NAVY INSTALLATION ID: DC317002431000

WASHINGTON NAVY YARD

washington, Washington, DC

Cost So Far

$40.6M

Money already spent on the evaluation and cleanup of hazardous sites.

Expected Additional Cost

$7.83M

The estimated amount of money needed for evaluation and cleanup of hazardous sites at this installation.

Expected Completion Date

2049

The date by which the DOD estimates cleanup of all sites will be complete. Long term monitoring may continue after this date.

33 Hazardous Sites

Below are the locations of hazardous sites associated with this military installation, according to the DOD. A site’s contamination may affect a much larger area, including public and private lands and the water supplies beneath them.

High Risk

Medium Risk

Low Risk

Risk Not Evaluated or Not Required

Response Complete

We haven't independently confirmed the location of every site. If you notice a site placed at the incorrect location, please contact us.

Not all sites in the DOD data include location information, so there may be sites listed below that are missing from the map. The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.

9 Active Sites

Sites where military cleanup actions are still ongoing. The risk level of a site refers to a relative risk assessment made by the DOD, which prioritizes the cleanup of sites that pose greatest threat to safety, human health, and the environment.

Site ID: UST 000111

WASHINGTON NAVY YARD

Underground Storage Tanks

Cost

$843K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Mar 2018

Contaminated Areas

Groundwater: High Risk

Contaminants: Benzene 100000.0 ppb

Soil: Low Risk

Contaminants: Ethylbenzene 0.02 ppb Toluene 0.52 ppb

See more details...

Site ID: UST 000001

WASHINGTON NAVY YARD

Underground Storage Tanks

Cost

$1.1M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Aug 2018

Contaminated Areas

Groundwater: High Risk

Contaminants: Ethylbenzene 10100.0 ppb Xylene (mixed) 33000.0 ppb Toluene 87200.0 ppb Benzene 1420000.0 ppb

Soil: Medium Risk

Contaminants: Benzene 250.0 ppb

See more details...

Site ID: SITE 00006

WASHINGTON NAVY YARD

Incinerator

Cost

Unknown

Final Cleanup Action

Sep 2016

Contaminated Areas

Soil: Medium Risk

Contaminants: Dibenz[ah]anthracene 0.33 ppb Indeno[1,2,3-cd]pyrene 1.1 ppb Benzo[a]pyrene 1.2 ppb Beryllium and compounds 1.3 ppb Benz(a)anthracene 1.6 ppb Benzo[b]fluoranthene 2.2 ppb Arsenic (noncancer) 31.1 ppb Lead 730.0 ppb

Groundwater: Low Risk

Contaminants: Benzene 2000.0 ppb Cadmium and compounds 5800.0 ppb Bis(2-ethylhexyl)phthalate 9000.0 ppb Beryllium and compounds 9800.0 ppb Methylene chloride 17000.0 ppb Nickel and compounds 232000.0 ppb Manganese and compounds 432000.0 ppb

Sediment (Human): Low Risk

Contaminants: Acenaphthylene- 0.1 ppb Acenaphthene 0.16 ppb Dibenz[ah]anthracene 0.32 ppb Naphthalene 0.49 ppb Fluorene 0.63 ppb Anthracene 0.72 ppb Mercury 1.2 ppb Benzo[a]pyrene 1.3 ppb Benzo[b]fluoranthene 1.4 ppb Benz(a)anthracene 1.6 ppb Chrysene 2.1 ppb Cadmium and compounds 2.4 ppb Phenanthrene 3.1 ppb Pyrene 3.3 ppb Fluoranthene 3.6 ppb Polychlorinated biphenyls (PCBs) 38.0 ppb Arsenic (noncancer) 52.6 ppb Nickel and compounds 84.7 ppb Zinc 230.0 ppb Trichlorobenzene, 1,2,4- 490.0 ppb Lead 567.0 ppb

Surface Water (Human): Low Risk

Contaminants: Polychlorinated biphenyls (PCBs) 2200.0 ppb Cadmium and compounds 7200.0 ppb Arsenic (noncancer) 65400.00000000001 ppb Lead 305000.0 ppb Manganese and compounds 990000.0 ppb

See more details...

