SR 57 at the Twiggs/Wilkinson County Line to SR 243 milepost 3.32, the bridge over Commissioner Creek for a distance of 7.2 miles. This Funds Allocated: $56,366,519
|
Let in July. Awarded. No Notice to Proceed issued yet. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | Prince Contracting. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, De Kalb | This project is the milling and resurfacing of SR 10. This section of SR 10 needs resurfacing because the existing pavement is deteriorating. SR 10 was last resurfaced in 1990. Funds Allocated: $5,101,371
|
Let in July. Awarded. Notice to Proceed issued 7/17/09. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | ER Snell Contractors. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, Tattnall | This project is a bridge replacement on S.R. 56/Nail Bridge @ the Ohoopee River 2 miles west of Reidsville. Funds Allocated: $4,177,171
|
Let in June. Awarded. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | Southern Concrete Construction. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, Fayette | Project Description: Upgrade existing traffic signal equipment and pedestrian facilities for S.R. 314 and S.R. 54 at various intersections in Fayette County. The intersections are as follows: Funds Allocated: $213,440
|
Let in June. Awarded. Notice to Proceed issued 7/20/09. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | Comtrac Services. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, Lanier | This project proposes to realign on new location SR 11/US 129 and SR 31, 122/ US 221 to create two, (2), 90 degree "T" intersections with SR 37 to improve safety and turning movements. These intersec Funds Allocated: $3,129,018
|
Let in June. Awarded. Notice to Proceed issued 7/22/09. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | Dixie Roadbuilders. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, Catoosa | ARRA 2009 - CONSTRUCTION FOR PI# 0001418, CST Funds Allocated: $1,619,924
|
Let in June. Awarded. Notice to Proceed issued 7/27/09. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | CW Matthews Contractors. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, Dodge | This project is the milling and resurfacing of SR 117. This section of SR 117 needs resurfacing because the existing pavement is deteriorating. SR 117 was last resurfaced in 1989. Funds Allocated: $3,102,028
|
Let in May. Awarded. Notice to Proceed issued 6/22/09. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) Received Notice to Proceed 06/22/2009 (U.S. DOT, July 17, 2009) | Ross Construction. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, Ware | This project is the milling and resurfacing of SR 4 Business.This section of SR 4 Business needs resurfacing because the existing pavement is deteriorating. SR 4 Business was last resurfaced in 1991. Funds Allocated: $1,980,285
|
Let in May. Awarded. Notice to Proceed issued 6/25/09. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) Received Notice to Proceed 06/25/2009 (U.S. DOT, July 17, 2009) | Dixie Roadbuilders. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, Chatham | This project is the milling and resurfacing of SR 30. This section of SR 30 needs resurfacing because the existing pavement is deteriorating. SR 30 was last resurfaced in 1975. Funds Allocated: $204,108
|
Let in May. Awarded. Notice to Proceed issued 6/30/09. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) Received Notice to Proceed 06/30/2009 (U.S. DOT, July 17, 2009) | Baker Construction. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Georgia, Henry | ARRA 2009 - CONSTRUCTION FOR PI# 0008584, CST Funds Allocated: $1,767,050
|
Scheduled to be let in August. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) | NA. (Lillian Jackson, Communications Director, GA DOT, July 31, 2009) |
| Guam, Statewide | Rte 25 (Alageta Road) Reconstruction and Widening (Bello Road to Route 26) Funds Allocated: $6,500,000 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Hawaii, Kauai | KUHIO HIGHWAY RESURFACING, KAWAIHAU ROAD TO KAPAA BRIDGE (CON) Funds Allocated: $1,586,292
|
Awarded 6/19/09. Notice to Proceed issued 7/20/09. Anticipated that construction will start soon. (Tammy Mori, Hawaii DOT, August 3, 2009) | Grace Pacific (Tammy Mori, Hawaii DOT, August 3, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Hawaii, Maui | Reconstruction and beautification of Market Street from Kahawai Street to Makuhau Road. Install drainage system, street lights, landscaping and irrigation. Funds Allocated: $5,287,166
|
Project has not been let yet. Projected start date is January, 2010. (Cary Yamashita from Maui Council, July 28, 2009) | NA | NA |
| Idaho, Idaho | Widen 2.619 miles of road Funds Allocated: $5,602,116 |
Advertised 5/20/09. Awarded 7/2/09. Estimated construction start: Summer 2009. (Idaho DOT Web site) Received Notice to Proceed 07/02/2009 (U.S. DOT, July 17, 2009) | Knife River, Boise (Idaho DOT Web site) | 5 employees, 40 hours worked in June according to Idaho DOT Monthly Summary Employment Report |
| Idaho, Twin Falls | Resurface 0.19 mile of road Funds Allocated: $66,000 |
In design phase. (Jerry Flatz, Local Highway Technical Assistance Council, Idaho, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Idaho, Fremont | Resurface 0.47 mile of road Funds Allocated: $66,000 |
In design phase. (Jerry Flatz, Local Highway Technical Assistance Council, Idaho, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Na | |
| Illinois, Cook | FOSTER ST TO TOUHY AVE Funds Allocated: $2,513,174 |
Contract No: 60F01, Awarded 4/22/09, Contract started: 5/18/09 (Marisa Kollias, IL DOT, August 3, 2009) Received Notice to Proceed 04/30/2009 (U.S. DOT, July 17, 2009) | Arrow Road Construction (Marisa Kollias, IL DOT, August 3, 2009) | |
| Illinois, Cook | BURNHAM AVE TO INDIANA STATE LINE Funds Allocated: $565,000 |
Contract No: 60F21, Awarded 5/20/09, Contract started: 6/23/09 (Marisa Kollias, IL DOT, August 3, 2009) Received Notice to Proceed 06/01/2009 (U.S. DOT, July 17, 2009) | Gallagher Asphalt (Marisa Kollias, IL DOT, August 3, 2009) | |
| Illinois, Cook | Resurface FAU 1311 (Overlook Drive) from Waukegan Road to Golf Road, 1.47 miles in the Village of Golf in Cook County. Funds Allocated: $252,000 |
Contract No: 63191 – Project was on 07/31/09 letting. Not Awarded Yet (Marisa Kollias, IL DOT, August 3, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Illinois, Cook | AT VARIOUS STRUCTURES (103RD, 111TH, 112TH, 115TH, 125TH, 167TH AND AT PEOTONE-JOLIET RD) Funds Allocated: $1,300,000 |
103rd St. - Contract No: 60366, Awarded 4/20/09, Contractor: Lorig Construction, Contract started: 6/1/09; 111th St. Contract No.: 62532, Awarded 5/20/09, Contractor: Lorig Construction, Contract Started: 4/1/10; 112th St. Contract No.: 62533, Awarded 5/14/09, Contractor: Areatha Construction, Contract Started: 6/4/09; 115th St. Contract No.: 60371, Awarded 4/17/09, Contractor: Herlihy-Mid Continent Construction, Contract Started: 5/11/09; 125th St. Contract No.: 60862, Awarded 4/22/09, Contractor: Herlihy-Mid Continent Construction, Contract Started: 5/24/09; 167th St. Contract No.: 60D63, Awarded 5/13/09, Contractor: Sumit Construction, Contract Started: 7/17/09; Peotone-Joliet Rd. Contract No.: 60D65, Awarded 4/22/09, Contractor: D Construction, Contract Started: 7/20/09 (Marisa Kollias, IL DOT, August 3, 2009) Received Notice to Proceed 05/15/2009 (U.S. DOT, July 17, 2009) | Lorig Construction, Areatha Construction, Herlihy-Mld Continent Construction, Sumit Construction, D Construction (Marisa Kollias, IL DOT, August 3, 2009) | NA (Marisa Kollias, IL DOT, August 3, 2009) |
| Illinois, Du Page | E OF I-355 (VETERAN'S TOLLWAY) TO WARWICK AVE Funds Allocated: $2,535,235
|
Awarded 4/20/09. Started 5/2009, expected to end by 9/30/2009 (IDOT Web site) Contract No: 60A85, Awarded 4/20/09, Contract started: 5/1/09 (Marisa Kollias, IL DOT, August 3, 2009) | Central Blacktop Co. Inc. | Could not find this information online or through Central Blacktop. Stephen Mosz, accountant for Central Blacktop, said on 7/29/2009: “It has added jobs and had an impact. In our industry, it’s mid-year, probably less than two months into work let by the stimulus package. To be honest with you it’s almost too early to answer that question.” (Interview with Katie Foutz, The Bolingbrook Sun) |
| Illinois, Cook | OVER STATE ST, RRS & GRAND CALUMET RIVER Funds Allocated: $3,770,183 |
Contract No: 60D74, Awarded 4/17/09. Contract started: 5/6/09 (Marisa Kollias, IL DOT, August 3, 2009) Received Notice to Proceed 05/04/2009 (U.S. DOT, July 17, 2009) | Albin Carlson & Co. (Marisa Kollias, IL DOT, August 3, 2009) | |
| Illinois, Cook | 3.61m of patching, resurfacing & pvmnt marking on 31st St from Wolf Rd to IL 17, Villages of Westchester, Brookfield, LaGrange Pk Funds Allocated: $2,950,000 |
Contract No: 60F51. On 7/31/09 letting. Not Awarded Yet (Marisa Kollias, IL DOT, August 3, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Illinois, Lake | Construction engineering for Wilmot Road widening and resurfacing, Section 07-00080-00-WR Funds Allocated: $934,560
|
Contract No: 63124, Awarded 7/16/09 (Marisa Kollias, IL DOT, August 3, 2009) Received Notice to Proceed 06/12/2009 (U.S. DOT, July 17, 2009) | A. Lamp Concrete (Marisa Kollias, IL DOT, August 3, 2009) | |
| Illinois, Cook | Sidewalk improvement, brick paver sidewalk, pedestrian lighting & signing along FAP 347 (Roosevelt Rd) from Mannheim Road to * Funds Allocated: $268,960 |
Contract No: 63183, On 7/31/09 Letting. Not Awarded Yet (Marisa Kollias, IL DOT, August 3, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Illinois, Cook | Resurface FAU 1642 (99th St) from Oak Park Avenue to Ridgeland Avenue in Chicago Ridge in Cook County. Funds Allocated: $500,000 |
Contract No.: 63201, On 7/31/09 letting. Not Awarded Yet (Marisa Kollias, IL DOT, August 3, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Illinois, Cook | 87TH ST TO 91ST ST Funds Allocated: $500,000 |
Item withdrawn from letting(Marisa Kollias, IL DOT, August 3, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Illinois, Sangamon | MEADOWLARK DR TO 1ST ST IN SPRINGFIELD Funds Allocated: $818,311 |
This job is complete. (IL DOT spokeswoman Marisa Kollias) Received Notice to Proceed 04/23/2009 (U.S. DOT, July 17, 2009) | ||
| Illinois, Winnebago | WHITMAN ST TO WALNUT ST IN ROCKFORD NORTHBOUND AND SOUTHBOUND Funds Allocated: $610,289 |
"The Winnebago County project on IL 251 from Walnut to Whitman was completed in July. " (IL DOT spokeswoman Marisa Kollias) Received Notice to Proceed 04/23/2009 (U.S. DOT, July 17, 2009) | ||
| Illinois, Cumberland | WEST SIDE OF COURTHOUSE SQUARE IN TOLEDO TO CUMBERLAND ST IN GREENUP Funds Allocated: $1,464,670 |
Received Notice to Proceed 04/23/2009 (U.S. DOT, July 17, 2009) | ||
| Illinois, Iroquois | N OF THAWVILLE TO I-57 AT ONARGA Funds Allocated: $861,786 |
L 54 Started 7/15/09, 90% complete as of 8/8/09. (IL DOT spokeswoman Marisa Kollias) Received Notice to Proceed 04/28/2009 (U.S. DOT, July 17, 2009) | L 54 Started 7/15/09, 90% complete as of 8/8/09. (IL DOT spokeswoman Marisa Kollias) | |
| Illinois, Rock Island | 16TH ST TO S OF I-280 IN ROCK ISLAND Funds Allocated: $4,449,013 |
Received Notice to Proceed 04/28/2009 (U.S. DOT, July 17, 2009) | ||
| Illinois, Iroquois | US 24 TO MILFORD RD Funds Allocated: $2,185,660 |
Started on 6/8/09, 99.5% complete as of 8/8/09.(IL DOT spokeswoman Marisa Kollias) Received Notice to Proceed 04/28/2009 (U.S. DOT, July 17, 2009) | ||
| Illinois, Mclean | W OF MCLEAN ST IN GRIDLEY TO W OF I-55 Funds Allocated: $1,688,139 |
"The US-24 project from Mclean Street in Gridley to west of I-55 in McLean county was started on May 4th and the last day of work on the project was June 10th. " (IL DOT spokeswoman Marisa Kollias) Received Notice to Proceed 04/28/2009 (U.S. DOT, July 17, 2009) | ||
| Illinois, Stephenson | JODAVIESS CO LINE TO REES RD Funds Allocated: $1,733,973 |
Received Notice to Proceed 05/04/2009 (U.S. DOT, July 17, 2009) | ||
| Illinois, Cook | OVER STATE ST, RRS & LITTLE CALUMET RIVER Funds Allocated: $605,580 |
Received Notice to Proceed 05/05/2009 (U.S. DOT, July 17, 2009) | ||
| Illinois, Madison | Preliminary engineering for the milling and resurfacing of Madison Ave. in Edwardsville. Section 09-00099-00-RS Funds Allocated: $34,000 |
Received Notice to Proceed 06/18/2009 (U.S. DOT, July 17, 2009) | ||
| Illinois, Cook | THORNDALE AVE (ELGIN-O'HARE EXPY) TO GRAND AVE & I-88 (E-W TOLLWAY) TO I-90/94 (KENNEDY EXPY) Funds Allocated: $5,100,000
|
This project is still in Phase II. Contract not Awarded or Let Yet (Marisa Kollias, IL DOT, August 3, 2009) Received Notice to Proceed 05/18/2009 (U.S. DOT, July 17, 2009) | ||
| Illinois, Madison | HUMBERT RD Funds Allocated: $7,590,000
|
Issued Notice to Proceed 7/16/2009 (US DOT, August 7 2009) | X | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Illinois, White | Shape eroded slopes and place riprap along FAS 887 (CH 7) north of IL 141 north for 1.00 mile in White County. Funds Allocated: $300,757 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Illinois, Grundy | Resurface various FAU Routes in the City of Morris - total of 1.61 miles, FAU 5966 (Lisbon Rd), FAU 5967 (Lisbon St), ** Funds Allocated: $360,796 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Illinois, Mcdonough | Resurfacing on US 136 (Jackson Street) from west of Ward Street to west of Johnson Street in Macomb in McDonough County. Funds Allocated: $350,000 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Illinois, Jackson | Resurfacing of various streets in the city of Carbondale Section 09-00125-00-RS Funds Allocated: $455,000 |
Issued Notice to Proceed 7/30/2009 | X | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Illinois, Winnebago | Resurface FAU 9878 (E. Union Street) from Illinois Route 75 to Aspland Drive in the Village of Rockton in Winnebago County. Funds Allocated: $497,697 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Illinois, Winnebago | Resurface FAU 5036 (Windsor Rd) from Alpine Rd to Forest Hills Rd & FAP 525 (Riverside Blvd) from Rock Rvr to IL 251 in Loves Park Funds Allocated: $530,000 |
"The Rock Island project on IL 92 from 16th to I-280 did not start until late July." (IL DOT spokeswoman Marisa Kollias) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Illinois, Stark | Bridge replacement for the structure carrying CH 23 over Jack Creek, 4 miles northeast of Toulon in Stark County. Funds Allocated: $184,642 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Illinois, Henderson | N of Ellison Creek to S of TR 163 Funds Allocated: $415,000 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Illinois, Effingham | Resurface FAS 711 (CH 25) & construct aggregate shoulders from TR 257 north for 4.11 miles in Effingham Co. Funds Allocated: $361,611 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Illinois, Kane | Construction of four new structures, two to carry Stearns Rd. over Brewster Creek, and two new underpasses, contract 3 Section 06-00214-15-BR Funds Allocated: $1,100,000 |
Issued Notice to Proceed 7/27/2009 | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Indiana, Lawrence | US-50 - EB bridge over East Fork White River Funds Allocated: $107,236 |
Advertised 6/3/2009. Awarded 7/1/2009. (Indiana FHWA 1585 Report, July 10 submittal) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Sims and Pedigo Company Inc. (Indiana FHWA 1585 Report, July 10 submittal) | NA |
| Indiana, Tippecanoe | SR 25, NEW BRIDGE CONSTRUCTION, OVER CR 900N (NB), SEGMENT 1-PHASE B, TIPPECANOE COUNTY, SIR-30843 Funds Allocated: $1,025,635 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | NA |
| Indiana, Wayne | SR-227 - From CSX R/R to US 27 Funds Allocated: $514,000 |
Advertised 6/03/09. Issued Notice to Proceed 7/01/09. (Indiana FHWA 1585 Report, July 10 submittal) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Milestone Contractors LP. (Indiana FHWA 1585 Report, July 10 submittal) | NA |
| Indiana, Warren | SR-263 - Redwood Creek Funds Allocated: $562,438 |
Advertised 6/3/09. Awarded 7/1/09. (Indiana FHWA 1585 Report, July 10 submittal) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | His Constructors LLC (Indiana FHWA 1585 Report, July 10 submittal) | NA |
| Indiana, Lake | US-20 - from SR 912 to Bridge Street Funds Allocated: $61,884 |
Advertised 6/3/09. Awarded 7/1/09. (Indiana FHWA 1585 Report, July 10 submittal) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Moonrock Inc (Indiana FHWA 1585 Report, July 10 submittal) | NA |
| Indiana, Owen | SR-243 - 1.20 miles N of SR 42 Funds Allocated: $759,974 |
Advertised 6/3/09. Awarded 7/1/09. (Indiana FHWA 1585 Report, July 10 submittal) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Henderson H E Inc. (Indiana FHWA 1585 Report, July 10 submittal) | NA |
| Indiana, Gibson | SR-168 - US 41 to SR 57 Funds Allocated: $1,986,397 |
Advertised 6/3/09. Awarded 7/1/09. (Indiana FHWA 1585 Report, July 10 submittal) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | J H Rudolph & Company. (Indiana FHWA 1585 Report, July 10 submittal) | NA |
| Indiana, Posey | SR-69 - 2.48 mi S of W jct with SR 66 to 0.1 mi N of I-64 Funds Allocated: $1,765,000 |
Advertised 6/3/09. Awarded 7/1/09. (Indiana FHWA 1585 Report, July 10 submittal) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Gohmann Asphalt & Construction (Indiana FHWA 1585 Report, July 10 submittal) | NA |
| Indiana, Lake | US-41 - from Huehn St to 0.25 mi N of Sheffield Ave Funds Allocated: $19,081 |
Advertised 6/3/2009. Awarded 7/1/2009. (Indiana FHWA 1585 Report, July 10 submittal) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Moonrock Inc. (Indiana FHWA 1585 Report, July 10 submittal) | NA |
| Indiana, Statewide | SR 44 - From I-65 to the WCL of Shelbyville Funds Allocated: $26,276 |
Construction awarded. Advertised 4/01/09. Awarded 5/07/09. Issued Notice to Proceed 5/12/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 05/12/2009 (U.S. DOT, July 17, 2009) | Rieth Riley Construction (Indiana Monthly Employment Summary Report, June, IN DOT) | NA (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, St Joseph | US 20 - Bridge (Over US 20) under Locust Rd, 0.99 mile E of SR 23 Funds Allocated: $3,054,834 |
