NAVY INSTALLATION ID: IL517002259600

GREAT LAKES NTC

great lakes, Illinois

Cost So Far

$28.2M

Money already spent on the evaluation and cleanup of hazardous sites.

Expected Additional Cost

$179M

The estimated amount of money needed for evaluation and cleanup of hazardous sites at this installation.

Expected Completion Date

2026

The date by which the DOD estimates cleanup of all sites will be complete. Long term monitoring may continue after this date.

45 Hazardous Sites

Below are the locations of hazardous sites associated with this military installation, according to the DOD. A site’s contamination may affect a much larger area, including public and private lands and the water supplies beneath them.

High Risk

Medium Risk

Low Risk

Risk Not Evaluated or Not Required

Response Complete

We haven't independently confirmed the location of every site. If you notice a site placed at the incorrect location, please contact us.

Not all sites in the DOD data include location information, so there may be sites listed below that are missing from the map. The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.

Land Controls & Restrictions

Many sites have been declared “clean” by the DOD but are still not safe for people. This military installation is safe only with the following conditions in place: barriers. see more » annual written certification of compliance with lucs a barrier, including but not limited to a paved surface or landfill cap, must be maintained in order to prevent exposure to contaminants, including vapor intrusion into an enclosed structure. incorporation of lucs into a base master plan state or local permits required for construction, development, excavation, well drilling, etc. the agencies issuing the permits should be notified of areas impacted by lucs. prohibit residential use in certain areas, unless prior written approval of the navy and lead regulatory agency is obtained. prohibits disturbance of surface or subsurface soil due to invasive activities such as construction, unless prior written approval of the navy and lead regulatory agency is obtained. prohibit removal or breaching of existing exposure barriers (e.g. concrete blding foundations, surfaced parking lots, and other paved surfaces), unless prior written approval of the navy and lead regulatory agency is obtained. groundwater use restricted. a landfill cover at the site prevents exposure to contaminated soil and reduces infiltration of groundwater. this cover will be inspected and maintained. prohibits any use other than industrial in certain areas, unless prior written approval of the navy and lead regulatory agency is obtained. prohibits the disturbance or use of existing groundwater wells, unless prior written approval of the navy and lead regulatory agency is obtained. prohibit construction and/or operation of businesses, structures or other areas frequented by sensitive populations, such as children and the elderly, unless prior written approval of the navy and lead regulatory agency is obtained. « see less

6 Active Sites

Sites where military cleanup actions are still ongoing. The risk level of a site refers to a relative risk assessment made by the DOD, which prioritizes the cleanup of sites that pose greatest threat to safety, human health, and the environment.

Site ID: SITE 00024

GREAT LAKES NTC

Contaminated Fill

Cost

$7.04M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Mar 2018

This site is under ongoing monitoring until Sep 2047

Contaminated Areas

Groundwater: Medium Risk

Contaminants: Aldrin 55.4 ppb Aroclor-1242 6000.0 ppb Nickel (Soluble Salts) 144000.0 ppb Manganese and compounds 28200000.0 ppb Iron 918000000.0 ppb

Soil: Low Risk

Contaminants: Arsenic 0.0125 ppb DDT 0.147 ppb Arochlor 1260 0.269 ppb Aroclor 1254 0.392 ppb Naphthalene 0.539 ppb Benzo(a)Pyrene 1.39 ppb Benz(a)Anthracene 1.43 ppb Aroclor-1242 23.2 ppb

Sediment (Fresh): Risk Not Evaluated

Sediment (Human): Risk Not Evaluated

Surface Water (Fresh): Risk Not Evaluated

Surface Water (Human): Risk Not Evaluated

See more details...

Site ID: SITE 00027

GREAT LAKES NTC

Contaminated Sediments

Cost

$7.38M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Apr 2022

Contaminated Areas

Sediment (Human): Medium Risk

Contaminants: Vinyl Chloride 0.08 ppb DDE 0.11 ppb DDT 0.12 ppb DDD 0.17 ppb Acenaphthene 0.61 ppb Aroclor 1254 0.78 ppb Anthracene 0.91 ppb Mercury and compounds 1.1 ppb Phenol 6.8 ppb Silver and compounds 8.5 ppb Lead (Tetraethyl) 5720.0 ppb Copper and compounds 20200.0 ppb Zinc 45100.0 ppb

See more details...