Site ID: SITE 00011

WASHINGTON NAVY YARD

Incinerator

Cost

$1.44M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Oct 2015

This site is under ongoing monitoring until Sep 2026

Contaminated Areas

Soil: Medium Risk

Contaminants: Dibenz[ah]anthracene 3.9 ppb Benzo[k]fluoranthene 5.0 ppb Beryllium and compounds 5.4 ppb Indeno[1,2,3-cd]pyrene 7.1 ppb Benzo[a]pyrene 12.0 ppb Chrysene 13.0 ppb Benz(a)anthracene 15.0 ppb Benzo[b]fluoranthene 20.0 ppb Arsenic (noncancer) 33.2 ppb Lead 851.0 ppb

See more details...

Site ID: SITE 00008

WASHINGTON NAVY YARD

Storage Area

Cost

$316K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Jan 2017

Contaminated Areas

Groundwater: Medium Risk

Contaminants: Barium 100000.0 ppb

Soil: Low Risk

Contaminants: Dibenz[ah]anthracene 0.14 ppb Benzo[a]pyrene 0.51 ppb Beryllium and compounds 0.94 ppb

See more details...

Site ID: SITE 00024

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

$694K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Apr 2018

Contaminated Areas

Groundwater: Medium Risk

Contaminants: Trichloroethylene (TCE) 2200.0 ppb

Soil: Low Risk

Contaminants: Manganese and compounds 448.0 ppb Iron 26000.0 ppb

See more details...

Site ID: SITE 00019

WASHINGTON NAVY YARD

Contaminated Fill

Cost

Unknown

Final Cleanup Action

Jan 2017

Contaminated Areas

Soil: Medium Risk

Contaminants: Benzo(a)Pyrene 10.0 ppb Iron 50.0 ppb Manganese and compounds 50.0 ppb Chromium 50.0 ppb

See more details...

Site ID: SITE 00021

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Oct 2017

Contaminated Areas

Groundwater: Medium Risk

Contaminants: Anthracene 5000.0 ppb Lead 75000.0 ppb Barium 968000.0 ppb

Soil: Medium Risk

Contaminants: Anthracene 5.0 ppb Lead 75.0 ppb Barium 968.0 ppb

Sediment (Human): Risk Not Evaluated

See more details...

Site ID: SITE 00018

WASHINGTON NAVY YARD

Contaminated Sediments

Cost

$2.53M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Aug 2019

Contaminated Areas

Soil: Low Risk

Contaminants: Aroclor 1.0 ppb

See more details...

24 Inactive Sites

Sites where military cleanup actions are complete, according to the DOD. Note that this status does not necessarily mean the site is no longer hazardous, as many of these sites are put under long-term monitoring or other restrictions.

Site ID: UST 000169

WASHINGTON NAVY YARD

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Apr 2001

Site ID: SITE 00012

WASHINGTON NAVY YARD

Industrial Discharge

Cost

Unknown

Final Cleanup Action

Sep 1999

Contaminated Areas

Sediment (Fresh): High Risk

Contaminants: Mercury and compounds (inorganic) 810.0 ppb Lead 3570.0 ppb

Sediment (Human): High Risk

Contaminants: PCBs 3.8 ppb Mercury and compounds (inorganic) 810.0 ppb Lead 3570.0 ppb Copper and compounds 3780.0 ppb

Sediment (Marine): High Risk

Contaminants: PCBs 3.8 ppb Mercury and compounds (inorganic) 810.0 ppb Copper and compounds 3550.0 ppb Lead 3570.0 ppb

See more details...

Site ID: SITE 00003

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Oct 2007

Contaminated Areas

Groundwater: Medium Risk

Contaminants: Bis(2-ethylhexyl)phthalate 5000.0 ppb Beryllium and compounds 5900.0 ppb Arsenic (noncancer) 6000.0 ppb Lead 57200.0 ppb Manganese and compounds 746000.0 ppb Iron 27300000.0 ppb

Soil: Medium Risk

Contaminants: Arsenic (noncancer) 4.2 ppb Beryllium and compounds 4.2 ppb Iron 55700.0 ppb

See more details...