Construction started. (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | LaPorte Construction Co. (Indiana Monthly Employment Summary Report, June, IN DOT) | 4 employees and 182 hours worked as of June 30, 2009 (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Benton | US 41 - NB & SB Bridge over KB and S RR and US 52 EB, 2.45 miles N of SR 18 Funds Allocated: $1,825,001 |
Construction started. Advertised 2/27/09. Awarded 3/25/09. Issued Notice to Proceed 4/29/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 04/29/2009(U.S. DOT, July 17, 2009) | Wirtz & Yates Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | 53 employees, 3,398 hours (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Dubois | SR 164 - From US 231 to 0.47 mi E of US 231 Funds Allocated: $196,282 |
Construction started. Advertised 2/27/09. Awarded 3/25/09. Issued Notice to Proceed 4/30/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 04/29/2009 (U.S. DOT, July 17, 2009) | Calcar Paving Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | 24 employees, 557 hours as of June 30, 2009 (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Marshall | SR 10 - Bridge over Clarence Baker Ditch, 0.6 mile E of SR 331 Funds Allocated: $243,248 |
Construction started. Advertised 2/27/09. Awarded 4/14/09. Issued Notice to Proceed 4/17/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 04/17/2009 (U.S. DOT, July 17, 2009) | R.L. McCoy, Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | NA (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Statewide | I-74 - Various locations Funds Allocated: $588,801 |
Construction started. Advertised 2/27/09. Awarded 4/15/09. Issued Notice to Proceed 4/29/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 04/29/2009 (U.S. DOT, July 17, 2009) | C-Tech Corporation Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | 38 employees, 1,885 hours worked as of June 30, 2009 (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Statewide | Various -At various locations in Lake and Porter Counties Funds Allocated: $283,824 |
Construction started. Advertised 2/27/09. Awarded 4/8/09. Issued Notice to Proceed 4/29/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 04/29/2009 (U.S. DOT, July 17, 2009) | TGB Unlimited Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | 8 employees and 478 hours worked as of June 30, 2009 (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Statewide | I-70 - Various locations in Vigo, Hendricks and Morgan counties Funds Allocated: $1,157,982 |
Construction started. Advertised 2/27/09. Awarded 5/28/09. Issued Notice to Proceed 6/10/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 06/10/2009 (U.S. DOT, July 17, 2009) | C-Tech Corporation Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | 8 employees, 244 hours worked as of June 30, 2009 (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Tippecanoe | US 52 - E side of SR 443 bridge at Happy Hollow Road Funds Allocated: $44,866 |
Construction started. Advertised 2/27/09. Awarded 6/04/09. Issued Notice to Proceed 6/09/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 06/09/2009 (U.S. DOT, July 17, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Slusser's Green Thumb Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | 1 employee, 0 hours worked as of June 30, 2009 (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Noble | SR 9 - N&S of SR 8 and on SR 8 from SR 9 in Albion Funds Allocated: $557,627 |
Construction started. Advertised 2/6/09. Awarded 3/27/09. Issued Notice to Proceed 3/31/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 03/31/2009 (U.S. DOT, July 17, 2009) | E&B Paving Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | 26 employees and 1,556 hours worked as of June 30, 2009 (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Statewide | SR 44 - From I-65 to the WCL of Shelbyville Funds Allocated: $13,291,724 |
Construction started. Advertised 4/1/09. Awarded 5/7/09. Issued Notice to Proceed 5/12/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 05/12/2009 (U.S. DOT, July 17, 2009) | Rieth Riley Construction (Indiana FHWA 1585 Report, July 10 submittal) | |
| Indiana, De Kalb | I-69 - Various locations along I-69 median in Dekalb County Funds Allocated: $378,654 |
Construction started. Advertised 4/1/09. Awarded 5/7/09. Issued Notice to Proceed 5/16/09 (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 05/16/2009 (U.S. DOT, July 17, 2009) | RMD Holdings Ltd. (Indiana Monthly Employment Summary Report, June, IN DOT) | NA (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Howard | US 31, NEW ROAD CONSTRUCTION, FROM 2.5 MI S OF SR 22/US 35 TO 0.5 MI S OF SR 22/US 35, HOWARD COUNTY, SIR-30106 Funds Allocated: $8,764,930 |
Construction started. Advertised 4/27/09. Awarded 5/28/09. Issued Notice to Proceed 6/1/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 06/01/2009 (U.S. DOT, July 17, 2009) | PRIMCO Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | NA (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Statewide | VARIOUS LOCATIONS, PAVEMENT MARKINGS, IN THE LAPORTE DISTRICT, ST-31880 Funds Allocated: $346,986 |
Construction started. Advertised 4/27/09. Awarded 5/28/09. Issued Notice to Proceed 6/19/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 06/19/2009 (U.S. DOT, July 17, 2009) | Airmarking Company Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | NA (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Noble | US 33, ADDED TRAVEL LANES WITH TURN LANES, AT SR 109 (EB TURN LANE WITH WB PASSING LANE), NOBLE COUNTY, SR-30183 Funds Allocated: $561,750 |
Construction started. Advertised 4/2709. Awarded 6/12/09. Issued Notice to Proceed 6/22/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 06/22/2009 (U.S. DOT, July 17, 2009) | API Construction Corp. (Indiana Monthly Employment Summary Report, June, IN DOT) | NA (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Tippecanoe | SR 25, NEW BRIDGE CONSTRUCTION, OVER CR 900N (SB), SEGMENT 1-PHASE B, TIPPECANOE COUNTY, SIR-30843 Funds Allocated: $893,653 |
Construction started. Advertised 4/29/09. Awarded 5/28/09. Issued Notice to Proceed 6/15/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 06/15/2009 (U.S. DOT, July 17, 2009) | Crider & Crider Inc. (Indiana Monthly Employment Summary Report, June, IN DOT) | NA (Indiana Monthly Employment Summary Report, June, IN DOT) |
| Indiana, Starke | US 35, SMALL STRUCTURE REPLACEMENT, 0.01 MI S OF N JCT WITH SR 8, OVER LARAMORE DITCH, STARKE COUNTY, SR-29588 Funds Allocated: $793,700 |
Construction started. Advertised 4/29/09. Awarded 5/28/09. Issued Notice to Proceed 6/4/09. (Indiana FHWA 1585 Report, July 10 submittal) Received Notice to Proceed 06/04/2009 (U.S. DOT, July 17, 2009) | GARIUP CONSTRUCTION CO INC (IN DOT, August 4, 2009, Will Wingfield) | |
| Indiana, Clark | I -65 - Riverside Dr & Market St Funds Allocated: $1,020,000 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | NA |
| Iowa, Lee | AT ONE LOCATION ON US 61 (FORT MADISON BY-PASS) JUST S. OF BLUFF ROAD Funds Allocated: $299,530 |
Awarded. | Bloomfield Bridge & Culvert, Inc. (Iowa DOT, June Monthly Employment Summary Report) | NA (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Appanoose | J18: Rathbun Lake Multi-Use Trail-Culvert Extension at Highway J18 and Ham Creek, Trail Construction Funds Allocated: $150,000 |
Awarded. No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | DeLong Construction, Inc. (Iowa DOT, June Monthly Employment Summary Report) | NA (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Story | S14: Hwy 30 to 1st Street, Pavement Rehab Funds Allocated: $245,333 |
Awarded. Received Notice to Proceed 05/27/2007 (U.S. DOT, July 17, 2009) | Manatt's, Inc. | NA (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Madison | FAS: PAVEMENT RESURFACING/REHAB ON FAS ROUTES P53 AND G4R, Pavement Rehab Funds Allocated: $569,170 |
Awarded. Received Notice to Proceed 06/03/2009 (U.S. DOT, July 17, 2009) | Henningsen Construction, Inc. (Iowa DOT, June Monthly Employment Summary Report) | NA (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Iowa | F-67: 325th St (F67) HMA Resurface w CIPR & H Ave (V52) subdrain, Pavement Rehab Funds Allocated: $773,396 |
Awarded. Received Notice to Proceed 06/16/2006 (U.S. DOT, July 17, 2009) | L.L. Pelling Co, Inc. (Iowa DOT, June Monthly Employment Summary Report) | NA (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Polk | 75th St: 75th St to Hwy 163, Traffic Signals Funds Allocated: $750,000 |
Awarded. Received Notice to Proceed 06/16/2009 (U.S. DOT, July 17, 2009) | Elder Corporation (Iowa DOT, June Monthly Employment Summary Report) | NA (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Jefferson | Kirkwood Ave: 5th Street to 2nd Street, Pavement Rehab Funds Allocated: $344,000 |
Awarded. Received Notice to Proceed 06/24/2009 (U.S. DOT, July 17, 2009) | Vieth Construction Corporation (Iowa DOT, June Monthly Employment Summary Report) | NA (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Union | US 169 From Ringgold Co. Line N. To Afton Funds Allocated: $3,202,870 |
Awarded. Received Notice to Proceed 07/10/2009 (U.S. DOT, July 17, 2009) | Henningsen Construction, Inc. (Iowa DOT, June Monthly Employment Summary Report) | NA (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Clinton | Z2E: Charlotte to E-63, Pavement Rehab Funds Allocated: $524,593 |
Construction started. Awarded. | Mathy Construction Co. (contractor) River City Paving (subcontractor) | 3 employee, 11 hours through June (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Mills | S.B & N.B. I-29 OVER SAINT MARYS CREEK 0.9 MI. S. OF IA 370 Funds Allocated: $1,726,111 |
Construction started. Awarded. Received Notice to Proceed 03/06/2009 (U.S. DOT, July 17, 2009) | Western Engineering, Co. (Iowa DOT, June Monthly Employment Summary Report) | 10 employees, 510 hours worked through June (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Osceola | From E. Of Reloc. Ia. 60 E. To W. Of E. Jct. Co. Rd. L-58 Funds Allocated: $4,865,289 |
Construction started. Awarded. Received Notice to Proceed 03/30/2009 (U.S. DOT, July 17, 2009) | Flynn Company, Inc. | 106 employee, 2885 hours worked through June (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Clarke | From Decatur Co. Line N. To US 34(SBL) Funds Allocated: $15,304,219 |
Construction started. Awarded. Received Notice to Proceed 03/30/2009 (U.S. DOT, July 17, 2009) | Manatt's, Inc. (Iowa DOT, June Monthly Employment Summary Report) | 104 employees, 8378 hours worked through June (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Chickasaw | From ECL New Hampton E. To W. Jct. Co. Rd. V-56 In Lawler Funds Allocated: $3,200,829 |
Construction started. Awarded. Received Notice to Proceed 04/03/2009 (U.S. DOT, July 17, 2009) | Mathy Construction, Co. (Iowa DOT, June Monthly Employment Summary Report) | 35 employees, 1065 hours worked through June (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Polk | NW/NE 118 Ave: Polk City Limits to NE 14 St, Pavement Rehab Funds Allocated: $1,950,000 |
Construction started. Awarded. Received Notice to Proceed 05/06/2009 (U.S. DOT, July 17, 2009) | OMG Midwest Inc. (contractor) Des Moines Asphalt & Paving (subcontractor) (Iowa DOT, June Monthly Employment Summary Report) | 26 employees, 426 hours worked through June (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Buchanan | D-22: Independence to Jesup, Pavement Rehab/Widen Funds Allocated: $1,730,000 |
Construction started. Awarded. Received Notice to Proceed 05/13/2009 (U.S. DOT, July 17, 2009) | Flynn Company, Inc. (Iowa DOT, June Monthly Employment Summary Report) | 34 employees, 1147 hours worked through June (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Wapello | H21, J12, H31, V17: H21 Blackhawk north, J12 65th St to 110th Ave, H31 100th St to V37, V17 CL to 30th St, Pavement Rehab Funds Allocated: $375,619 |
Construction started. Awarded. Received Notice to Proceed 05/15/2009 (U.S. DOT, July 17, 2009) | Norris Asphalt Paving Co. (Iowa DOT, June Monthly Employment Summary Report) | 1 employee, 1 hour worked through June (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Plymouth | K-30: C-12 to N 1 MILE, Grading Funds Allocated: $125,000 |
Construction started. Awarded. Received Notice to Proceed 06/05/2009 (U.S. DOT, July 17, 2009) | Knife River Midwest, LLC. (Iowa DOT, June Monthly Employment Summary Report) | 1 employee, 26 hours worked through June (Iowa DOT, June Monthly Employment Summary Report) |
| Iowa, Adams | N26: US Highway 34 to Town of Nodaway, Pavement Rehab Funds Allocated: $217,179 |
Advertised | NA | |
| Iowa, Polk | US 69: IA 160 to 1st Street, Pavement Rehab Funds Allocated: $1,000,000 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Kansas, Greenwood | RS-291 FROM HAMILTON TO VIRGIL Funds Allocated: $490,000 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Kentucky, Monroe | TOMPKINSVILLE - KY-90 (PRIORITY SECTION 1): FROM 0.34MI SOUTH OF BUSHONG ROAD EXTENDING NORTHERLY TO 0.68MI SOUTH OF CYCLONE ROAD (GRADE DRAIN & INC. SURFACE). (02CCR)(2002BOP)(SEE 3-276.11 FOR 2005HP Funds Allocated: $9,590,000 |
Construction started. Awarded. (KY DOT Monthly Employment Summary Report, June) | Scotty's Contracting (KY DOT Monthly Employment Summary Report, June) | 12 employees, 238 hours worked through June (KY DOT Monthly Employment Summary Report, June) |
| Kentucky, Carroll | POLK STREET EXTENSION PROJECT - PROJECT WILL ENABLE STUDENTS TO WALK OR BICYCLE TO 4 AREA SCHOOLS VIA SIDEWALK CONSTRUCTION,TRAFFIC CALMING MEASURES AND PEDESTRIAN AND BICYCLE CROSSING IMPROVEMENTS. Funds Allocated: $247,000 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Kentucky, Union | MORGANFIELD WALKING AND BICYCLE TRAIL - ADD BICYCLE RACKS AND SIGNAGE, DESIGNATION OF BICYCLE LANES CONSTRUCTION OF BICYCLE AND WALKING TRAIL SYSTEM AND AESTHETIC IMPROVEMENTS. Funds Allocated: $55,500 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Kentucky, Shelby | HOSPITAL DRIVE SIDEWALK PROJECT - CONSTRUCTION OF 1700 LINEAR FEET OF SIDEWALK WITH CURB AND GUTTERING ALONG HOSPITAL DRIVE. THE NEW SIDEWALKS WILL CONNECT WITH US 60 SIDEWALKS. Funds Allocated: $103,500 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Kentucky, Madison | TATES CREEK TRAIL PROJECT- CONSTRUCT A SIDEWALK ALONG THE OLD ABANDONED RINEY B RAIL THAT RUNS ALONG KY 169. Funds Allocated: $157,500 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Louisiana, Lafourche | Construction of a new vertical life bridge to replace a 55 yr. old pontoon bridge Funds Allocated: $32,878,408 |
Let 3/18/09, awarded 3/31/09, Notice to Proceed issued 6/15/09, work began mid-July. Stimulus funds obligated changed to $37,067,216.83. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | James Construction Group. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | 66 hours since work began mid-July. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) |
| Louisiana, West Carroll | Bridge Replacement Project Funds Allocated: $412,700 |
Let 4/29/09, awarded 5/06/09. Notice to Proceed should be issued by mid-August. Stimulus funds obligated changed to $543,460.34. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | CW&W Contractors. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | NA. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) |
| Louisiana, Jackson | Rehabilitation of two existing lanes on TIMED 4-lane project Funds Allocated: $5,178,546 |
Let 5/20/09, awarded 6/8/09. Notice to Proceed will be issued 8/1/09. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) * Stimulus funds obligated reduced to $3,303,711.89. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | D&J Construction. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | NA. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) |
| Louisiana, Jefferson | Intersection modification Funds Allocated: $68,575,860 |
Let 6/17/09, awarded 7/14/09, and Notice to Proceed expected to be issued by mid-August. * Stimulus funds obligated changed to $56,194,317.50 (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | James Construction Group. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | NA. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) |
| Louisiana, Orleans | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs Funds Allocated: $1,575,665 |
Let 6/24/09, awarded 7/14/09. Stimulus funds obligated changed to $2,192,674.30. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | Boh Bros. Construction. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | NA. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) |
| Louisiana, Orleans | Construction of sidewalks, shared use bike lanes, dedicated use bike lanes, landscaping (trees), stiping, symbols, signs Funds Allocated: $998,661 |
Let 7/29/09. * Stimulus funds obligated changed to $524,264.28. (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | NA (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) | NA (Amber Hebert, Public Information Officer, LA DOT, July 31, 2009) |
| Maine, Cumberland | Intersection Improvement with signal: Located at the intersection of Auburn Street and Lyseth Moore Drive. Funds Allocated: $224,761 |
Awarded (ME DOT) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Maine, Kennebec | Highway Resurfacing: Beginning at Route 11 and extending northerly 1.16 miles. Funds Allocated: $368,114 |
Construction began 04/27/09 (ME DOT). Awarded 04/04/09 (ME DOT, Brad Foley, August 3, 2009) Received Notice to Proceed 04/08/2009 (U.S. DOT, July 17, 2009) | Pike Industries (ME DOT, Brad Foley, August 3, 2009) | 1,224 hours through June 30, 2009 (Buddy Spaulding, ME DOT, August 3, 2009) |
| Maine, Kennebec | Highway Resurfacing: Beginning 0.03 of a mile northerly of Greeley Street and extending northerly 0.85 of a mile to 0.30 of a mile northerly of Municipal Drive. Funds Allocated: $173,248 |
Construction began 04/27/09 (ME DOT). Awarded 4/08/09 (ME DOT, Brad Foley, August 3, 2009). Received Notice to Proceed 04/08/2009 (U.S. DOT, July 17, 2009) | Pike Industries (ME DOT, Brad Foley, August 3, 2009) | 254 hours through June 30, 2009 (Buddy Spaulding, ME DOT, August 3, 2009) |
| Maine, Waldo | Bridge Replacement: Knights Hill Bridge(# 3194) over Meservy Brook and located 0.17 of a mile northerly of Route 173. Funds Allocated: $265,000 |
Construction began 06/04/09 (ME DOT) Received Notice to Proceed 05/21/2009 (U.S. DOT, July 17, 2009) | N F Luce, Inc (Bradford Foley, WA DOT, August 3, 2009) | 3 hours through June 30, 2009 (Buddy Spaulding, ME DOT, August 3, 2009) |
| Maine, Penobscot | Highway Resurfacing: Beginning 325' easterly of the I-95 northbound Exit 185 ramps and extending northerly 0.23 of a mile to the I-95 southbound Exit 185 ramps. Funds Allocated: $89,609 |
Construction began 07/25/09 (ME DOT). Awarded 4/13/09 (ME DOT, Brad Foley, August 3, 2009). Received Notice to Proceed 04/13/2009 (U.S. DOT, July 17, 2009) | Vaughn Thibodeau & Sons (ME DOT, Brad Foley, August 3, 2009) | 0 hours through June 30, 2009 (Buddy Spaulding, ME DOT, August 3, 2009) |
| Maine, Hancock | Bridge Substructure Rehabilitation: Sedgwick Bridge (#3257) over Eggemoggin Reach, located on the Deer Isle-Sedgwick town line. Funds Allocated: $8,571,897
|
Maine DOT advertised for bids on the $8M-plus project (#3257) to repair the concrete supports on the Sedgwick Bridge in June, but due to the technical and insurance requirements of the project (namely the need for trained divers) no contractors came back with a bid. DOT is restructuring the project to make bids more likely and will advertise the project again in August. [July 22, 2009] | NA | NA |
| Maryland, Statewide | Sidewalks Funds Allocated: $2,302,300
|
Construction started. Advertised 2/10/09, awarded 6/09/09, and issued Notice to Proceed 6/23/09. As of June 30, 2009 47% of the project had been completed. (MD DOT, Monthly Status Report, June) | American Infrastructure, MD (MD DOT, Monthly Status Report, June) | NA (MD DOT, Monthly Status Report, June) |
| Maryland, Statewide | Sidewalks Funds Allocated: $1,794,107
|
Construction started. Advertised 2/10/2009, awarded 4/212009. As of June 30, 2009 MD DOT says project is 59% complete. (MD DOT, Monthly Status Report, June) | Keystone Lime Co., Inc. (MD DOT, Monthly Status Report, June) | NA (MD DOT, Monthly Status Report, June) |
| Maryland, Cecil | Ridesharing Facilities Funds Allocated: $457,455
|
Construction started. Advertised 2/24/09, awarded 5/11/09, and issued a Notice to Proceed 6/22/09. As of June 30, 2009 it was 11% complete. Scheduled completion date is 12/2009. (MD DOT, Monthly Status Report, June) | Bardon Inc. (contractor) Aggregate Industries (subcontractor) (MD DOT, Monthly Status Report, June) | NA (MD DOT, Monthly Status Report, June) |
| Maryland, Statewide | Guardrail Funds Allocated: $339,768
|
Construction started. Advertised 2/24/2009, awarded 4/9/2009 to L.S. Lee, Inc. and Notice to Proceed issued 6/9/2009. As of June 30, 2009 MD DOT reports it's 22% complete. 12/2011 is the scheduled completion date. | L.S. Lee, Inc | NA (MD DOT, Monthly Status Report, June) |
| Maryland, Statewide | Landscaping Funds Allocated: $194,499
|
Construction started. Advertised 3/3/09, awarded 5/11/09, and issued Notice to Proceed 6/15/2009. MD DOT estimates project is 21% complete. (MD DOT, Monthly Status Report, June) Received Notice to Proceed 06/15/2009 (U.S. DOT, July 17, 2009) | American Paving Corp (MD DOT, Monthly Status Report, June) | NA (MD DOT, Monthly Status Report, June) |
| Maryland, Allegany | Resurfacing Funds Allocated: $2,297,378
|
Construction started. Advertised 3/3/2009, awarded 5/11/2009 and Notice to Proceed issued 6/9/2009. As of June 30, 2009 it was 6% complete.(MD DOT, Monthly Status Report, June) Notice to Proceed delivered 6/9/2009 (U.D. DOT July 17, 2009 reports the same). | L.S. Lee, Inc. (MD DOT, Monthly Status Report, June) | NA (MD DOT, Monthly Status Report, June) |
| Maryland, Baltimore City | Rehabitation Funds Allocated: $10,886,546
|
It was advertised 2/27/2009, awarded 5/27/2009, but has not yet been given a Notice to Proceed. (MD DOT, Monthly Status Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA (MD DOT, Monthly Status Report, June) | NA (MD DOT, Monthly Status Report, June) |
| Maryland, Prince Georges | MD 212 @ ALLVIEW DRIVE / EVANS TRAIL - WIDEN & RESURFACE Funds Allocated: $1,744,696
|
Not awarded (MD DOT, Monthly Status Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA (MD DOT, Monthly Status Report, June) | NA (MD DOT, Monthly Status Report, June) |
| Massachusetts, Barnstable | The purpose of this project is to resurface the Bourne Route 6 Scenic Highway from the intersection with Nightingale Pond Road to just east of the intersection with Bourndale Road. Funds Allocated: $1,805,110
|
Construction has begun (Wendey, District 5, MA Ex. Office of Transportation). Received Notice to Proceed 04/23/2009 (U.S. DOT, July 17, 2009) | P.A. Landers, Inc. | NA |
| Massachusetts, Hampshire | ERP-001S(934)X, Easthampton-Greenfield-Northampton-Southampton-Westfield: Resurfacing & related work on Routes 5 and 10. Funds Allocated: $4,243,640
|
Notice to proceed issued May 21, 2009. Construction started July 21, 2009. | Warner Bros. LLC. Contract Awarded for $3,246,543 | Warner Bros. LLC was awarded four stimulus contracts to date. According to Jim Tudryn, a construction manager at Warner Bros. LLC, the company has hired 15 laborers and retained its workforce from last year to support that work. |
| Massachusetts, Berkshire | The project will begin at the Adams/Cheshire town boundary (MM 66.3) and will end just north of Commonwealth Avenue (MM 67.8) for a project length of approximately 1.5 miles. MassHighway will resurfac Funds Allocated: $2,199,456
|
Work began on April 22, 2009 and is currently 30% complete. (Colin Durrant, Dep. Press Sec., MA Ex. Office of Transportation) Received Notice to Proceed 04/23/2009 (U.S. DOT, July 17, 2009) | A. Pereira Construction of Ludlow, MA (Colin Durrant, Dep. Press Sec., MA Ex. Office of Transportation) | NA (Colin Durrant, Dep. Press Sec., MA Ex. Office of Transportation) |
| Michigan, Ottawa | Pin and Hanger Replacment Funds Allocated: $767,596 |
Advertised 5/1/09. Awarded 7/1/09. (Michigan, Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Anlaan Corporation. (Michigan, Monthly Summary Employment Report, June) | NA |
| Michigan, Oceana | Deck ptch, P/H, jts, subst rep Funds Allocated: $832,723 |
Advertised 6/05/09. (Michigan, Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Michigan, Oakland | Resurface Funds Allocated: $350,000 |
Advertised 6/12/009. (Michigan, Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Michigan, Wayne | Resurface road Funds Allocated: $360,000 |
Advertised 6/12/2009. (Michigan, Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Michigan, Saginaw | Resurface Funds Allocated: $1,794,668 |
Advertised 6/18/2009. (Michigan, Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Michigan, Branch | Single Course Chip Seal Funds Allocated: $85,200 |
Awarded 6/4/2009. (Michigan, Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Branch Co. Road Commission - Trenton J. Arver (Michigan, Monthly Summary Employment Report, June) | NA |
| Michigan, Washtenaw | Mill and two course overlay Funds Allocated: $16,359,686 |
Awarded. Advertised 5/15/2009. (Michigan, Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Rieth-Riley Construction Co., Inc. (Michigan, Monthly Summary Employment Report, June) | NA |
| Michigan, Muskegon | Resurface Funds Allocated: $503,211 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Michigan, Montcalm | Resurface Funds Allocated: $669,549 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Michigan, Washtenaw | Resurface road Funds Allocated: $210,000 |
Let July 10, 2009 | NA | |
| Michigan, Wexford | Bridge Replacement Funds Allocated: $233,642 |
Let July 10, 2009 | NA | |
| Michigan, Berrien | Red Arrow/Warren Woods/Shawnee Browntown Road to Sawyer Road Single Course Chip Seal Funds Allocated: $90,283 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Michigan, Lake | Single Course Chip Seal Funds Allocated: $93,367 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Michigan, Muskegon | Road Rehab; Add Roundabout Funds Allocated: $3,278,891 |
Issued Notice to Proceed 7/1/2009 | X | |
| Michigan, Oakland | Resurface, rehabilitate Funds Allocated: $415,000
|
Let July 10, 2009 | NA | |
| Michigan, Berrien | Reconstruction Funds Allocated: $309,925 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Michigan, Wayne | Deck Replacement Funds Allocated: $13,733,403 |
Let July 10, 2009 | NA | |
| Michigan, Saginaw | Barrier Rail Replacement Funds Allocated: $1,105,965 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Michigan, Alcona | Crack Relief Layer and Resurf Funds Allocated: $3,402,383 |
Received Notice to Proceed 05/01/2009 (U.S. DOT, July 17, 2009) | Rieth-Riley Construction Co. (Monthly Summary Employment Report May 2009, Michigan DOT) | 70 employees and 2,294 hours worked up to May 31, 2009 (Monthly Summary Employment Report May 2009, Michigan DOT) |
| Minnesota, Clay | MSAS 126 (20TH ST S): IN MOORHEAD, 12TH AV TO 24TH AV, URBAN GRADING & SURFACING Funds Allocated: $1,400,000
|
Advertised at the end of June, which means the letting will be late this month or early next month. (per Kevin Gutknecht on 7/30, Communications Director MnDOT, St. Paul office) | -- | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Minnesota, Hennepin | TH 7: AT WOODDALE AVE - CONST A GRADE SEPARATED INTERCHANGE, ETC & NEW BRIDGE #27B65 FR CP RR CR #5199 TO TH 100 SB Funds Allocated: $3,465,000
|
An Advertisement For Bids has been published and bids will be opened on August 13, 2009. A contract award is expected in early September with construction anticipated to commence shortly thereafter per the City of St. Louis Park's website and was confirmed by Kevin Gutknecht, Director of Communications at MnDOT | -- | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Minnesota, Blue Earth | CSAH 12: OVER DM&E RR, CONST NEW BR #07589 Funds Allocated: $4,065,812
|
Awarded 8/04/09. (Alan Forsberg, 8/05/09, Blue Earth County Director, MN) The County Committee recommended that the Blue Earth CSAH 12 project proposed for 2013 be moved to 2012 as backfill for the Noble CSAH 1 project that will be receiving recovery money. Also, the $100,000 CSAH 12 place holder money [07-612-10] should be added to this new Blue Earth CSAH project in 2012, bringing it to $1,426,000. The ATP approved these. It doesn't look like this project will begin until 2012. No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Lunda Construction Company. (Alan Forsberg, 8/05/09, Blue Earth County Director, MN) | NA |
| Minnesota, Clay | I-94: LANDSCAPING OF THE MOOREHEAD STATE ENTRY SIGN & LANDSCAPING Funds Allocated: $90,950
|
Awarded. Anticipated start date is September 28, completion anticipated mid-October. (per Kevin Gutknecht on 7/30, Communications Director, MnDOT / confirmed by contractor) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | K & L Landscape & Construction Inc (per Kevin Gutknecht on 7/30, Communications Director, MnDOT) | Most likely no new hires, because it is a small job. (Christine Brandon on 8/3, accounting manager, K&L Landscape & Construction Inc) |
| Minnesota, Freeborn | I-35: STATE ENTRY SIGN LOCATION LANDSCAPE REHAB AT ALVERT LEA, NO OF IA/MN BORDER - ENTRY AND EXIT SIGNS Funds Allocated: $90,950
|
Awarded. Estimated start date August 25 (MNDOT, Kevin Gutknecht, 7/30) Received Notice to Proceed 07/02/2009 (U.S. DOT, July 17, 2009) | K & L Landscape and Construction Inc. (MN DOT Web site) | NA (MNDOT, Kevin Gutknecht, 7/30) The company will probably not hire anyone else for this job, because it is a small one. (per Christine Brandon, accounting manager, K&L Landscape and Construction Inc.) |
| Minnesota, Sibley | TH 93:FR TH 112 TO BR #9309 AT LESUEUR TO TH 169 - REPL CONCRETE PAVEMENT, MILL & OVLY, REPL EXP JOINTS & APPRO PANES FOR BR #72007 Funds Allocated: $437,312
|
Construction started May 11, completion anticipated in early August (MNDOT, Kevin Gutknecht, 7/30) Received Notice to Proceed 04/15/2009 (U.S. DOT, July 17, 2009) | Chard Tiling and Excavating (MN May Employment Summary Report) | No jobs were created at Chard, but they were able to hire two subcontractors for this project. The total number of employees working on this between the two subcontractors is seven. This information comes from their hiring reports (per Connie Chard on 7/30, Vice President, interview by Chelsey Perkins) |
| Minnesota, Morrison | CR 203: (330TH ST) FR TH 10 TO CSAH 2 - GR, AGG BASE, BIT SURF & AGG SHOULDERS Funds Allocated: $786,114
|
Started June 15, completion in early October (per Kevin Gutknecht on 7/30, Communications Director, MNDOT). Received Notice to Proceed 05/27/2009 (U.S. DOT, July 17, 2009) | Tri-City Paving (per Kevin Gutknecht on 7/30, Communications Director, MNDOT). | NA |
| Minnesota, Statewide | I-90: 0.1 MI E OF TH 22 INTCHG TO 0.4 MI W OF TH 109, CONC PVMT REHAB, RESURF SHLDRS Funds Allocated: $3,923,374
|
Started June 16, completion anticipated in September (per Kevin Gutknecht on 7/30, Communications Director, MNDOT). Started June 29 (C. P. R. Inc., August 4, 2009)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | C. P. R. Inc. (MN DOT Web site) | No information available at this time (per Kevin Gutknecht on 7/30, Communications Director, MNDOT). |
| Minnesota, Statewide | I-94: CSAH 75 TO 1.5 MI W OF TH 23 & STEARNS / WRIGHT CO LN TO TH 25, CONC PVMT REHAB / DIAMOND GRIND Funds Allocated: $6,312,466
|
Started May 11, anticipated completion in September(per Kevin Gutknecht on 7/30, Communications Director, MNDOT) | Diamond Surface, Inc. (per Kevin Gutknecht on 7/30, Communications Director, MNDOT) | Unable to obtain specific numbers by this point (per Kevin Gutknecht on 7/30, Communications Director, MNDOT) Project saved jobs within company, and allowed them to hire 25 additional workers for the duration of this project. (Interview with Kerry Kraemer, PResident, Diamond Surface, Inc. 8/05/09) |
| Minnesota, Statewide | TH 94: FR DOUGLAS / TODD CO LINE TO SAUK CENTRE - INSTALL HIGH TENSION CABLE MEDIAN BARRIER (GUARDRAIL) Funds Allocated: $1,551,326
|
Started May 4, anticipated completion in September (MNDOT, Kevin Gutknecht). Started the week ending May 16, completed the week ending July 25. (Contractor Bob Ronning, owner of H & R Construction). Received Notice to Proceed 04/10/2009 (U.S. DOT, July 17, 2009) | H & R Construction | From start to finish, this project accounted for 2600 hours worked. Anywhere from 7-10 employees were working on this project at a given time. The company hired 6 additional people in general, not as a direct result of this project. Employment at H & R is up 10%. They also hired more people back (no number), which wouldn't have been possible without stimulus projects. They've worked on other stimulus-funded projects in addition to this one. (per Bob Ronning on 7/30, owner of H & R Construction) |
| Minnesota, Freeborn | TH 90: FR W LIMITS ALDEN TO TH 13 - INSTALL HEAVY BIT OVLY ON I-90 (WB & UNBONDED CONCRETE OVLY ON I-90 (EB) Funds Allocated: $17,117,366
|
Started on May 11, projected completion date is September (per Kevin Gutknecht on 7/30, Communications Director, MnDOT). Received Notice to Proceed 05/11/2009 (U.S. DOT, July 17, 2009) | Ulland Brothers (per May 2009 Employment Summary, MnDOT) | Ulland Brothers has hired 14 subcontractors for this job. May: For both the prime and subcontractors, a total of 85 employees worked for 2,038 hours. June: Subcontractors had 75 employees working 3,400 hours. Prime contractor had 110 employees working 6,087.5 hours. (Per Valerie Nelson on 7/30, Assistant Controller; data came from the Trax system through MnDOT) Valerie stated that had the company not been awarded the contract for this project, they would have had to lay off people. She did not know what the anticipated number of lay offs would have been. She stated that this has been one of the main jobs they've worked on this summer. |
| Minnesota, Statewide | Pavement Preservation - North junction of 35E/35W to North of TH 8 - bituminous mill and overlay, includes CMPS aux. lane. Funds Allocated: $8,239,000
|
Work began August 3, 2009. (per Kevin Gutknecht on 7/30, Communications Director, MnDOT / confirmed by contractor) | Hardrives Inc. (MN DOT Web site) | No new jobs were created as a result of this project. However, employees that were hired back will be able to have full-time weeks, rather than most likely working only part time this summer. The number of employees this July is the same as last July for the company, but more hours are available. (per Bobbi Hahn on 8/3, HR Manager for Hardrives Inc.) |
| Mississippi, Franklin | US 84 FROM 7.5 MILES EAST OF ADAMS COUNTY LINE TO WEST END OF BUDE-MEADVILLE BYPASS IN FRANKLIN COUNTY. OVERLAY. Funds Allocated: $4,383,300 |
Advertised 03/09/2009; Let 03/24/2009; Awarded 03/25/09 (MS DOT, August 4, 2009); Received Notice to Proceed 03/31/2009 (U.S. DOT, July 17, 2009) | W.E. Blain & Sons, Inc. Mount Olive, MS (MS DOT, August 4, 2009) | 33382 hours worked through July 2009 (MS DOT, August 4, 2009) |
| Mississippi, Statewide | SR 8 Bolivar County Hospital to Ruleville Funds Allocated: $2,500,000 |
Advertised 05/04/2009; Let 05/26/2009; Awarded 06/09/09; Received Notice to Proceed 07/09/2009 (MS DOT, August 4, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Lehman-Roberts Company Memphis,TN (MS DOT, August 4, 2009) | NA (MS DOT, August 4, 2009) |
| Mississippi, Statewide | US 45 A FM THE S MON CL TO THE N MON CL Funds Allocated: $4,000,000 |
Advertised 05/04/2009; Let 05/26/2009; Awarded 06/09/09; Received Notice to Proceed 07/09/2009 (MS DOT, August 4, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | APAC-Mississippi Jackson, MS(MS DOT, August 4, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Mississippi, Forrest | US 49 from Edwards St. to 31st Avenue Funds Allocated: $9,544,300 |
Advertised 05/04/2009; Let 05/26/2009; Awarded 06/09/09; Received Notice to Proceed 07/09/2009 (MS DOT, August 4, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Dunn Roadbuilders, LLC Laurel, MS (MS DOT, August 4, 2009) | 80 hours worked through July 2009 (MS DOT, August 4, 2009) |
| Mississippi, Perry | SR 198 REPLACE BRIDGE 179.0 OVER DICKEY CREEK AT BEAUMONT Funds Allocated: $1,469,900 |