Site ID: SITE 00001

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Oct 2007

Contaminated Areas

Groundwater: Medium Risk

Contaminants: Antimony and compounds 6200.0 ppb Barium 344000.0 ppb Manganese and compounds 5720000.0 ppb Iron 94200000.0 ppb

Soil: Low Risk

Contaminants: Beryllium and compounds 4.6 ppb Arsenic (noncancer) 5.9 ppb Chromium VI and compounds 18.6 ppb Lead 58.2 ppb Barium and compounds 59.6 ppb Manganese and compounds 203.0 ppb Aluminum 15300.0 ppb

See more details...

Site ID: SITE 00004

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Apr 2005

Contaminated Areas

Groundwater: Medium Risk

Contaminants: Beryllium and compounds 5800.0 ppb Methylene chloride 18000.0 ppb Lead 38200.0 ppb Chloromethane 42000.0 ppb Nickel and compounds 532000.0 ppb Manganese and compounds 1640000.0 ppb

Soil: Low Risk

Contaminants: Beryllium and compounds 1.3 ppb Arsenic (noncancer) 8.1 ppb Iron 33200.0 ppb

See more details...

Site ID: SITE 00005

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Jul 2006

Contaminated Areas

Groundwater: High Risk

Contaminants: Beryllium and compounds 6900.0 ppb Methylene chloride 14000.0 ppb Chloromethane 22000.0 ppb Arsenic (noncancer) 61700.0 ppb Lead 1080000.0 ppb Nickel and compounds 3190000.0 ppb Copper and compounds 3910000.0 ppb Manganese and compounds 4170000.0 ppb Aluminum 23100000.0 ppb

Soil: Medium Risk

Contaminants: Benzo[a]pyrene 0.29 ppb Beryllium and compounds 1.1 ppb Arsenic (noncancer) 83.6 ppb Lead 4420.0 ppb Iron 53900.0 ppb

See more details...

Site ID: SITE 00020

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Feb 2007

Contaminated Areas

Soil: Medium Risk

Contaminants: Benz(a)Anthracene 2.0 ppb Iron 2.0 ppb Manganese and compounds 2.0 ppb Barium 2.0 ppb Beryllium and compounds 2.0 ppb

See more details...

Site ID: SITE 00009

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Sep 2007

Contaminated Areas

Groundwater: Medium Risk

Contaminants: Arsenic 4400.0 ppb Beryllium and compounds 5300.0 ppb Lead 7600.0 ppb Chloroform 10000.0 ppb Manganese and compounds 440000.0 ppb Nickel and compounds 1880000.0 ppb

Soil: Low Risk

Contaminants: Beryllium and compounds 0.68 ppb Arsenic (noncancer) 4.3 ppb

See more details...

Site ID: SITE 00010

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Aug 2008

Contaminated Areas

Soil: High Risk

Contaminants: Lead 18700.0 ppb

See more details...

Site ID: SITE 00013

WASHINGTON NAVY YARD

Contaminated Buildings

Cost

Unknown

Final Cleanup Action

Nov 2007

Contaminated Areas

Groundwater: Low Risk

Contaminants: Chloroform 2000.0 ppb Manganese and compounds 304000.0 ppb

Soil: Low Risk

Contaminants: PCBs 10.0 ppb

See more details...

Site ID: SITE 00014

WASHINGTON NAVY YARD

Contaminated Buildings

Cost

Unknown

Final Cleanup Action

Aug 2005

Contaminated Areas

Soil: Medium Risk

Contaminants: Arsenic 7.2 ppb PCBs 40.0 ppb

See more details...

Site ID: SITE 00016

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Jul 2006

Contaminated Areas

Groundwater: High Risk

Contaminants: Arsenic 12900.0 ppb

Sediment (Marine): High Risk

Contaminants: Benzo(a)Pyrene 1.7 ppb Arsenic 9.2 ppb

Soil: Medium Risk

Contaminants: Arsenic 5.4 ppb Lead 430.0 ppb

See more details...

Site ID: SITE 00017

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Dec 2004

Contaminated Areas

Groundwater: Low Risk

Contaminants: Vinyl Chloride 400.0 ppb Arsenic 3400.0 ppb Barium 561000.0 ppb

Soil: Low Risk

Contaminants: Beryllium and compounds 17.0 ppb Iron 24500.0 ppb

See more details...