Advertised 05/04/2009; Let 05/26/2009; Awarded 06/09/09; Received Notice to Proceed 07/09/2009 (MS DOT, August 4, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Tanner Construction Company, Inc. Laurel, MS (MS DOT, August 4, 2009) | NA |
| Mississippi, Statewide | US 45 A FM WEST POINT TO 1 MI N OF SR 25 Funds Allocated: $4,000,000 |
Advertised 05/04/2009; Let 05/26/2009; Awarded 06/09/09; Received Notice to Proceed 07/09/2009 (MS DOT, August 4, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Falcon Contracting Company Columbus, MS (MS DOT, August 4, 2009) | NA |
| Mississippi, Jefferson Davis | SR 13 from 4.7 miles north of Marion CL to US 84 at Prentiss in Jefferson Davis County. Overlay Funds Allocated: $1,749,000 |
Advertised 05/04/2009; Let 05/26/2009; Awarded 06/09/09; Received Notice to Proceed 07/09/2009 (MS DOT, August 4, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | W.E. Blain & Sons, Inc. Mount Olive, MS (MS DOT, August 4, 2009) | NA |
| Mississippi, Tishomingo | SR 365 FM PRENTISS CL TO US 72 Funds Allocated: $1,548,700 |
Advertised 05/04/2009; Let 05/26/2009; Awarded 06/09/09; Received Notice to Proceed 07/09/2009 (MS DOT, August 4, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Mississippi, Attala | VAIDEN-FRENCH CAMP ROAD; KNOX CROSSING ROAD Funds Allocated: $1,375,600 |
NA (MS DOT, August 4, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Missouri, Clay | Thin lift overlay from the Clinton County line to Rte. 92. Funds Allocated: $260,300
|
Advertised 1/30/09, awarded 3/04/09, and issued Notice to Proceed 4/06/09. 0% completed as of June 30, 2009. (Missouri Monthly Summary Employment Report, June) Received Notice to Proceed 04/06/2009 (U.S. DOT, July 17, 2009) As of July 31, 2009 work has not yet begun on this project. Estimates indicate that monies for this project will support 7 direct, indirect and induced jobs. | Chester Bross Construction Co. (Missouri Monthly Summary Employment Report, June) | NA (Missouri Monthly Summary Employment Report, June) |
| Missouri, Ray | Thin lift overlay from Rte. U to Rte. 10. Funds Allocated: $182,000
|
Advertised 1/30/09, awarded 3/04/09, and issued Notice to Proceed 4/06/09. 0% completed as of June 30, 2009. (Missouri Monthly Summary Employment Report, June) Received Notice to Proceed 04/06/2009 (U.S. DOT, July 17, 2009) As of July 31, work has not begun on this project. Estimates indicate that monies for this project will support 5 direct, indirect and induced jobs. | Chester Bross Construction Co. (Missouri Monthly Summary Employment Report, June) | NA (Missouri Monthly Summary Employment Report, June) |
| Missouri, Bates | Convert at-grade intersection at Route 52 (south) to interchange as part of the upgrade to I-49. Funds Allocated: $5,096,700
|
Advertised 4/03/09, awarded 5/06/09, and issued Notice to Proceed 6/08/09. (Missouri DOT Monthly Summary Employment Report, June) Received Notice to Proceed 06/08/2009 (U.S. DOT, July 17, 2009) As of July 31, work has not begun on this project. Estimates indicate that monies for this project will support 147 direct, indirect and induced jobs. | Hilty Quarries Inc. (Missouri DOT Monthly Summary Employment Report, June) | NA (Missouri DOT Monthly Summary Employment Report, June) |
| Missouri, Boone | Thin lift overlay from Rte. 63 North Connector to Rte. Z. Funds Allocated: $290,000
|
As of July 2009, work has not started on this project. (Sally Oxenhandler, Community Relations Manager, Missouri Department of Transportation) | APAC | NA [It is estimated that monies for this project will support 8 direct, indirect and induced jobs. (Sally Oxenhandler, Community Relations Manager, Missouri Department of Transportation)] |
| Missouri, Greene | Thin lift overlay from Rte. 160 to Rte. 266. Funds Allocated: $281,100
|
Awarded (Missouri Monthly Summary Employment Report, June) | APAC-Missouri, Inc. (Missouri Monthly Summary Employment Report, June) | NA (Missouri Monthly Summary Employment Report, June) |
| Missouri, Howell | Asphalt mill and fill from Rte. 63 North to Broadway in West Plains. Funds Allocated: $506,000
|
Awarded. | Pace Construction Company, LLC (Missouri Monthly Summary Employment Report, June) | NA (Missouri Monthly Summary Employment Report, June) |
| Missouri, Lawrence | Thin lift overlay from Rte. 60 to 1.5 miles north of Rte. 248. Funds Allocated: $498,500
|
Completed. Advertised 1/30/09, awarded 3/04/09, and issued Notice to Proceed 4/06/09. (Missouri DOT Monthly Summary Employment Report, June) Received Notice to Proceed 04/06/2009 (U.S. DOT, July 17, 2009) This project began work on April 14, 2009. Estimates indicate that monies for this project will support 14 direct, indirect and induced jobs. | Leo Jounagan Construction Co (Missouri DOT Monthly Summary Employment Report, June) | NA (Missouri Monthly Summary Employment Report, June) |
| Missouri, Vernon | Thin lift overlay from Rte. 54 to Rte. F. Funds Allocated: $282,400
|
Completed. Advertised 1/30/09, awarded 3/04/09, and issued Notice to Proceed 5/04/09. (Missouri Monthly Summary Employment Report, June) Received Notice to Proceed 05/04/2009 (U.S. DOT, July 17, 2009) Work began on this project on April 18 and was complete on April 27, 2009. Estimates indicate that monies for this project will support 8 direct, indirect and induced jobs. | Leo Jounagan Construction Co. (Missouri Monthly Summary Employment Report, June) | 23 total employees working 306 hours (Missouri DOT Monthly Summary Employment Report, May) |
| Missouri, Jasper | Thin lift overlay from Rte. Z to Rte. P. Funds Allocated: $179,600
|
Construction started. | Leo Jounagan (Missouri Monthly Summary Employment Report, June) | 12 employees, 136 hours worked through June 30, 2009 (Missouri Monthly Summary Employment Report, June) |
| Missouri, Butler | Thin lift overlay from Rte. WW in Poplar Bluff to Rte. 158. Funds Allocated: $276,700
|
Construction started. (Missouri Monthly Summary Employment Report, June) | Pace Construction Company, LLC (Missouri Monthly Summary Employment Report, June) | 7 employees, 560 hours worked through June 30, 2009 (Missouri Monthly Summary Employment Report, June) |
| Missouri, Platte | Pavement repair, resurface pavement and shoulders at various locations from Rte. 273 to Vivion Road. Incorportates project 4I1819. Funds Allocated: $11,799,300
|
Construction started. Advertised 1/30/09, awarded 3/04/09, and issued Notice to Proceed 5/04/09. 21% completed as of June 30, 2009. (Missouri Monthly Summary Employment Report, June) Received Notice to Proceed 05/04/2009 (U.S. DOT, July 17, 2009) Work on this project began May 18, 2009 and as of July 31, 2009 the project is 33% complete. Estimates indicate that monies for this project will support 342 direct, indirect and induced jobs. | Ideker Inc. (Missouri Monthly Summary Employment Report, June) | 63 employees, 6376 hours worked through June 30, 2009 (Missouri Monthly Summary Employment Report, June) |
| Missouri, Clinton | Resurface north of Shoal Creek to north of Rte. 116 near Lathrop. Funds Allocated: $14,156,500
|
Construction started. Project ongoing. Began Feb. 17. According to Missouri DOT spokesperson this was one of the first stimulus projects in the nation to kick off. (Info. provided via Holly Murphy, senior community relations specialist with Missouri Department of Transportation July 29, 2009) Received Notice to Proceed 1/20/2009 (U.S. DOT, July 17, 2009) | Loch Sand and Construction Company (Missouri DOT Monthly Summary Employment Report, June) | 143 employees, 1557 hours worked through June 30, 2009 (Missouri DOT Monthly Summary Employment Report, June) Loch Sand and Construction Company, Maryville, Mo. Company was able to put back to work, eventually, about 18 laid-off workers. As many as eight new workers were hired. (Info. provided via Holly Murphy, senior community relations specialist with Missouri Department of Transportation July 29, 2009) |
| Missouri, Greene | Widen to six lanes from I-44 to Bus. 65 (Chestnut Expressway). Funds Allocated: $2,359,316
|
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Missouri, Cole | Thin lift overlay from Rte. 54 to Brush Creek. Funds Allocated: $848,200
|
Project completed. Project started June 15. Project awarded to APAC-Missouri, Columbia, Mo. (Info. provided via Holly Murphy, senior community relations specialist with Missouri Department of Transportation July 29, 2009) Received Notice to Proceed 06/08/2009 (U.S. DOT, July 17, 2009) | APAC-Missouri, Inc. (Missouri Monthly Summary Employment Report, June) | 36 employees, 739 hours worked through June 30, 2009 (Missouri Monthly Summary Employment Report, June) |
| Missouri, Cooper | Pavement improvements on the westbound lanes from 0.3 mile east of Rte. B to the Saline County line. Funds Allocated: $7,612,000
|
Received Notice to Proceed 05/04/2009 (U.S. DOT, July 17, 2009) This project began June 12, 2009 and is approximately 30 percent complete. (Sally Oxenhandler, Community Relations Manager, Missouri Department of Transportation) | Chester Bross Construction | To date, Chester Bross Construction, contractor for state project number 5I2154, has reported that 23 direct jobs, 1996.5 work hours and $75,965 payroll dollars have been supported by their work on the project. The hours reported by the contractor include only direct, on site employment and do not include indirect or induced supported employment. MoDOT estimates the monies for this project will support 220 direct, indirect and induced jobs. The methodology for estimating the number of direct, indirect and induced jobs supported with infrastructure investment stems from a report published by the Federal Highway Administration (FHWA) in 2007. The equation states that for every 1.2 billion in highway infrastructure investment, 34,779 direct, indirect and induced jobs are supported. These are not necessarily considered full-time equivalent positions, nor does it distinguish between new hires or sustained employment.(Sally Oxenhandler, Community Relations Manager, Missouri Department of Transportation) |
| Montana, Missoula | 0.17 mile mill and fill in Missoula Funds Allocated: $76,845 |
Awarded 5/19/09, issued Notice to Proceed 6/01/09, and 07/09 is estimated completion. (Montana DOT Web site June report). | Knife River - Missoula (Montana DOT Web site June report). | |
| Montana, Daniels | 14.2 mile chip seal on MT 13 in Daniels County north of Scoby Funds Allocated: $518,694 |
Awarded 5/19/09, issued Notice to Proceed 6/15/09, and 10/09 is estimated completion date. | Riverside Contracting Inc. - MSLA (Montana DOT Web site June report). | |
| Montana, Lewis And Clark | 0.3 mile mill and fill in Helena Funds Allocated: $242,918 |
Awarded 5/19/09, issued Notice to Proceed 7/06/09. Estimated completion is 08/09. (Montana DOT Web site June report). | Helena Sand & Gravel (Montana DOT Web site June report). | |
| Montana, Rosebud | 8.1 mile pavement preservation, minor widening & pavement marking/guardrail upgrade on MT 39 in Rosebud County, just north of the Northern Cheyenne Reservation. Funds Allocated: $1,905,486 |
Awarded 5/26/09, issued Notice to Proceed 6/22/09, and estimated completion is 09/09. (Montana DOT Web site June report).Received Notice to Proceed 06/08/2009 (U.S. DOT, July 17, 2009) | Prince Inc. | |
| Montana, Carter | Pave State Secondary 323 from RP 24.83 to 37.1 This is the section that is currently under contract with a total reconstruct to a all weather gravel surface. Funds Allocated: $8,652,601 |
Awarded 6/02/09, issued Notice to Proceed 7/06/09. Estimated completion date is 07/10. (Montana DOT Web site June report). | Foothills Contracting, Inc. | |
| Montana, Cascade | 0.6 mile overlay in Great Falls. Funds Allocated: $327,122 |
Issued Notice to Proceed 7/20/2009 (US DOT, August 7, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Montana, Lewis And Clark | I 15 Dearborn Rest Area Replacement Funds Allocated: $4,506,500 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Montana, Sheridan | 15.3 mile overlay on MT 16 between Plentywood and the Port of Raymond in Sheridan County. Funds Allocated: $3,022,926 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Montana, Statewide | I 94 Bridge Deck Rehabilitation In Rosebud County Funds Allocated: $4,931,200 |
Issued Notice to Proceed 8/03/2009 (US DOT August 7, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Nebraska, Jefferson | Resurf. Funds Allocated: $2,878,863 |
Construction started. (Nebraska Monthly Summary Employment Report, June) | Werner Construction, Inc. (Nebraska Monthly Summary Employment Report, June) | 35 employees, 1599 hours worked through June 30, 2009 (Nebraska Monthly Summary Employment Report, June) |
| Nebraska, Clay | Gr., Culv., Resurf. Funds Allocated: $1,947,585 |
Construction started. (Nebraska Monthly Summary Employment Report, June) Received Notice to Proceed 04/07/2009 (U.S. DOT, July 17, 2009) | Vontz Paving, Inc. (Nebraska Monthly Summary Employment Report, June) | 28 employees, 1453 hours worked through June 30, 2009 (Nebraska Monthly Summary Employment Report, June) |
| Nebraska, Jefferson | Br. Funds Allocated: $2,966,171 |
Construction started. (Nebraska Monthly Summary Employment Report, June) Received Notice to Proceed 05/04/2009 (U.S. DOT, July 17, 2009) | Hawkins Construction Company. (Nebraska Monthly Summary Employment Report, June) | 41 employees, 1484 hours worked through June 30, 2009. (Nebraska Monthly Summary Employment Report, June) |
| Nebraska, Dawson | Resurf., S. Shld. Funds Allocated: $6,670,500 |
Construction started. (Nebraska Monthly Summary Employment Report, June) Received Notice to Proceed 03/25/2009 (U.S. DOT, July 17, 2009) | Werner Construction, Inc. (Nebraska Monthly Summary Employment Report, June) | 19 employees, 630 hours worked through June 30, 2009 (Nebraska Monthly Summary Employment Report, June) |
| Nebraska, Kimball | Resurf. Funds Allocated: $4,633,135 |
Construction started. (Nebraska Monthly Summary Employment Report, June) Received Notice to Proceed 06/03/2009 (U.S. DOT, July 17, 2009) | Werner Construction, Inc. (Nebraska Monthly Summary Employment Report, June) | 3 employees, 30 hours worked through June 30, 2009 (Nebraska Monthly Summary Employment Report, June) |
| Nebraska, Douglas | Gr., Surf., S. Shld. Funds Allocated: $18,737,482
|
Contract awarded. (Nebraska Monthly Summary Employment Report, June) | Hawkins Construction Company (Nebraska Monthly Summary Employment Report, June) | NA (Nebraska Monthly Summary Employment Report, June) |
| Nevada, Humboldt | Cold in Place Recycle Funds Allocated: $1,011,170
|
Awarded. Construction started about two weeks ago. (Scott Magruder, Public Information Officer, NV DOT, July 31, 2009) | Q&D Construction Inc. (Scott Magruder, Public Information Officer, NV DOT, July 31, 2009) | NA. (Scott Magruder, Public Information Officer, NV DOT, July 31, 2009) |
| Nevada, Lander | Overlay Plantmix Bituminous Surface Funds Allocated: $2,587,040
|
Awarded. Expected to begin construction in the next two weeks. (Scott Magruder, Public Information Officer, NV DOT, July 31, 2009) | Frehner Construction Co. (Scott Magruder, Public Information Officer, NV DOT, July 31, 2009) | NA. (Scott Magruder, Public Information Officer, NV DOT, July 31, 2009. Frehner Construction confirmed 7/29/09.) |
| New Hampshire, Merrimack | EXIT 14 NORTH TO EXIT 17, 1.5" TW INLAY WITH 1.5" FULL WIDTH OVERLAY (6.1 MILES) [Parents = IPPP*3927, BRPPI 6601 AND GRR 785] [ARRA] Funds Allocated: $5,356,186
|
Work Started (Company reported hours worked in NH Monthly Employment Summary for July). Awarded/Notice to Proceed on June 17, 2009 (July 22, 2009 NHDOT Bill Cass Director of Project Development) | Continental Paving Inc. | 30 hours worked Continental & 6 hours worked NHDOT (New Hampshire Monthly Summary Employment Report: June) |
| New Hampshire, Statewide | EXIT 19 NORTH TO EXIT 22, LEVEL .5" AND 1" OVERLAY (3.5 MILES) [PARENT = IPPP*3927 & BRPPI*6601] [ARRA] Funds Allocated: $2,413,045
|
Work Started (Company reported hours worked in NH Monthly Employment Summary for July). Awarded/Notice to Proceed on May 20, 2009 (July 22, 2009 NHDOT Bill Cass Director of Project Development). | Pike Industries, Inc. | 1 hour worked NHDOT & 7 hours worked Pike Industries (New Hampshire Monthly Summary Employment Report ) |
| New Hampshire, Merrimack | KING ST SIDEWALK CONNECTOR: CONSTRUCT SIDEWALKS ALONG NORTH MAIN ST FORM EXISTING SIDEWALK TO INTERSECTION OF US 3/4 & FROM US 3/4 INTERSECTION TO RIVER RD CONNECTING WITH EXISTING SIDEWALK ON KING ST Funds Allocated: $484,050
|
Not yet awarded or let to bid. | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| New Jersey, Essex | This is a resurfacing project consists of milling 2" and repaved with 5" of Superpave Hot Mix Asphalt. Substandard guide rail will be upgraded. Existing vertical under-clearances will be maintained at Funds Allocated: $11,502,043
|
Awarded, and a Notice to Proceed issued 6/2/09. (Erin Phalon, Public Information Officer, NJ DOT, July 31, 2009) | Intercounty Paving. (Erin Phalon, Public Information Officer, NJ DOT, July 31, 2009) | 165 hours worked through June 30, 2009 (Erin Phalon, Public Information Officer, NJ DOT, July 31, 2009) |
| New Jersey, Hunterdon | ROUTE 29 WEST AMWELL TOWNSHIP DRAINAGE (SHEET FLOW) Funds Allocated: $168,405
|
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| New Jersey, Bergen | Addresses painting needs for 9 bridges along the I-80 corridor. Funds Allocated: $8,655,670
|
Not awarded. (Erin Phalon, Public Information Officer, NJ DOT, July 31, 2009) | NA (Erin Phalon, Public Information Officer, NJ DOT, July 31, 2009) | NA (Erin Phalon, Public Information Officer, NJ DOT, July 31, 2009) |
| New Jersey, Statewide | Contract # 10 will protect about 5.14 miles of Route 18, from MP 16.56 to MP 19.20, MP 24.30 to MP 25.2; and MP 28.70 to MP 30.70; and 4.64 miles of Route I-95, from MP 0.55 to MP 2.22 and from MP 5. Funds Allocated: $4,554,354
|
Not awarded. (Erin Phalon, Public Information Officer, NJ DOT, July 31, 2009) | NA (Erin Phalon, Public Information Officer, NJ DOT, July 31, 2009) | NA (Erin Phalon, Public Information Officer, NJ DOT, July 31, 2009) |
| New Mexico, San Juan | US 491, Tohatchi to Shiprock Funds Allocated: $31,500,000
|
Construction started (NM DOT). Received Notice to Proceed 6/30/2009 (U.S. DOT, July 17, 2009) | FNF Construction (Phoenix Business Journal) | |
| New York, Steuben | DRAINAGE MBC Funds Allocated: $974,155 |
Advertised 2/04/09. Awarded 4/06/09. Issued Notice to Proceed 4/20/09. (New York Monthly Summary Employment Report, June) Received Notice to Proceed 04/20/2009 (U.S. DOT, July 17, 2009) | Slate Hill Contractors, Inc. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) |
| New York, Statewide | BRIDGE JOB ORDER CONTRACT (JOC), BROOME, CHENANGO, TIOGA COUNTIES Funds Allocated: $1,010,000
|
Advertised 4/22/09. (New York Monthly Summary Employment Report, June) This project has not yet been awarded. (Carol Breen, Public Information Office, NYSDOT, August 3, 2009) | NA (Ann Schrader, Purchasing Coordinator, ITCS Dept. in Owego (Tioga County)) | |
| New York, Ontario | RESURFACING OF VARIOUS FA ROUTES REGIONWIDE - 4VPP01 Funds Allocated: $633,000 |
Advertised 4/27/09. Awarded 7/02/09. Issued Notice to Proceed 7/16/09. (New York Monthly Summary Employment Report, June) Received Notice to Proceed 07/16/2009 (U.S. DOT, July 17, 2009) | Midland (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) |
| New York, Statewide | BRIDGE PAINTING ON VARIOUS BRIDGES IN REG 7 (BINS 1008940, 1017270, 1029600, 1023922, 3321950, 1024020, 1048260, 1023820, 1023830) Funds Allocated: $3,653,000
|
Advertised 5/20/09. (New York Monthly Summary Employment Report, June) This project has not yet been awarded. (Carol Breen, Public Information Office, NYSDOT, August 3, 2009) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Erie | HIGHWAY RESURFACING, ROUTE 265, FLETCHER STREET TO NIAGARA COUNTY LINE, CITY OF TONAWANDA, ERIE COUNTY AND ROUTE 265, BUFFALO City LINE TO ROUTE 324, TOWN OF TONAWANDA, VILLAGE OF KENMORE, ERIE COUNTY Funds Allocated: $1,229,631
|
Construction is scheduled to start in the summer of 2009 and completion expected in fall 2010 according to NYDOT web page. Bids were opened June 25, 2009. Contract for the project should become effective by August 2. Construction should begin by mid to end of August. (Anthony Milone, Accadia Site Contracting Inc., July 24, 2009) | Accadia Site Contracting Inc. | NA |
| New York, Westchester | REPLACEMENT OF BRIDGE (BIN 2254910) AT ODELL AVENUE BETWEEN THE SAW MILL RIVER PARKWAY AND SAW MILL RIVER ROAD OVER ABANDONED RAIL ROAD IN THE CITY OF YONKERS Funds Allocated: $2,810,000
|
Construction started. Advertised 2/02/09. Awarded 3/18/09. Issued a Notice to Proceed 5/11/09. (New York Monthly Summary Employment Report, June) Received Notice to Proceed 03/30/2009 (U.S. DOT, July 17, 2009) | PCI Industries Corp. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) |
| New York, Statewide | I-86 BRIDGE DECK OVERLAYS REHAB., VARIOUS LOCATIONS, BINS 1061382 & 1062131, ALLEGANY & STEUBEN COUNTIES. Funds Allocated: $444,923
|
Construction started. Advertised 4/08/09. Awarded 6/01/09. Issued Notice to Proceed 6/15/09. (New York Monthly Summary Employment Report, June) Received Notice to Proceed 06/15/2009 (U.S. DOT, July 17, 2009) | C.P. Ward, Inc. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) 7 hours worked in June (Carol Breen, Public Information Office, NYSDOT, August 3, 2009) |
| New York, Statewide | BRIDGE PAINTING, BINS 1008601, 1008602, 1027470, 1027510, 3339020, 1043270, 1032251, 1032252, JEFFERSON AND ST LAWRENCE COUNTIES Funds Allocated: $4,024,872
|
Construction started. Advertised 4/08/09. Awarded 6/30/09. Issued Notice to Proceed 7/14/09. (New York Monthly Summary Employment Report, June) Received Notice to Proceed07/14/2009 (U.S. DOT, July 17, 2009) | Erie Painting & Maintenance. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) No hours worked yet (Carol Breen, Public Information Office, NYSDOT, August 3, 2009) |
| New York, Schuyler | CR 16 RESURFACING MEADS HILL ROAD TO TOWNSEND ROAD, TOWN OF DIX, SCHUYLER COUNTY. Funds Allocated: $270,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Rockland | GUIDERAIL REPLACEMENT ON COUNTY FEDERAL AID ROADWAYS. ROCKLAND COUNTY Funds Allocated: $1,000,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Statewide | Highway Resurfacing on Route 12B in the Towns of Marshall, Kirkland, Oneida County and in the Towns of Madison and Augusta, Madison County (Vendor Placed Paving) Funds Allocated: $972,000
|
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Jefferson | CONSTRUCTION OF RECREATIONAL TRAIL FROM FORT PIKE TO SACKETS HARBOR CENTRAL SCHOOL AND BATTLEFIELD (SACKETS HARBOR WAR OF 1812 BICENTENIAL TRAIL), JEFFERSON COUNTY (TRANSPORTATION ENHANCEMENT PROJECT) Funds Allocated: $495,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Essex | TICONDEROGA:TICONDEROGA TRAIN TRESTLE CONVERSION AND HISTORIC TRAIL EXPANSION. Funds Allocated: $325,000
|
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Lewis | REHABILITATION OF 2.8 miles County Route.29 (WEST ROAD), IN THE TOWN OF MARTINSBURGH, Lewis County (Multi Course Overlay) Funds Allocated: $1,754,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Statewide | BRIDGE CORRECTIVE REPAIR TO ADDRESS DEFICIENT BRIDGE CONDITIONS CITYWIDE ON THE FEDERAL AID HIGHWAY SYSTEM. REPLACEMENT OF THE WATERBURY AVENUE PEDESTRIAN BRIDGE SPAN OVER I-95 S/B WILL BE INCLUDED. Funds Allocated: $6,000,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | ||
| New York, Herkimer | DOLGEVILLE:MAIN STREET STREETSCAPE PROJECT-LANDSCAPING AND SIDEWALKS. Funds Allocated: $1,000,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Wyoming | RESURFACING OF VARIOUS FA ROUTES REGIONWIDE - 4VPP01 Funds Allocated: $214,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Cattaraugus | ROUTE 954J RESURFACING FROM I86 TO ROUTE 430, TOWN OF ELLERY AND VILLAGE OF BEMUS POINT, CHAUTAUQUA COUNTY Funds Allocated: $370,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Wayne | RESURFACING OF VARIOUS FA ROUTES REGIONWIDE - 4VPP01 Funds Allocated: $540,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Cattaraugus | PERSIA:COUNTY ROUTE 4/BROADWAY ROAD FROM 1000 FEET SOUTH OF POINT PETER ROAD TO PALMER FOR HIGHWAY RESURFACING. Funds Allocated: $300,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Genesee | HIGHWAY RESURFACING, COUNTY ROUTE 19 (TOWNLINE ROAD), RT. 33 TO HAWLEY DRIVE AND COUNTY ROUTE 48 (HAWLEY DRIVE), BANK STREET TO BATAVIA-STRAFFORD TOWN LINE ROAD, TOWN OF BATAVIA, GENESEE COUNTY. Funds Allocated: $860,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Ontario | RESURFACING OF VARIOUS FA ROUTES REGIONWIDE - 4VPP01 Funds Allocated: $402,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Livingston | RESURFACING OF VARIOUS FA ROUTES REGIONWIDE - 4VPP01 Funds Allocated: $582,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Statewide | Highway Resurfacing on Routes 8, 12 and 20 in the Towns of Trenton, Stuben, Forestport, Cazenovia, Oneida County and the Town of Brookfield, Madison County (Vendor Placed Paving) Funds Allocated: $1,525,000 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | ||
| New York, Schoharie | COBLESKILL:COUNTY ROUTE 8 BOX CULVERT REPLACEMENT. PE FOR BOX CULVERT REPLACEMENT (SCOPING & 1-6). Funds Allocated: $30,000
|
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Monroe | INSTALLATION OF DETECTABLE WARNING FIELDS ON SIDEWALK RAMPS TO MEET AMERICAN WITH DISABILITY ACT STANDARDS, VARIOUS LOCATIONS REGIONWIDE Funds Allocated: $330,663
|
Not advertised yet for bids. (New York Monthly Summary Employment Report, June) | NA (New York Monthly Summary Employment Report, June) | |
| New York, Tompkins | COLUMBIA ST PEDESTRIAN BRIDGE REHABILITATION ENHANCEMENT PROJECT, CITY OF ITHACA, TOMPKINS CO. Funds Allocated: $1,077,628 |
Not advertised yet for bids. (New York Monthly Summary Employment Report, June)' | NA (New York Monthly Summary Employment Report, June) | |
| New York, Niagara | NIAGARA FALLS:HIGHWAY RESURFACING ON MAIN STREET, 11th STREET, AND ONTARIO AVENUE. Funds Allocated: $1,204,000
|
Not advertised yet for bids. (New York Monthly Summary Employment Report, June)According to Gary Gottlieb, Planning and Program Manager for Region 5, NYSDOT, the project has been certified and bids are scheduled to be opened on August 4, 2009. | NA | NA |
| New York, Clinton | RESURFACE OF VARIOUS FEDERAL AID HIGHWAYS IN REGION 7, VENDOR PAVING PROJECTS (VPP) BLOCK - 7T0441 Funds Allocated: $174,000
|
Not awarded yet. (New York Monthly Summary Employment Report, June) Received Notice to Proceed 04/22/2009 (U.S. DOT, July 17, 2009) | ||
| New York, Chautauqua | BRIDGE REPLACEMENT, RT. 60 (WASHINGTON ST.) OVER WESTERN NY & PENNSYLVANIA RAILROAD, CHADAKOIN RIVER & HARRISON ST. (BIN 1027770); RECONSTRUCT RT. 60, SOUTH MAIN ST.-WEST 2nd ST.; RESURFACE 6th ST., W Funds Allocated: $4,032,000
|
Project Development began in Spring 2004. It was authorized/certified on May 15, 2009, with a total project cost of $19,800,000, of which $4 million is ARRA funding. Project completion date was listed as Summer 2011 in this source. However, another NYSDOT document cites a later expected completion date: “Construction is expected to be completed in Winter 2010/2011". Bids for this project were opened on July 9, 2009. Jeff Bower of UCC Constructors says the company expects the contract should be signed by August 23, and that construction should begin immediately after. He estimates that funding for this project will not create new jobs, but will save approximately 20 jobs. | UCC Constructors, Inc. | NA (New York Monthly Summary Employment Report, June) |
| North Carolina, Cabarrus | Mount Pleasant-NC 73 from the East City Limits to SR 2411 (Cold Springs Rd) Funds Allocated: $25,000
|
A proposal has not been put together. The project will require environmental review. The project is expected to begin in Spring 2010. (Marc Morgan, NC DOT 10th Division, July 24, 2009) | NA | NA |
| North Carolina, Swain | Pavement Rehabilitation Funds Allocated: $6,483,915
|
Let 4/29/09. Received Notice to Proceed 06/01/2009 (U.S. DOT, July 17, 2009) | Harrison Construction Company, a division of APAC-Atlantic, Inc. | |
| North Carolina, Surry | Pavement Rehabilitation Funds Allocated: $4,032,676
|
Received Notice to Proceed 07/06/2009 (U.S. DOT, July 17, 2009) | ||
| North Carolina, Bertie | Resurface Funds Allocated: $119,500
|
The contract was awarded June 12. Work has not started. The completion date is November 13. (Steve Abbott in the N.C. DoT communications office) | Rose Brothers Paving (Steve Abbott in the N.C. DoT communications office) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| North Carolina, Union | Intersection Improvements Funds Allocated: $25,000
|
The estimated cost of this project has increased to $75,000. It has not been let yet. The DOT expect to let it in 6 weeks. (Tim Boland, NC DOT Div 10, July 24, 2009) | NA | NA |
| North Dakota, Williams | APPROX. 0.33 MILES OF Mill & Overlay, Sidewalks, driveways & curbramps Funds Allocated: $108,686 |
Received Notice to Proceed 06/17/2009 (U.S. DOT, July 17, 2009) | ||
| North Dakota, Mclean | APPROX. 28.1129 MILES OF Thin Overlay Funds Allocated: $3,499,737 |
This project was bid on 4/3/09 and awarded on 4/16/09. (Peg Anderson, ND DOT, August 3, 2009) | Mayo Construction Company, Inc. | NA |
| North Dakota, Mckenzie | APPROX. 19.2917 MILES OF Thin Overlay Funds Allocated: $2,666,789 |
This project was bid on 5/15/09 and awarded on 6/7/09. (Peg Anderson, ND DOT, August 3, 2009) | Northern Improvement Company (Peg Anderson, ND DOT, August 3, 2009) | NA |
| North Dakota, Pembina | APPROX. 0.1 MILES OF Structure Funds Allocated: $283,909 |
This project was bid on 6/19/09 and awarded on 7/7/09. Notice to Proceed has not gone through yet. (Peg Anderson, ND DOT, August 3, 2009) Received Notice to Proceed 07/07/2009 (U.S. DOT, July 17, 2009) | Contractor N/A (Peg Anderson, ND DOT, August 3, 2009) | |
| North Dakota, Emmons | APPROX. 0.5 MILES OF HBP Funds Allocated: $174,310 |
This project was bid on 6/19/09 and awarded on 7/7/09. Notice to Proceed has not gone through yet. Received Notice to Proceed 07/07/2009 (U.S. DOT, July 17, 2009) | Contractor N/A (Peg Anderson, ND DOT, August 3, 2009) | |
| North Dakota, Griggs | APPROX. 8 MILES OF Chip seal Funds Allocated: $136,481 |
This project was bid on 6/5/09 and awarded on 6/17/09. Work is expected to begin soon. (Peg Anderson, ND DOT, August 3, 2009) Received Notice to Proceed 06/17/2009 (U.S. DOT, July 17, 2009) | Morris Sealcoat & Trucking, Inc. | |
| North Dakota, Grand Forks | APPROX. 1.06 MILES OF Concrete Panel Replacement, Mill & Overlay, 3" Funds Allocated: $244,479
|
This project was bid on 6/5/09 and awarded on 6/17/09. (Peg Anderson, ND DOT, August 3, 2009) | Opp Construction, Inc. | NA |
| Ohio, Clinton | Plane and pave SR 380 in Clinton County Funds Allocated: $2,231,250 |
Award Aug. 10 (Nancy Burton, OH DOT, August 5, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Ohio, Preble | Plane and pave portions of SR 732 in Preble County. Also to resurface Eaton Oxford Road, C-29, in from of the Morning Sun Outpost. Funds Allocated: $2,478,290 |
Award Aug. 10 (Nancy Burton, OH DOT, August 5, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Ohio, Greene | REHABILITATE US 35 AT THE US 35/I-675 INTERCHANGE. Funds Allocated: $6,258,000 |
Contract Awarded (Nancy Burton, OH DOT, August 5, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Complete General (Nancy Burton, OH DOT, August 5, 2009) | NA |
| Ohio, Athens | Two-Lane Resurfacing Project. Ath 356 0.00-4.77. Includes ATH 682 5.96-7.75 And VIN 356 0.00-5.97. Funds Allocated: $857,000 |
Contract awarded. (Nancy Burton, OH DOT, August 5, 2009) | Shelly & Sands (Nancy Burton, OH DOT, August 5, 2009) | |
| Ohio, Mahoning | Deck replacement, widening, and painting of two structures. Funds Allocated: $2,378,250 |
Contract awarded. (Nancy Burton, OH DOT, August 5, 2009)No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Marucci & Gaffney Excavating Company | NA |
| Ohio, Portage | REPLACE OR REHAB BRIDGE OVER CUYAHOGA RIVER AND CSX. IMPROVE CRAIN AVE. INTERSECTION IMPROVEMENT OF THREE INTERSECTIONS. Funds Allocated: $3,000,000
|
Contract awarded.(Nancy Burton, OH DOT, August 5, 2009) Received Notice to Proceed 07/09/2009. Awarded 6/30/09. (U.S. DOT, July 17, 2009) | Beaver Excavating Company | |
| Ohio, Morgan | Guardrail project on CR 2, CR 70 and CR 92 on various sections in Morgan County. STIMULUS FUNDED ARRA ID 7312 Funds Allocated: $150,000 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Ohio, Medina | resurface existing pavement and add paved shoulders to provide a new pavement surface and preserve the pavement structure Funds Allocated: $776,663 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Ohio, Hocking | Part 3 of 3, the Nelsonville By-Pass (CO phase). Part 1 CO Phase under PID 80949. PE, RW and CO Phase Part 2 under PID 23846. Some environmental under old PID 14040. ARRA ID 7217 Funds Allocated: $120,210,000 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Ohio, Greene | Asphalt resurfacing project. Funds Allocated: $383,740 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Ohio, Portage | Replacement of existing 2 span steel truss and steel beam structure, also includes approach reconstruction Funds Allocated: $1,124,000 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Ohio, Geauga | Washington Street (A&B) resurfacing project. Funds Allocated: $500,000 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Ohio, Medina | Replacement of rail, ballast, crossing surfaces, and other system improvements along the city's 3.6-mile long rail line. Funds Allocated: $949,795 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Ohio, Franklin | Camp Chase Railroad Line Rehabilitation Funds Allocated: $300,000 |
Project is expected to sell this year, but still waiting for plans from the Railroad. (Nancy Burton, OH DOT, August 5, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Ohio, Stark | Reconstruct & Rehab Of SR153 With New Curb And Gutters. Sidewalk Pavement Widening West Of California And Signals At California Funds Allocated: $330,000 |
Received Notice to Proceed 06/16/2009 (U.S. DOT, July 17, 2009) | ||
| Ohio, Medina | REPLACE DEFICIENT 68' STRUCTURE (9.88) OVER RUDD CREEK** Selected Stimulus project ** Funds Allocated: $430,000 |
Received Notice to Proceed E080129 (U.S. DOT, July 17, 2009) | ||
| Ohio, Perry | Replace the deck and paint the structure on the SR 93 bridge Funds Allocated: $1,093,050 |
Work started July 6. (Nancy Burton, OH DOT, August 5, 2009) Received Notice to Proceed 06/25/2009 (U.S. DOT, July 17, 2009) | Righter Company (Nancy Burton, OH DOT, August 5, 2009) | |
| Ohio, Guernsey | 3" mill & fill with 1-3/4" intermediate and 1-1/4" surface and associated additional work on a portion of Interstate Route 77 in Guernsey County Funds Allocated: $1,604,000 |
Work Started: July 9, 2009 (Nancy Burton, OH DOT, August 5, 2009)Received Notice to Proceed 6/26/2009 (U.S. DOT, July 17, 2009) | Shelly and Sands (Nancy Burton, OH DOT, August 5, 2009) | |
| Ohio, Summit | Deck overlay and fence installation. Funds Allocated: $7,500,000 |
NA | ||
| Ohio, Trumbull | Transportation issue to be corrected : Mill and resurface roadway including repair of curbs, sidewalks and install ADA curb ramps. Install / upgrade lighting. Funds Allocated: $711,060 |
|||
| Oklahoma, Noble | CO. BR: OVER RED ROCK CREEK, 0.7 MI WEST OF THE US-77/SH-15 JCTSOUTHWEST OF CERES Funds Allocated: $765,687 |
Awarded. (Oklahoma Monthly Summary Employment Report, June) | K & R Builders, Inc. (Oklahoma Monthly Summary Employment Report, June) | NA (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Pawnee | US-64: BEGIN AT INTERSECTION OF SH-99, EXTEND EAST 7.65 MI.(ADD ALTERNATES) Funds Allocated: $2,108,340 |
Awarded. (Oklahoma Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Chester Bross Construction (Oklahoma Monthly Summary Employment Report, June) | NA (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Lincoln | SH-105 BEG @ US-177 & EXT EAST APPROX 8.0 MILE T0 SH-18. Funds Allocated: $985,000 |