Site ID: UST 000184

WASHINGTON NAVY YARD

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Mar 2003

Site ID: SITE 00002

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Oct 2007

Contaminated Areas

Groundwater: Medium Risk

Contaminants: Beryllium and compounds 2900.0 ppb Arsenic (noncancer) 5800.0 ppb Lead 51800.0 ppb Manganese and compounds 1460000.0 ppb Methylene chloride 2400000.0 ppb

Soil: Medium Risk

Contaminants: Beryllium and compounds 2.1 ppb Arsenic (noncancer) 11.2 ppb Iron 63600.0 ppb

See more details...

Site ID: SITE 00022

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Dec 2014

Contaminated Areas

Soil: Medium Risk

Contaminants: Arsenic 62.0 ppb Chromium 80.0 ppb Anthracene 2300.0 ppb Barium 7150.0 ppb

See more details...

Site ID: UST 000002

WASHINGTON NAVY YARD

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Jun 1998

Contaminated Areas

Groundwater: High Risk

Contaminants: Lead 2000.0 ppb Toluene 4430.0 ppb Xylene (mixed) 10500.0 ppb Ethylbenzene 43000.0 ppb Benzene 200000.0 ppb

Soil: Medium Risk

Contaminants: Lead 131.0 ppb

See more details...

Site ID: UST 000003

WASHINGTON NAVY YARD

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Aug 2000

Site ID: UST 000004

WASHINGTON NAVY YARD

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Sep 1998

Site ID: SITE 00100

WASHINGTON NAVY YARD

Landfill

Cost

$2.21M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2010

This site is under ongoing monitoring until Jun 2045

Contaminated Areas

Soil: Medium Risk

Contaminants: Mercury (Inorganic) 0.29 ppb Fluorene 0.35 ppb Aroclor 1254 1.6 ppb Selenium 4.3 ppb Arsenic 4.5 ppb Benzene 42.0 ppb Lead 101.0 ppb Barium 116.0 ppb Vanadium 164.0 ppb Manganese and compounds 16100.0 ppb

See more details...

Site ID: UXO 000001

WASHINGTON NAVY YARD

Explosive Ordnance Disposal Area

Cost

Unknown

Final Cleanup Action

Sep 2010

Site ID: SITE 00007

WASHINGTON NAVY YARD

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Sep 2007

Contaminated Areas

Groundwater: High Risk

Contaminants: Methylene chloride 14000.0 ppb Arsenic (noncancer) 16900.0 ppb Manganese and compounds 237000.0 ppb Lead 656000.0 ppb

Soil: Medium Risk

Contaminants: Dibenz[ah]anthracene 0.45 ppb Beryllium and compounds 0.62 ppb Benzo[k]fluoranthene 9.8 ppb Arsenic (noncancer) 11.3 ppb Indeno[1,2,3-cd]pyrene 15.0 ppb Chrysene 21.0 ppb Benz(a)anthracene 21.0 ppb Benzo[b]fluoranthene 22.0 ppb Benzo[a]pyrene 25.0 ppb

See more details...

Site ID: SITE 00023

WASHINGTON NAVY YARD

Building Demolition/Debris Removal

Cost

Unknown

Final Cleanup Action

Apr 2013

Contaminated Areas

Soil: Medium Risk

Contaminants: Barium 1080.0 ppb Benzo(a)Pyrene 3500.0 ppb

See more details...

Site ID: SITE 00015

WASHINGTON NAVY YARD

Storm Drain

Cost

Unknown

Final Cleanup Action

Sep 1999

Contaminated Areas

Sediment (Fresh): High Risk

Contaminants: Mercury and compounds (inorganic) 35.0 ppb PCBs 85.0 ppb

Sediment (Human): High Risk

Contaminants: Mercury and compounds (inorganic) 35.0 ppb PCBs 85.0 ppb

Sediment (Marine): High Risk

Contaminants: Mercury 35.0 ppb PCBs 85.0 ppb

See more details...

Update (Dec. 5, 2017): We have changed the source of the installation cost data after being notified by the Department of Defense that they erroneously reported their own cost figures on the DERP website. We are now displaying the costs the department says are the most accurate available, from the Pentagon’s DERP database that we received in a FOIA request.

Note: The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.

Data: All data comes from the Defense Environmental Restoration Program and the U.S. Army Corps of Engineers, and will be released soon at the ProPublica Data Store. Read our methodology »