Awarded. (Oklahoma Monthly Summary Employment Report, June) Received Notice to Proceed 04/09/2009 (U.S. DOT, July 17, 2009) | The Quapaw Company. (Oklahoma Monthly Summary Employment Report, June) | NA (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Canadian | PIEDMONT ARRA: PIEDMONT RD FROM ARROWHEAD ST (192) TO APACHE ST (206) Funds Allocated: $188,523 |
Awarded. (Oklahoma Monthly Summary Employment Report, June) Received Notice to Proceed 07/02/2009 (U.S. DOT, July 17, 2009) | Haskell Lemon Construction. (Oklahoma Monthly Summary Employment Report, June) | NA (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Stephens | CO BR OVER STAGE STAND CR, 6.0 MI SOUTH & 6.0 MI WEST OF THE NORTHSH-7/US-81 JCT, Funds Allocated: $452,164 |
Awarded. (Oklahoma Monthly Summary Employment Report, June) Received Notice to Proceed 5/11/2009 (U.S. DOT, July 17, 2009) | K&R Builders. (Oklahoma Monthly Summary Employment Report, June) | NA (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Stephens | CO BR OVER DEER CR, 3.5 MI SOUTH & 7.7 MI EAST OF SH-53/US-81 JCT Funds Allocated: $382,956 |
Awarded. (Oklahoma Monthly Summary Employment Report, June) Received Notice to Proceed 5/11/2009 (U.S. DOT, July 17, 2009) | K&R Builders, Inc. (Oklahoma Monthly Summary Employment Report, June) | NA (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Canadian | I-40: FROM FROM MILE MARKER 132 TO MILE MARKER 136(PAVE & BR REHAB) Funds Allocated: $30,000,000 |
Construction started. (Oklahoma Monthly Summary Employment Report, June) | Duit Construction Company. (Oklahoma Monthly Summary Employment Report, June) | 50 employees, 2658 hours worked through June 30, 2009 (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Murray | I-35: BEGINNING AT THE CARTER C/L EXTEND N. 6.56 MILES Funds Allocated: $4,927,000 |
Construction started. (Oklahoma Monthly Summary Employment Report, June) | Silver Star Construction. (Oklahoma Monthly Summary Employment Report, June) | 62 employees, 2469 hours worked through June 30, 2009. (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Comanche | SH-7: OVER BEAVER CR, 2.4 MI WEST OF THE COMANCHE/STEPHENS C/L(1.6 MI EAST OF SH 65) Funds Allocated: $2,241,000 |
Construction started. (Oklahoma Monthly Summary Employment Report, June) Received Notice to Proceed 04/13/2009 (U.S. DOT, July 17, 2009) | Plains Bridge Contracting. (Oklahoma Monthly Summary Employment Report, June) | 58 employees, 3183 hours worked through June 30, 2009. (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Woods | SH-45: BEGIN 4.6 MILES EAST OF THE US-281 JCT., EXTEND EAST 3.5 MILES Funds Allocated: $598,700 |
Construction started. (Oklahoma Monthly Summary Employment Report, June) Received Notice to Proceed 04/14/2009 (U.S. DOT, July 17, 2009) | The Cummins Construction Co. (Oklahoma Monthly Summary Employment Report, June) | 8 employees, 526 hours worked through June, 30, 2009(Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Carter | US-70 BEG @ JEFFERSON C/L & EXTENDING EAST 3.08 MILEBR=09247(14) Funds Allocated: $5,344,000 |
Construction started. (Oklahoma Monthly Summary Employment Report, June) Received Notice to Proceed 04/16/2009 (U.S. DOT, July 17, 2009) | Silver Star Construction. (Oklahoma Monthly Summary Employment Report, June) | 58 employees, 2435 hours worked through June 30, 2009. (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Tulsa | I-244 FROM US-64 INTERCHANGE EAST TO THE US-75 INTERCHANGE IN TULSA(E.B. LANES OF NORTH LEG OF IDL)(DEL FR 03-09, ADD TO 04-09; AS PER O.E.) Funds Allocated: $15,100,000 |
Construction started. (Oklahoma Monthly Summary Employment Report, June) Received Notice to Proceed 06/01/2009 (U.S. DOT, July 17, 2009) | Manhattan Road & Bridge. (Oklahoma Monthly Summary Employment Report, June) | 12 employees, 760 hours worked through June 30, 2009. (Oklahoma Monthly Summary Employment Report, June) |
| Oklahoma, Tulsa | BROKEN ARROW ARRA: KENOSHA ST: HICKORY COURT TO ASPEN AVE (145TH E AVE) Funds Allocated: $344,000 |
NA (Oklahoma Monthly Summary Employment Report, June) | NA (Oklahoma Monthly Summary Employment Report, June) | |
| Oregon, Morrow | 1ST ST & MAIN AVE SIDEWALK & BIKE LANES (IRRIGON) LOCAL CONSTRUCT WIDEWALKS, BIKE LANE AND A PLANTER STRIP W/TREES MORROW Funds Allocated: $85,356 |
Construction started. (Oregon Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Otak, Inc. (Oregon Monthly Summary Employment Report, June) | 16 employees, 112 hours worked through June 30, 2009. (Oregon Monthly Summary Employment Report, June) |
| Oregon, Lincoln | NORTH BANK RD & SCHOONER CREEK RD PAVING LOCAL 2 IN PAVEMENT OVERLAY IN ACCORDANCE WITH 1R GUIDELINES LINCOLN Funds Allocated: $55,000 |
Construction started. (OregonMonthly Summary Employment Report, June) Received Notice to Proceed 05/20/2009 (U.S. DOT, July 17, 2009) | David Evans and Associates. (OregonMonthly Summary Employment Report, June) | 9 employees, 73 hours worked through June 30, 2009 (OregonMonthly Summary Employment Report, June) |
| Oregon, Lane | E. LOCUST ST-N. DIAMOND ST PRESERVATION (COBURG) LOCAL OVERLAY ROADWAYS & IMPROVE STREET DRAINAGE LANE Funds Allocated: $10,000 |
NA (Oregon Monthly Summary Employment Report, June) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Oregon, Marion | MARION COUNTY & WOODBURN: PAVEMENT RESURFACING MARION COUNTY Funds Allocated: $1,779,023 |
Letting postponed until July 30, 2009 | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Oregon, Lane | CLEAR LAKE RD & MARCOLA RD PAVING LOCAL 2 IN OVERLAY IN ACCORDANCE W/ 1R GUIDELINES LANE Funds Allocated: $104,000 |
NA (Oregon Monthly Summary Employment Report, June) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Oregon, Morrow | RAIL SERVICE IMPROVEMENTS (PORT OF MORROW) / PE FOR RAIL SYSTEM IMPROVEMENTS / MORROW COUNTY Funds Allocated: $30,000 |
NA (OregonMonthly Summary Employment Report, June) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Oregon, Multnomah | OR99E:MLK/GRAND O-XING UPRR #02115 & 08905 VIADUCT PACIFIC HIGHWAY EAST MULTNOMAH COUNTY Funds Allocated: $1,250,000 |
Received Notice to Proceed 01/12/2007 (U.S. DOT, July 17, 2009) NA (Oregon Monthly Summary Employment Report, June) | Max J. Kuney Company (Steve Leep, OR DOT, August 3, 2009) | |
| Oregon, Malheur | OR201: WEISER INTCHG-SNAKE RIVER (PAYETTE BRIDGE) OLDS FERRY-ONTARIO HIGHWAY MALHEUR COUNTY Funds Allocated: $6,959,443 |
Received Notice to Proceed 06/04/2009 (U.S. DOT, July 17, 2009) NA (Oregon Monthly Summary Employment Report, June) | McCafferty-Whittle Construction Co (Steve Leep, OR DOT, August 3, 2009) | |
| Oregon, Washington | OR 8: N 10TH AVE-N 19TH AVE (CORNELIUS) TUALATIN VALLEY HIGHWAY WASHINGTON COUNTY Funds Allocated: $385,000
|
Several Oregon DOT officials said this project consists of beautifying nine blocks or so through downtown Cornelius, Ore. The $385,000 in federal stimulus funds is a tiny share of the total cost: the federal dollars essentially provide for an accelerated repaving of the road and a few benches and trash receptacles on the sidewalk. The "stimulus work" won't be started until July although construction on the street has already started. (Michael Andersen interview with Steve Leep of the Oregon DOT's finance group, August 2009) (Oregon Monthly Summary Employment Report, June) Received Notice to Proceed 05/22/2008 (U.S. DOT, July 17, 2009). | Kerr Contractors of Woodburn, Ore. (Oregon DOT officials, Steve Leep and Michelle Thom) Harper Houf Peterson Righellis, Inc. (Oregon Monthly Summary Employment Report, June) | 13 employees, 249 hours worked through June 30, 2009. (Oregon Monthly Summary Employment Report, June) July numbers not available yet. |
| Oregon, Deschutes | REDMOND ADAPTIVE TRAFFIC SIGNAL SYSTEM THE DALLES-CALIFORNIA COORDINATED TRAFFIC SYSTEM @ 19 SIGNAL LOCATIONS DESCHUTES Funds Allocated: $150,000 |
Work started. (Oregon Monthly Summary Employment Report, June) Received Notice to Proceed 03/13/2009 (U.S. DOT, July 17, 2009) | State/local government (Oregon Monthly Summary Employment Report, June) | 12 employees, 218 hours worked through June 30, 2009. (Oregon Monthly Summary Employment Report, June) |
| Oregon, Lane | EWEB BIKE PATH: PIONEER PKWY - 31ST STREET (SPRINGFIELD) LOCAL 3 IN OVERLAY IN ACCORDANCE W/ 1R GUIDELINES LANE Funds Allocated: $5,000 |
Work started. (Oregon Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | State/local government (Oregon Monthly Summary Employment Report, June) | 6 employees, 48 hours worked through June 30, 2009 (Oregon Monthly Summary Employment Report, June) |
| Oregon, Lincoln | NEWPORT CITY STREETS: PAVEMENT RESURFACING LOCAL PAVEMENT PRESERVATION PROJECT LINCOLN Funds Allocated: $10,000 |
Work started. (Oregon Monthly Summary Employment Report, June) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | City of Newport. (Oregon Monthly Summary Employment Report, June) | 1 employee, 51 hours worked through June 30, 2009. (Oregon Monthly Summary Employment Report, June) |
| Oregon, Umatilla | ROCKFALL SCREEN Funds Allocated: $206,652 |
Work started. (Oregon Monthly Summary Employment Report, June)Received Notice to Proceed 05/26/2009 (U.S. DOT, July 17, 2009) | State/local government. (Oregon Monthly Summary Employment Report, June) | 4 employees, 20 hours worked through June 30, 2009. (Oregon Monthly Summary Employment Report, June) |
| Pennsylvania, Crawford | SR 1020 OVER CLARKS RUN, APPROX. 136 FT. NE OF THE INTERSECTION W | FOR THE SUPERSTRUCTURE REPLACEMENTS ON ONE SPAN PRESTRESSED CO Funds Allocated: $825,000 |
Awarded. (Pennsylvania Monthly Summary Employment Report, June) | Allison Park Contractors, Inc. (Pennsylvania Monthly Summary Employment Report, June) | |
| Pennsylvania, Lawrence | Bridge Rehabilitation of State Route 2004 (Grove Street) bridge over Neshannock Creek in City of New Castle Funds Allocated: $3,491,447 |
Awarded. (Pennsylvania Monthly Summary Employment Report, June) Received Notice to Proceed 06/30/2009 (U.S. DOT, July 17, 2009) | Delta Constructors. (Pennsylvania Monthly Summary Employment Report, June) | NA. (Pennsylvania Monthly Summary Employment Report, June) |
| Pennsylvania, Luzerne | Interstate 81 Resurfacing from Milepost 139-144 in Luzerne County Funds Allocated: $3,200,000
|
Construction is supposed to start first week of August (PA DOT)Received Notice to Proceed 07/09/2009 (U.S. DOT, July 17, 2009) | Barletta Construction and Material of Hazleton, Pa | NA (Pennsylvania Monthly Summary Employment Report, June) |
| Pennsylvania, Montgomery | Establish gateway medians and install trees to delineate entranceways to the Village Shopping Districts and the Valley Green Road Commercial Center in Springfield and Whitemarsh Townships Funds Allocated: $273,000
|
Construction start date (PA DOT) is 7/17/09. Estimated completion date is 10/30/09. (PA DOT) (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Tony DePaul and Son | NA. (Pennsylvania Monthly Summary Employment Report, June) |
| Pennsylvania, Potter | Restoration of US Route 6 from Coudersport toward Sweden Valley in Coudersport Borough and Eulalia Township Funds Allocated: $1,990,000 |
Construction started. (Pennsylvania Monthly Summary Employment Report, June) Received Notice to Proceed 04/13/2009 (U.S. DOT, July 17, 2009) | Glenn O. Hawbaker, Inc. (Pennsylvania Monthly Summary Employment Report, June) | 27 employees, 1742 hours worked through June 30, 2009. (Pennsylvania Monthly Summary Employment Report, June) |
| Pennsylvania, Erie | Highway Resurfacing on State Route 8 from Haskill Hill Road to Grandview Boulevard in Venango and Millcreek Townships and the City of Erie Funds Allocated: $1,346,000 |
Construction started. (Pennsylvania Monthly Summary Employment Report, June) Received Notice to Proceed 06/16/2009 (U.S. DOT, July 17, 2009) | Russell Standard Corp. (Pennsylvania Monthly Summary Employment Report, June) | 26 employees, 724 hours worked through June 30, 2009 (Pennsylvania Monthly Summary Employment Report, June) |
| Pennsylvania, Clearfield | Resurfacing and safety and drainage improvements on State Route 219 from Chestnut Grove to Anderson Creek in Brady and Bloom Townships Funds Allocated: $3,562,943 |
Construction started. (Pennsylvania Monthly Summary Employment Report, June) Received Notice to Proceed 4/20/2009 (U.S. DOT, July 17, 2009) | New Enterprise Stone & Lime Co., Inc. (Pennsylvania Monthly Summary Employment Report, June) | 85 employees, 5904 hours worked through June 30, 2009. (Pennsylvania Monthly Summary Employment Report, June) |
| Pennsylvania, Clarion | Preservation of State Route 66 McGregor Road Bridge over Little Piney Creek in Limestone Township Funds Allocated: $860,000 |
Construction started. (Pennsylvania Monthly Summary Employment Report, June) Received Notice to Proceed 5/4/2009 (U.S. DOT, July 17, 2009) | Francis J. Palo, Inc. (Pennsylvania Monthly Summary Employment Report, June) | 49 employees, 2246 hours worked through June 30, 2009 (Pennsylvania Monthly Summary Employment Report, June) |
| Pennsylvania, Bradford | Rehabilitation of State Route 187 over the Susquehanna River in Asylum and Wysox Townships Funds Allocated: $1,025,483 |
Issued Notice to Proceed 7/21/2009 (US DOT, August 7, 2009) | NA. (Pennsylvania Monthly Summary Employment Report, June) | |
| Pennsylvania, Greene | Replacement of State Route 18 over Branch of Browns Run in Morris Township Funds Allocated: $1,200,000 |
Awarded. Estimated construction start date is August 17, 2009. | Frank Gavlik & Sons, Inc. | NA (Pennsylvania Monthly Summary Employment Report, June) |
| Pennsylvania, Schuylkill | Replacement of precast bridge parapets Funds Allocated: $11,250 |
Estimated start date is September 16, 2009 | NA (Pennsylvania Monthly Summary Employment Report, June) | |
| Pennsylvania, Dauphin | Resurfacing of Interstate 83 from south of Union Deposit Road interchange to Bridge over Valley Road in Lower Paxton Township Funds Allocated: $2,970,447 |
Issued Notice to Proceed 7/27/2009 (US DOT August 7, 2009) | NA (Pennsylvania Monthly Summary Employment Report, June) | |
| Pennsylvania, Crawford | Resurfacing of Interstate 79 from milepost 136 to milepost 141 in Greenwood and Union Townships Funds Allocated: $4,542,712 |
Awarded. Estimated start date is August 10, 2009. | NA (Pennsylvania Monthly Summary Employment Report, June) | |
| Pennsylvania, Susquehanna | Rehabilitation of State Route 2040 over Lackawanna River in Uniondale Borough Funds Allocated: $1,503,255 |
Estimated start date is August 24, 2009 | NA (Pennsylvania Monthly Summary Employment Report, June) | |
| Pennsylvania, Lycoming | Resurfacing of State Route 2014 from Montour Street to Fairfield Road in Montoursville Borough Funds Allocated: $593,498 |
Received Notice to Proceed 06/01/2009 (U.S. DOT, July 17, 2009) | Glenn O. Hawbaker, Inc. (Pennsylvania Monthly Summary Employment Report, June) | NA. (Pennsylvania Monthly Summary Employment Report, June) |
| Pennsylvania, Westmoreland | Preservation of Walworth Bridge on US Route 30 in South Greensburg and Southwest Greensburg Boroughs Funds Allocated: $2,000,000 |
Received Notice to Proceed 07/13/2009 (U.S. DOT, July 17, 2009) | NA. (Pennsylvania Monthly Summary Employment Report, June) | |
| Pennsylvania, Allegheny | Bridge Restoration and approach work of Ft. Duquesne Bridge in City of Pittsburgh Funds Allocated: $26,190,521
|
Start date: 2009-08-03. More info | Trumbull Corporation awarded contract for $23,372,232. Inspection will be done by M.J. Mctish And Associates, Inc. for $2,131,786. | NA. (Pennsylvania Monthly Summary Employment Report, June) |
| Pennsylvania, Wayne | Preservation of State Route 4031 bridge over Johnson Creek in Mount Peasant Township Funds Allocated: $143,000 |
Work started. (Pennsylvania Monthly Summary Employment Report, June) Received Notice to Proceed Z046218 (U.S. DOT, July 17, 2009) | Amstar of Western New York, Inc. (Pennsylvania Monthly Summary Employment Report, June) | State/gov 1 employee, 3 hours worke.d (Pennsylvania Monthly Summary Employment Report, June) |
| Puerto Rico, Aguadilla | Bridge Replacement Num. 763, PR-2, km. 127.4 Funds Allocated: $7,396,021 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Rhode Island, Providence | Replacement of all signage on Route 37 from Post Rd./Route 1 in Warwick to Natick Ave. in Cranston (3.2 miles). Funds Allocated: $3,315,933 |
Liddell Brothers, Inc. is the apparent low bidder at $2,734,378.80. It was submitted but not yet awarded. We anticipate award this week. (Heidi Cote, Rhode Island DOT, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | ||
| Rhode Island, Washington | Resurfacing of Kingstown Rd./Route 138 from Beaver River Rd. to 660 feet west of Route 112 (2 miles). Funds Allocated: $3,015,646 |
The contract was awarded on 7/20, but construction has not yet begun. (Heidi Cote, Rhode Island DOT, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Cardi (Heidi Cote, Rhode Island DOT, August 3, 2009) | NA |
| Rhode Island, Statewide | Installation of radar-based vehicle detectors, at same location as existing traffic cameras, to collect data on traffic volume, speeds. The new detectors provide alerts to TMC operators to announce i Funds Allocated: $505,203 |
The project is under construction. (Heidi Cote, Rhode Island DOT, August 3, 2009) Received Notice to Proceed 5/8/2009 (U.S. DOT, July 17, 2009) | Arden Engineering (Heidi Cote, Rhode Island DOT, August 3, 2009) | |
| Rhode Island, Washington | I-95 Resurfacing from the CT State Line to Exit 3, Richmond & Hopkinton (Engineer: Preiss) STIMULUS FUNDING Funds Allocated: $12,551,712 |
The project is under construction. (Heidi Cote, Rhode Island DOT, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | D’Ambra (Heidi Cote, Rhode Island DOT, August 3, 2009) | Week #1- W/E 7/18/09: Average employees for the week: 8 per night (based on a 5-night work week); Week #2 – W/E 7/25/09:Average employees for the week: 24 per night (based on a 5-night work week); Week #3 – W/E 8/01/09:Average Employees for the week: 35 per night (based on a 5 night work week) (Heidi Cote, Rhode Island DOT, August 3, 2009) |
| South Carolina, Statewide | 14.1 miles of markings Funds Allocated: $267,323 |
Let 4/28/09 Awarded 5/18/09. No work has started. (South Carolina DOT, Peter Poore, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Oglesby Construction Inc. (South Carolina DOT, Peter Poore, August 3, 2009) | NA (South Carolina DOT, Peter Poore, August 3, 2009) |
| South Carolina, Berkeley | Pavement Reconstruction/Rehab Funds Allocated: $1,914,025 |
Let 4/28/09 Awarded 5/18/09. Work has not started. (South Carolina DOT, Peter Poore, August 3, 2009) | Sanders Brothers Construction Co., Inc. (South Carolina DOT, Peter Poore, August 3, 2009) | NA (South Carolina DOT, Peter Poore, August 3, 2009) |
| South Carolina, Lexington | Pavement Reconstruction/Rehab Funds Allocated: $3,273,380 |
Let 5/12/09 Awarded 6/5/09. Work has not started. (South Carolina DOT, Peter Poore, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | REA Construction LLC. (South Carolina DOT, Peter Poore, August 3, 2009) | NA (South Carolina DOT, Peter Poore, August 3, 2009) |
| South Dakota, Perkins | Asphalt Conc Surfacing Funds Allocated: $4,302,829 |
Awarded. (Amy Brady, South Dakota DOT, August 4, 2009) Received Notice to Proceed 04/01/2009 (U.S. DOT, July 17, 2009) | Anderson Western (Amy Brady, South Dakota DOT, August 4, 2009) | 0 employees worked 0 hours through June 30, 2009 (Amy Brady, South Dakota DOT, August 4, 2009) |
| South Dakota, Lyman | Asphalt Concrete Surfacing Funds Allocated: $1,303,170 |
Construction started. (Amy Brady, South Dakota DOT, August 4, 2009) Received Notice to Proceed 03/27/2009 (U.S. DOT, July 17, 2009) | Asphalt Paving & Materials (Amy Brady, South Dakota DOT, August 4, 2009) | 9 employees worked 34 hours through June 30, 2009 (Amy Brady, South Dakota DOT, August 4, 2009) |
| State, County | Project Description Funds Allocated: Stimulus Funds Obligated*
|
Project Status | Company Awarded Contract | # of Hours Worked/Month |
| Tennessee, Giles | Bridge over the West Fork of Shoal Creek (LM 0.07) Funds Allocated: $273,702 |
Let 3/20/09, awarded 3/27/09, and issued Notice to Proceed 4/20/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | RaCon, Inc. - Tennessee. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 2862 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Hardeman | Bridge over Clover Creek (LM 2.04) Funds Allocated: $754,281 |
Let 3/20/09, awarded 3/27/09, and issued Notice to Proceed 4/20/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 04/20/2009 (U.S. DOT, July 17, 2009) | Ford Construction Company. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 4027 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Carroll | Bridges over the Big Sandy River LM 7.64 and Overflow LM 7.56 Funds Allocated: $1,802,813 |
Let 3/20/09, awarded 3/27/09, and issued Notice to Proceed 4/20/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009)Received Notice to Proceed 04/20/2009 (U.S. DOT, July 17, 2009) | Mountain States Contractors, LLC. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 6878 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Anderson | BRIDGE OVER LITTLE DISMAL CREEK, LM 0.96 NEAR CLINTON Funds Allocated: $209,099 |
Let 5/08/09, awarded 5/14/09, and issued Notice to Proceed 5/27/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 05/27/2009 (U.S. DOT, July 17, 2009) | Bell & Associates Construction. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 17 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Madison | BRIDGES OVER BRANCHS, LM 1.46 AND LM 1.51 Funds Allocated: $315,464 |
Let 5/08/09, awarded 5/14/09, issued Notice to Proceed 6/11/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 06/11/2009 (U.S. DOT, July 17, 2009) | King Construction Company, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 537 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Blount | BRIDGE OVER NINE MILE CREEK, LM 0.01 Funds Allocated: $1,386,644 |
Let 5/08/09, awarded 5/1409, and issued Notice to Proceed 5/29/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 05/29/2009 (U.S. DOT, July 17, 2009) | Mountain States Contractors, LLC. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 1374 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Robertson | FROM SR-49 TO NEAR NEW CUT ROAD Funds Allocated: $797,103 |
Let 5/08/09, awarded 5/20/09, and issued Notice to Proceed 5/28/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | Eubank Asphalt Paving & Sealing. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 3807 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Clay | FROM EAST END OF CUMBERLAND RIVER BRIDGE TO SR-53 Funds Allocated: $318,728 |
Let 5/08/09, awarded 5/20/09, and issued Notice to Proceed 6/03/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 06/03/2009 (U.S. DOT, July 17, 2009) | Highways, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Madison | FROM SOUTH OF LOWER BROWNSVILLE RD TO BRIDGE OVER I-40 Funds Allocated: $449,372 |
Let 5/08/09, awarded 5/20/09, and issued Notice to Proceed 6/05/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | Ford Construction Company. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Williamson | FROM MARSHALL COUNTY LINE TO RUTHERFORD COUNTY LINE Funds Allocated: $122,319 |
Let 5/08/09, Awarded 5/20/09, and Issued Notice to Proceed 6/05/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 06/05/2009 (U.S. DOT, July 17, 2009) | Wright Paving Contractors, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 20 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Madison | FROM POPLAR CORNER ROAD TO BRIDGE OVER OLD SR-20 Funds Allocated: $1,619,040 |
Let 5/08/09, Awarded 5/20/09, and Issued Notice to Proceed 6/11/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009). Received Notice to Proceed 06/11/2009 (U.S. DOT, July 17, 2009) | Delta Contracting Company, LLC. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 2516 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Maury | FROM GILES COUNTY LINE TO SOUTH OF SR-50 Funds Allocated: $1,609,573 |
Let 5/08/09, awarded 5/20/09, and issued Notice to Proceed 6/11/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009)Received Notice to Proceed 06/11/2009 (U.S. DOT, July 17, 2009) | LoJac Enterprises, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 1028 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Loudon | FROM WEST OF SR-73 TO WEST OF SR-1 Funds Allocated: $909,796 |
Let 5/08/09, Awarded 5/20/09, and Issued Notice to Proceed 6/12/2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009)Received Notice to Proceed 06/12/2009(U.S. DOT, July 17, 2009) | APAC-Atlantic, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 34 hours worked through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Washington | FROM SOUTH OF SHADDEN ROAD TO NORTH OF I-26 Funds Allocated: $526,000 |
Let 6/12/09, awarded 6/18/09, and issued Notice to Proceed 7/15/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | Summers-Taylor, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Marion | FROM SR-27/150 TO TENNESSEE RIVER BRIDGE Funds Allocated: $2,748,000 |
Let 6/12/09, awarded 6/18/09, and issued Notice to Proceed 7/15/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 07/15/200 (U.S. DOT, July 17, 2009) | Highways, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | 0 hours through June 30, 2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Tipton | BRIDGE OVER DRAINAGE CANAL, LM 1.17 Funds Allocated: $211,000 |
Let 6/12/09, awarded 6/18/09, and issued Notice to Proceed 7/15/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 07/15/2009 (U.S. DOT, July 17, 2009) | Rose Construction, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Washington | FROM LEGION STREET TO SR-34(WB) AND FROM SR-34 TO LEGION STREET (EB) Funds Allocated: $827,195 |
Let 6/12/09, awarded 6/18/09, and issued Notice to Proceed 7/15/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 07/15/2009 (U.S. DOT, July 17, 2009) | Summers-Taylor, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Knox | FROM PARKSIDE DRIVE TO JAMESTOWN BOULEVARD IN FARRAGUT Funds Allocated: $2,355,370 |
Let 6/12/09, awarded 6/18/09, and issued Notice to Proceed 7/15/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009)Received Notice to Proceed 07/15/2009 (U.S. DOT, July 17, 2009) | APAC-Atlantic, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Van Buren | FROM WARREN COUNTY LINE TO WHITE COUNTY LINE Funds Allocated: $321,330 |
Let 6/12/09, awarded 6/18/09, and issued Notice to Proceed 7/15/2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | Highways, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Carter | FROM UNICOI COUNTY LINE TO SR-37 Funds Allocated: $282,000 |
Let 6/12/09, awarded 6/18/09, and issued Notice to Proceed 7/17/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 07/17/2009 (U.S. DOT, July 17, 2009) | Summers-Taylor, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Macon | FROM LAFAYETTE CITY LIMITS TO NEAR BUTLER ROAD Funds Allocated: $1,252,325 |
Let 6/12/09, awarded 6/18/09, and then issued Notice to Proceed 7/13/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 07/13/2009 (U.S. DOT, July 17, 2009) | Rogers Group, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Hamilton | WELCOME CENTER NEAR GEORGIA STATE LINE Funds Allocated: $130,000 |
Let 6/12/09, awarded 6/19/09, issued Notice to Proceed 7/15/09. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) Received Notice to Proceed 07/15/2009 (U.S. DOT, July 17, 2009) | CHW Landscaping, Inc. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Trousdale | HARTSVILLE/TROUSDALE COUNTY COURTHOUSE REHABILITATION AND SIDEWALK IMPROVEMENTS - PHASE II Funds Allocated: $548,452 |
Let 7/23/2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | Contract not yet awarded. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Tennessee, Bledsoe | FROM 90 DEGREE TURN TO RHEA COUNTY LINE Funds Allocated: $79,377
|
Project let on 6/12/2009, Awarded 6/18/2009, and issued Notice to Proceed on 7/16/2009. (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | Thomas Brothers Construction Company (Julie Oaks, Tennessee Public Information Officer, July 31 2009) | NA (Julie Oaks, Tennessee Public Information Officer, July 31 2009) |
| Texas, Waller | FM 362 Fr. BU US 290 To. 1.943 MI S OF BU 290H ;ADD SHOULDERS AND ACP OVERLAY Funds Allocated: $1,560,717
|
Advertised 4/01/09. Awarded 5/15/09. Issued Notice to Proceed 6/02/09. (Texas Monthly Summary Employment Report, June) | Durwood Greene Construction Co. (Texas Monthly Summary Employment Report, June) | NA (Texas Monthly Summary Employment Report, June) |
| Texas, Harris | FM 1093Fr. DAIRY ASHFORD To. IH 610 ;2" PLANING, 2" ACP OVERLAY, PAVEMENT MARKINGS Funds Allocated: $8,700,000
|
Advertised 4/01/09. Awarded 5/21/09. Issued Notice to Proceed 6/05/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 06/05/2009 (U.S. DOT, July 17, 2009) | Durwood Greene Construction Co. (Texas Monthly Summary Employment Report, June) | NA (Texas Monthly Summary Employment Report, June) |
| Texas, Kerr | FM 1350Fr. 0.1 MILE W. OF GUADALUPE RIVER To. 0.2 MILE E. OF GUADALUPE RIVER ;REMOVE & REPLACE GUADALUPE RVR BRIDGE & RECONST APPROACHES Funds Allocated: $1,323,035 |
Advertised 4/01/09. Awarded 5/21/09. issued Notice to Proceed 6/09/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 06/09/2009 (U.S. DOT, July 17, 2009) | ACME Bridge Company (Texas Monthly Summary Employment Report, June) | NA (Texas Monthly Summary Employment Report, June) |
| Texas, Waller | FM 1458Fr. FM 359 To. BRAZOS RIVER ;SUBGRADE WIDENING, SEAL COAT, ACP O/L AND PAVEMENT MARKINGS Funds Allocated: $3,040,000
|
Advertised 4/01/09. Awarded 5/22/09. Issued Notice to Proceed 6/08/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 06/08/2009 (U.S. DOT, July 17, 2009) | Durwood Greene Construction Co. (Texas Monthly Summary Employment Report, June) | NA. (Texas Monthly Summary Employment Report, June) |
| Texas, Wharton | US 90A Fr. 3.3 MI E OF LISSIE To. FORT BEND C/L ;SEAL COAT, ACP & SET Funds Allocated: $5,800,000 |
Advertised 4/01/09. Awarded 5/28/09. Issued Notice to Proceed 6/16/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 06/16/2009 (U.S. DOT, July 17, 2009) | Durwood Greene Construction Co. (Texas Monthly Summary Employment Report, June) | NA (Texas Monthly Summary Employment Report, June) |
| Texas, Martin | SH 137 Fr. 7 MI SOUTH OF DAWSON CO.LINE To. DAWSON CO. LINE ;PAVEMENT STRUCTURE RESTORATION Funds Allocated: $2,307,629 |
Advertised 4/01/09. Awarded 5/29/09. Issued Notice to Proceed 6/05/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 06/05/2009 (U.S. DOT, July 17, 2009) | Jones Bros. Dirt & Paving Contractors (Texas Monthly Summary Employment Report, June) | NA (Texas Monthly Summary Employment Report, June) |
| Texas, Starr | FM 509 Fr. FM 106 To. BUSINESS 77 ;OVERLAY Funds Allocated: $9,058,283 |
Advertised 4/01/09. Awarded 6/02/09. Issued Notice to Proceed 6/22/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 06/10/2009 (U.S. DOT, July 17, 2009) | Ballenger Construction Comp. (Texas Monthly Summary Employment Report, June) | NA (Texas Monthly Summary Employment Report, June) |
| Texas, Hidalgo | SH 107 Fr. FM 2128 To. US 281 ;FULL DEPTH REPAIR BOTH LANES Funds Allocated: $3,770,821 |
Advertised 4/01/09. Awarded 6/03/09. Issued Notice to Proceed 6/22/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 06/10/2009 (U.S. DOT, July 17, 2009) | Ballenger Construction Comp. (Texas Monthly Summary Employment Report, June) | NA (Texas Monthly Summary Employment Report, June) |
| Texas, Childress | CR Fr. CR 25 @DRAW To. . ;REPLACEMENT OF EXISTING BRIDGE FACILITY Funds Allocated: $134,256 |
Advertised 4/01/09. Awarded 6/0909. Issued Notice to Proceed 6/22/09. (Texas Monthly Summary Employment Report, June)Received Notice to Proceed 6/22/2009 (U.S. DOT, July 17, 2009) | Baker Bridge, L.P. (Texas Monthly Summary Employment Report, June) | NA (Texas Monthly Summary Employment Report, June) |
| Texas, Caldwell | SH 80 Fr. 0.35 MILES WEST OF HAYS C/L FM 20 PAVEMENT REPAIR,MILL,SEAL & OVERLAY Funds Allocated: $6,000,012
|
Advertised 4/16/09. Awarded 6/15/09. Issued Notice to Proceed 7/6/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 07/06/2009 (U.S. DOT, July 17, 2009) | Angel Brothers Enterprises, LTD. (Texas Monthly Summary Employment Report, June) | NA (Texas Monthly Summary Employment Report, June) |
| Texas, Waller | FM 1098 Fr. BU 290 To. US 290; WIDEN TO 4-LANE DIVIDED URBAN SECTION Funds Allocated: $3,930,000 |
Advertised 6/16/09. (Texas Monthly Summary Employment Report, June) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Texas, Grayson | FM 691 Fr. 1,520' WEST OF US 75 C/L To. 2,661' EAST OF US 75 C/L ;WIDEN EXISTING HIGHWAY TO INCLUDE TURN LANES, TURN BAYS AND Funds Allocated: $3,000,000 |
Advertised 6/16/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 06/29/2009 (U.S. DOT, July 17, 2009) | NA (Texas Monthly Summary Employment Report, June) | |
| Texas, Brazos | FM 1179Fr. 0.1 MILE EAST OF FM 158 To. THE SH 6 NORTHBOUND FRONTAGE ROAD ;OVERLAY CONSISTING OF A SURFACE TREATMENT, HMA OVERLAY AND Funds Allocated: $420,000 |
Construction started. Advertised 4/01/09. Awarded 5/07/09. Issued Notice to Proceed 5/19/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 05/19/2009 (U.S. DOT, July 17, 2009) | Knife River Corp. (Texas Monthly Summary Employment Report, June) | 63% completed as of June 30, 2009. (Texas Monthly Summary Employment Report, June) |
| Texas, Gregg | US 259 Fr. IH 20 N FRONTAGE RD, N To. US 80, IN LONGVIEW ;PLANE & RESURFACE ROADWAY Funds Allocated: $3,100,000 |
Construction started. Advertised 4/01/09. Awarded 5/07/09. Issued Notice to Proceed 5/19/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 05/19/2009 (U.S. DOT, July 17, 2009) | Knife River Corp - South (Texas Monthly Summary Employment Report, June) | 18.8% complete as of June 30, 2009 (Texas Monthly Summary Employment Report, June) |
| Texas, Grayson | FM 902 Fr. SH 289 To. US 75 WEST FRONTAGE ROAD ;REHABILITATE EXISTING ROADWAY Funds Allocated: $3,132,178 |
Construction started. Advertised 4/01/09. Awarded 5/12/09. Issued Notice to Proceed 5/28/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 05/28/2009 (U.S. DOT, July 17, 2009) | D.L. Lennon Incorporated Contractor (Texas Monthly Summary Employment Report, June) | 7.4% completed as of June 30, 2009. (Texas Monthly Summary Employment Report, June) |
| Texas, Grayson | FM 121 Fr. US 377 To. SH 289 ;REHABILITATE EXISTING ROADWAY Funds Allocated: $4,730,000 |
Construction started. Advertised 4/01/09. Awarded 5/20/09. Issued Notice to Proceed 6/02/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 06/02/2009 (U.S. DOT, July 17, 2009) | A.K. Gillis & Sons, Inc. (Texas Monthly Summary Employment Report, June) | 3.6% complete as of June 30, 2009. (Texas Monthly Summary Employment Report, June) |
| Texas, Montgomery | LP 494 Fr. US 59 To. KINGWOOD DRIVE ;WIDEN SUBGRADE, OCST AND ACP OVERLAY Funds Allocated: $5,299,527 |
Construction started. Advertised 4/01/09. Awarded 5/20/09. Issued Notice to Proceed 6/02/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 06/02/2009 (U.S. DOT, July 17, 2009) | Smith & Company (Texas Monthly Summary Employment Report, June) | 3% complete as of June 30, 2009 (Texas Monthly Summary Employment Report, June) |
| Texas, Jim Wells | BU 281RFr. FM 1352 To. FM 1930 ;OVERLAY ROADWAY Funds Allocated: $650,000
|
Construction started. Advertised 4/01/09. Awarded 5/22/09. Issued Notice to Proceed 6/09/09. (Texas Monthly Summary Employment Report, June) | Bay LTD (Texas Monthly Summary Employment Report, June) | 11.8% complete as of June 30, 2009 (Texas Monthly Summary Employment Report, June) |
| Texas, Harris | US 290 Fr. SH 6 To. FM 529 ;CRACK & SPALL REPAIR, FULL DEPTH CONCRETE REPAIR (IN Funds Allocated: $216,310
|
Construction started. Advertised 4/01/09. Awarded 5/28/09. Issued Notice to Proceed 6/04/09. (Texas Monthly Summary Employment Report, June)Received Notice to Proceed 06/04/2009 (U.S. DOT, July 17, 2009) | Main-Lane Industries, LTD (Texas Monthly Summary Employment Report, June) | 23.3% complete as of June 30, 2009 (Texas Monthly Summary Employment Report, June) |
| Texas, Mason | SH 29 Fr. MENARD C/L To. W OF US 377; SEAL COAT Funds Allocated: $1,642,100 |
Construction started. Advertised 4/16/09. Awarded 6/30/09. Issued Notice to Proceed 7/02/09. (Texas Monthly Summary Employment Report, June) Received Notice to Proceed 07/02/2009 (U.S. DOT, July 17, 2009) | Cox Paving Company L.P. (Texas Monthly Summary Employment Report, June) | 25.9% complete as of June 30, 2009 (Texas Monthly Summary Employment Report, June) |
| Utah, Salt Lake | ROTO-MILL AND HOT MIX ASPHALT OVERLAY Funds Allocated: $2,000,000 |
Received Notice to Proceed 04/27/2009 (U.S. DOT, July 17, 2009) | ||
| Utah, Summit | Road - Asphalt Pavement Rehabilitation Funds Allocated: $600,000 |
Received Notice to Proceed 05/05/2009 (U.S. DOT, July 17, 2009) | ||
| Utah, Statewide | CONSTRUCT SAFE SIDEWALK Funds Allocated: $100,000 |
Received Notice to Proceed 06/17/2009 (U.S. DOT, July 17, 2009) | ||
| Utah, Utah | BIKE / PED WIDEN SHOULDERS Funds Allocated: $263,686 |
Received Notice to Proceed 06/24/2009 (U.S. DOT, July 17, 2009) | ||
| Utah, Summit | WILDLIFE CONNECTIVITY Funds Allocated: $395,000 |
Received Notice to Proceed 06/25/2009 (U.S. DOT, July 17, 2009) | ||
| Utah, Weber | FIBER EXPANSION - DESIGN & INTALL FIBER/CONDUIT ON I-15 Funds Allocated: $974,999 |
Bid Opened June 6, NTP Awarded July 11 (Scott Thompson, UT DOT) | Contractor Americom Technology | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Utah, Salt Lake | CONSTRUCT SAFE SIDEWALK Funds Allocated: $200,000 |
Advertised, awarded and issued Notice to Proceed (Utah DOT). | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Utah, Salt Lake | ROAD- WIDEN RAMPS , PROVIDE DUAL EXIT LANES Funds Allocated: $2,200,228 |
Bid Opened June 20, NTP Awarded August 1 (Scott Thompson, UT DOT) | Contractor Reynolds Brothers | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Utah, Salt Lake | 4" rotomill and overlay Funds Allocated: $835,000 |
Bid Opened July 11, NTP awarded July 25 (Scott Thompson, UT DOT) | Contractor Kilgore Pavement Maintenance | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Utah, Tooele | NEW CONSTRUCTION Funds Allocated: $3,500,358 |
Bid Opened July 11, NTP awarded July 25 (Scott Thompson, UT DOT) | Contractor Kilgore Pavement Maintenance | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Utah, Weber | ENHANCEMENT - BIKE & PEDESTRAIN TRAIL Funds Allocated: $359,000 |
Advertised and awarded. NTP awarded August 1, 2009 (Scott Thompson, UT DOT) | Contractor Post Construction | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Virginia, Culpeper | Asphalt resurfacing Funds Allocated: $4,625,261
|
Received Notice to Proceed 06/16/2009 (U.S. DOT, July 17, 2009) | Chemumg Contracting Corporation (Virginia DOT, Mr. Bill Bailey from the Materials Dept.) | |
| Virginia, Statewide | Resurfacing and guardrail items Funds Allocated: $2,951,120 |
Received Notice to Proceed 06/22/2009 (U.S. DOT, July 17, 2009) | ||
| Virginia, Statewide | ARRA BRAC FT EUSTIS RTE 105 - CN OF PARALLEL LANES (WB) Funds Allocated: $27,731,101
|
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Virginia, Chesapeake City | ARRA- CIty of Chesapeake, Dismal Swamp Canal Trail Funds Allocated: $1,300,000
|
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Virginia, James City | Asphalt Resurfacing (James City County - Rtes. I64, 60, 143 and 321) Funds Allocated: $7,311,083 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Virginia, Prince Edward | Pavement rehabilitation, guardrail replacement, drainage structures. Funds Allocated: $4,429,997 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Virginia, Smyth | ARRA - Paving, Milling and Guardrail Upgrade Funds Allocated: $1,836,741 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Virginia, Brunswick | ARRA - Tobacco Heritage Trail Funds Allocated: $6,000,000 |
NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | ||
| Washington, King | ARRA - NORTHEAST 8TH STREET TO SR520 - BRAIDED RAMPS (DESIGN / BUILD) SR405-3.11 TO 4.61 MILES SOUTH OF JUNCTION SR908. Funds Allocated: $30,000,000
|
Advertised for bid 3/03/09. (WA DOT, July 31, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Washington, Kittitas | ARRA - Kittitas Co., Guardrail Hazard Elimination FROM:various TO:various LEN: 0.000MI Funds Allocated: $530,000 |
Advertised for bid 6/18/09 (WA DOT) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Washington, Thurston | ARRA - Thurston Co. ,Old Hwy 99 Turn Ln. & Prairie Cr Br FROM:203rd TO:600' N of Sargent LEN: 0.400MI Funds Allocated: $1,330,000 |
Advertised for bid 6/23/09. (WA DOT, July 31, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Washington, Mason | Place 0.15 ft of HMA overlay on McEwan Prairie Road. Recessed pavement markers, shoulder dressing, striping and miscellaneous traffic markings will be included in the project. Funds Allocated: $350,000 |
Advertised for bid 6/25/09. (WA DOT, July 31, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Washington, Franklin | ARRA - Franklin Co., R-170 Land Slide Area FROM:Sagehill I/S TO:Klamath Road I/S LEN: 2.810MI Funds Allocated: $750,000 |
Advertised for bid 6/25/09. (WA DOT, July 31, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Washington, Grant | ARRA - MOSES LAKE TO EPHRATA - PASSING LANE AND SAFETY SR17-VICINITY JUNCTION SR282 TO 18.60 MILES SOUTH. SR282-ENTIRE ROUTE. Funds Allocated: $6,088,296 |
Advertised for bid 7/0309 (WA DOT). Received Notice to Proceed 04/23/2009 (U.S. DOT, July 17, 2009) | ||
| Washington, Whatcom | ARRA - Ferndale ,2nd Avenue Extension FROM:Wash/2nd I/S TO:Portal Way/I-5 I/C LEN: 0.500MI Funds Allocated: $1,541,000 |
Advertised for bids 7/08/09. (WA DOT, July 31, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Washington, Klickitat | ARRA - Klickitat Co., South Columbus Overlay FROM:Godendale City Limit TO:Hocter Road LEN: 2.390MI Funds Allocated: $521,656 |
Advertised for construction and awarded July 21, 2009 (Gordon Kelsey, PE. Director/County Engineer, Klickitat County, Washington, August 3, 2009) | Granite NW, Inc., of Watsonville, CA (Gordon Kelsey, PE. Director/County Engineer, Klickitat County, Washington, August 3, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Washington, Whatcom | ARRA - Bellingham, 2009 Pedestrian Crossing Safety FROM:various TO:various LEN: 0.000MI Funds Allocated: $349,948 |
Awarded (WA DOT, July 31, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Colacurcio Brothers Construction of Blaine, Washington (Freeman Anthony P.E., Project Engineer - City of Bellingham, August 3, 2009) | We've had two weeks of work so far and the project has employed approximately 20 people (including Prime Contractor and Subcontractors, not including the City Engineer and Inspector) and approximately 350 work hours are on the books. (Freeman Anthony P.E., Project Engineer - City of Bellingham, August 3, 2009) |
| Washington, Spokane | ARRA - Spokane, Fish Lake Trail FROM:Fish Lk/S View Acres TO:Scribner/Sunset Hwy LEN: 7.000MI Funds Allocated: $778,317 |
The construction started on July 7, 2009 (Ken Brown, Principal Engineer - Construction Management, WA DOT) Awarded (WA DOT, July 31, 2009) | Wesslen Construction, Inc. | 20% of the work is complete, 80% remains. (Ken Brown, WA DOT, Director of Engineering Services, City of Spokane) |
| Washington, Spokane | ARRA - Spokane Co., Rutter Parkway Bridge Rehab FROM: TO: LEN: 0.044MI Funds Allocated: $448,329 |
Awarded (WA DOT, July 31, 2009) | NA Degerstrom | The month of June reported 7 employees a total of 75 hours and $3,174.00 in wages paid. (Craig McDaniel, WA DOT) |
| Washington, Island | ARRA - Island Co., Ault Field Road Widening FROM: Oak Harbor Rd. TO:Goldie Road LEN: 0.240MI Funds Allocated: $1,500,000 |
Awarded. (WA DOT, July 31, 2009 ) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Kreig Construction | NA |
| Washington, Benton | ARRA - Kennewick, Columbia Overlook - Phase 1 FROM:Volland St TO:Neel St. LEN: 0.000MI Funds Allocated: $140,000
|
Awarded. (WA DOT, July 31, 2009) Received Notice to Proceed 06/22/2009 (U.S. DOT, July 17, 2009) | ||
| Washington, San Juan | ARRA - San Juan Co., Fisherman Bay Road MP 0.43 - 2.19 FROM:Hummel Lake Rd. TO:Military Rd. LEN: 1.760MI Funds Allocated: $416,620 |
Awarded. (WA DOT, July 31, 2009) Awarded. Construction has not yet begun. (Stan Matthews, San Juan County Web/Communications, WA DOT, August 3, 2009) | Ramo Construction (Stan Matthews, San Juan County Web/Communications, WA DOT, August 3, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| Washington, Snohomish | ARRA - Everett, Holly Drive Non-Motorized FROM:4th Ave. West TO:92nd Street SW LEN: 0.200MI Funds Allocated: $447,886 |
Awarded. (WA DOT, July 31, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009 / WA DOT Gordon Larson, August 3, 2009) | T.E. Briggs Construction Company of Edmonds, WA (Gordon Larson, WA DOT, August 3, 2009) | NA |
| Washington, Clark | ARRA - Washougal, SR 14 Pedestrian Tunnel FROM:500' E of 15th St TO: LEN: 0.000MI Funds Allocated: $594,366 |
Awarded. (WA DOT, July 31, 2009) | Coffman Excavating LLC | The month of June reported 4 employees a total of 120 hours and $3,348.00 in wages paid. (Craig McDaniel, WA DOT) |
| Washington, Pend Oreille | ARRA - JUNCTION SR211 TO NEWPORT - PAVING SR2-VICINITY JUNCTION SR211 TO THE IDAHO / WASHINGTON STATE LINE. Funds Allocated: $7,819,040 |
Construction due to start mid-July. Awarded. (WA DOT, July 31, 2009)Received Notice to Proceed 06/24/2009(U.S. DOT, July 17, 2009) | Inland Asphalt Company (WA DOT) | |
| Washington, Snohomish | ARRA-SR2 / MONROE CITY LIMIT TO SULTAN PAVING SR2-1.85 TO 7.08 MILES EAST OF JUNCTION SR522. Funds Allocated: $3,146,099 |
Construction started June 1, 2009 and is expected to be done in Winter 2009. (WA DOT, July 31, 2009) Received Notice to Proceed 05/28/2009 (U.S. DOT, July 17, 2009) | Lakeside Industries, Inc. | The first working day was June 1. For the month of June, 42 people were directly employed on this project, for a total of 895 hours. This includes prime contractor and subcontractor totals. The July report will be available after Aug. 10. (Meghan Soptich Pembroke, WA DOT, August 3, 2009) |
| Washington, Yakima | Overlay Existing Roadway from MP 0.94 to MP 1.93. Upgrade handicap ramps to current ADA standards. The work will involve overlaying approximately 4.5 lane miles with Hot Mix Asphalt and upgrades. Funds Allocated: $400,000 |
Construction started/almost complete. Awarded in April. (WA DOT, July 31, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Columbia Asphalt (WA DOT) | NA (WA DOT) |
| Washington, Kitsap | ARRA - Poulsbo, Viking Avenue - Phase II FROM:SR 305 TO:Finn Hill LEN: 0.660MI Funds Allocated: $3,800,000 |
Contract awarded (WA DOT, July 31, 2009). Received Notice to Proceed 06/23/2009 (U.S. DOT, July 17, 2009) | Stan Palmer Construction | |
| Washington, Whitman | ARRA - Whitman Co., Wawawai Road Overlay FROM:MP 13.96 TO:MP 19.40 LEN: 5.440MI Funds Allocated: $896,000 |
Contract awarded. (WA DOT, July 31, 2009) | Debco Construction | The month of June reported 26 employees a total of 448 hours and $13,549.00 in wages paid. (Craig McDaniel, WA DOT) |
| Washington, Statewide | ARRA - I-205 JUNCTION TO DIKE ROAD - MEDIAN CABLE I-5 - VICINITY JUNCTION I-205 TO 14.76 MILES NORTH. Funds Allocated: $2,711,330 |
Contract awarded. (Todd Lamphere, WA DOT, August 6, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Coral Construction Company. (Todd Lamphere, WA DOT, August 6, 2009) | NA. (Todd Lamphere, WA DOT, August 6, 2009) |
| Washington, Statewide | ARRA - STATEWIDE CENTERLINE RUMBLE STRIP - STATEWIDE - Funds Allocated: $200,000 |
This funding is for WSDOT to conduct preliminary engineering for all Centerline Rumble Strip projects associated with the ARRA funding. The construction contracts associated with this preliminary engineering are administered and funded under separate contracts statewide. (Todd Lamphere, WA DOT, August 6, 2009). No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Washington, Yakima | ARRA - VALLEY MALL BOULEVARD INTERCHANGE IMPROVEMENTS SR82-1.23 TO 1.83 MILES SOUTH OF JUNCTION SR24. Funds Allocated: $1,264,317 |
Will advertise bids in November (WA DOT, July 31, 2009) | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) | |
| Washington, Clallam | Reconstruct and widen existing road. Funds Allocated: $500,000 |
Contract was awarded to Lakeside Industries on July 7, 2009 (Craig McDaniel, WA DOT) | Lakeside Industries | NA (No Notice to Proceed issued yet (U.S. DOT, July 17, 2009)) |
| West Virginia, Nicholas | Resurfacing Funds Allocated: $1,532,400 |
Awarded 6/09/09. Notice to Proceed issued 7/07/09. (Brent Walker, West Virginia DOT, August 6, 2009) | WV Paving (Brent Walker, West Virginia DOT, August 6, 2009) | under constr. NTP 7/7 (Susan Watkins, Director, WVDOT) |
| West Virginia, Mingo | MINGO, US 119, / PIGEON CR. 0.11 MI. W. WV 65, LMC O/L. Funds Allocated: $462,000 |
Awarded 6/30/09. (Brent Walker, West Virginia DOT, August 6, 2009) | Velotta Company (Brent Walker, West Virginia DOT, August 6, 2009) | |
| West Virginia, Marshall | Bridge Replacement Funds Allocated: $1,962,400 |
Notice to Proceed awarded 5/28. (Brent Walker, West Virginia DOT, August 6, 2009) Received Notice to Proceed 05/28/2009 (U.S. DOT, July 17, 2009) | Ohio - West Virginia Excavating (Brent Walker, West Virginia DOT, August 6, 2009) | |
| West Virginia, Marshall | Resurfacing Funds Allocated: $4,584,100 |
Notice to Proceed awarded 5/28. (Brent Walker, West Virginia DOT, August 6, 2009) Received Notice to Proceed 5/6/2009 (U.S. DOT, July 17, 2009) | Kelly Paving (Brent Walker, West Virginia DOT, August 6, 2009) | 2,498 hours worked and 36 employees (Susan Watkins, Director, WVDOT) |
| West Virginia, Berkeley | Resurfacing Funds Allocated: $2,439,900 |
Notice to Proceed issued 7/01/09. Awarded 5/11/09. (Brent Walker, West Virginia DOT, August 6, 2009) | Jefferson Asphalt (Brent Walker, West Virginia DOT, August 6, 2009) | under constr. NTP 7/1 (Susan Watkins, Director, WVDOT) |
| Wisconsin, Milwaukee | 1.2 MILE NORTH of CTH PP Funds Allocated: $295,960 |
Not let yet. (Peg Schmitt, WI DOT, August 3, 2009) Received Notice to Proceed 06/05/2009 (U.S. DOT, July 17, 2009) | ||
| Wisconsin, Adams | TOWNS OF STRONGS PRAIRIE & MONROE Funds Allocated: $5,424,979 |
Contract not awarded yet. S&N Incorporated provided the low bid in the July 28 bid letting. (Peg Schmitt, WI DOT, August 3, 2009) No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | NA | |
| Wisconsin, Rock | BR RACCOON CREEK BRIDGE & APP'S Funds Allocated: $458,806 |
No Notice to Proceed issued yet (U.S. DOT, July 17, 2009) | Concrete Structures, Inc. (Peg Schmitt, WI DOT, August 3, 2009) | NA |
| Wisconsin, Brown | CN RAILROAD - STH 96 Funds Allocated: $6,900,000 |
Received Notice to Proceed 05/19/2009 (U.S. DOT, July 17, 2009) | Northeast Asphalt, Inc. (Peg Schmitt, WI DOT, August 3, 2009) | |
| Wisconsin, Kenosha | MAINLINE Funds Allocated: $5,007,481
|
Received Notice to Proceed 05/29/2009 (U.S. DOT, July 17, 2009) | Walsh Construction (Peg Schmitt, WI DOT, August 3, 2009) | |
| Wisconsin, Kenosha | MAINLINE Funds Allocated: $34,193,017
|
Received Notice to Proceed 05/29/2009 (U.S. DOT, July 17, 2009) | Walsh Construction (Peg Schmitt, WI DOT, August 3, 2009) | |
| Wisconsin, Manitowoc | TOWN OF MANITOWOC RAPIDS SILVER CK Funds Allocated: $199,108 |
Received Notice to Proceed 05/29/2009 (U.S. DOT, July 17, 2009) | Pheifer Brothers Construction Co. (Peg Schmitt, WI DOT, August 3, 2009) | |
| Wisconsin, Green Lake | OLD COUNTY A TO STH 44 Funds Allocated: $1,157,737 |
Received Notice to Proceed 06/04/2009 (U.S. DOT, July 17, 2009) | Northeast Asphalt Inc. (Peg Schmitt, WI DOT, August 3, 2009) | |
| Wisconsin, Wood | STH 13 TO USH 10 Funds Allocated: $3,492,605 |
Received Notice to Proceed 06/05/2009 (U.S. DOT, July 17, 2009) | Concrete Structures, Inc. (Peg Schmitt, WI DOT, August 3, 2009) | |
| Wyoming, Laramie | PED LIGHTS & DECORATIVE RAILING Funds Allocated: $953,556 |
Received Notice to Proceed 5/08/09. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) Received Notice to Proceed 05/08/2009 (U.S. DOT, July 17, 2009) | Reiman Corp. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) | 1 employee, 26 hours reported as of June 30, 2009. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) |
| Wyoming, Statewide | CHIP SEAL Funds Allocated: $2,653,752 |
Received Notice to Proceed 5/11/09. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) Received Notice to Proceed 05/11/2009 (U.S. DOT, July 17, 2009) | Northern Improvement Co. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) | NA. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) |
| Wyoming, Lincoln | CONSTRUCT RETAINING WALL Funds Allocated: $204,160 |
Received Notice to Proceed 5/20/09. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) Received Notice to Proceed 05/20/2009 (U.S. DOT, July 17, 2009) | Hout Fencing of Wyoming. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) | NA. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) |
| Wyoming, Goshen | RESTORATION & REHABILITATION Funds Allocated: $3,415,493 |
Received Notice to Proceed 5/20/09. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) Received Notice to Proceed 05/20/2009 (U.S. DOT, July 17, 2009) | Mountain Construction Co. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) | 6 employees, 962 hours reported as of June 30, 2009. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) |
| Wyoming, Uinta | MICROSURFACE Funds Allocated: $2,883,277 |
Received Notice to Proceed 6/10/09. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) | Geneva Rock Products. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) | NA. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) |
| Wyoming, Crook | MICROSURFACE Funds Allocated: $2,353,763 |
Received Notice to Proceed 6/10/09. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) | Reiman Corp. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) | 2 employees, 220 hours reported as of June 30, 2009. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) |
| Wyoming, Carbon | DEER UNDERPASS Funds Allocated: $1,551,431 |
Received Notice to Proceed 6/11/09. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) | Hout Fencing of Wyoming. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) | 3 employes, 476 hours reported as of June 30, 2009. (Ron Kisicki, Public Information Officer, WY DOT, July 31, 2009) |