Site ID: UXO 000004

GREAT LAKES NTC

Firing Range

Cost

$141M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2026

Contaminated Areas

Sediment (Fresh): Low Risk

Contaminants: HMX 0.152 ppb RDX 0.427 ppb Lead 15.8 ppb Copper and compounds 27.7 ppb Zinc 55.7 ppb Iron 18000.0 ppb

Sediment (Human): Low Risk

Contaminants: HMX 0.152 ppb RDX 0.427 ppb Lead 15.8 ppb Copper and compounds 27.7 ppb Zinc 55.7 ppb Strontium (Stable) 73.6 ppb Iron 18000.0 ppb

See more details...

Site ID: SITE 00025

GREAT LAKES NTC

Contaminated Fill

Cost

$4.5M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Jan 2018

This site is under ongoing monitoring until Sep 2047

Contaminated Areas

Soil: Low Risk

Contaminants: Arsenic 2.0 ppb

Groundwater: Risk Not Evaluated

See more details...

Site ID: SITE 00012

GREAT LAKES NTC

Surface Disposal Area

Cost

$827K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2015

This site is under ongoing monitoring until Sep 2026

Contaminated Areas

Soil: Medium Risk

Contaminants: Toluene 0.02 ppb Methylene chloride 0.07 ppb DDT 0.16 ppb Acetone 0.17 ppb DDD 0.43 ppb DDE 0.83 ppb Beryllium and compounds 2.2 ppb Selenium 2.34 ppb Mercury and compounds (inorganic) 5.14 ppb Cadmium and compounds 8.73 ppb Antimony and compounds 10.0 ppb Arsenic (cancer endpoint) 20.85 ppb Silver and compounds 36.73 ppb Nickel and compounds 78.43 ppb Chromium (total) 92.83 ppb Copper and compounds 308.45 ppb Lead 396.4 ppb Zinc 845.28 ppb

See more details...

Site ID: SITE 00026

GREAT LAKES NTC

Landfill

Cost

$2.98M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Nov 2017

This site is under ongoing monitoring until Sep 2047

Contaminated Areas

Soil: Risk Not Evaluated

See more details...

39 Inactive Sites

Sites where military cleanup actions are complete, according to the DOD. Note that this status does not necessarily mean the site is no longer hazardous, as many of these sites are put under long-term monitoring or other restrictions.

Site ID: SITE 00002

GREAT LAKES NTC

Landfill

Cost

$3.95M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Aug 2007

This site is under ongoing monitoring until Sep 2045

Site ID: SITE 00005

GREAT LAKES NTC

Storage Area

Cost

$382K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2014

This site is under ongoing monitoring until Jan 2045

Contaminated Areas

Soil: Low Risk

Contaminants: DDT 0.01 ppb Endosulfan I 0.01 ppb Dibenz[ah]anthracene 0.03 ppb Diethyl phthalate 0.07 ppb Bis(2-ethylhexyl)phthalate 0.08 ppb Phenanthrene 0.09 ppb Indeno[1,2,3-cd]pyrene 0.1 ppb Benzo[a]pyrene 0.13 ppb Fluoranthene 0.14 ppb Pyrene 0.15 ppb Chrysene 0.15 ppb Silver and compounds 0.16 ppb Benzo[b]fluoranthene 0.27 ppb Beryllium and compounds 0.34 ppb Cadmium and compounds 1.6 ppb Selenium 1.8 ppb Arsenic (III) 4.6 ppb Chromium VI and compounds 11.0 ppb Nickel and compounds 12.0 ppb Lead 15.2 ppb Vanadium 18.0 ppb Copper and compounds 18.7 ppb Barium and compounds 74.9 ppb Zinc 153.0 ppb Manganese 590.0 ppb Aluminum 4910.0 ppb

See more details...

Site ID: SITE 00009

GREAT LAKES NTC

Surface Disposal Area

Cost

$742K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2014

This site is under ongoing monitoring until Sep 2045

Contaminated Areas

Soil: Low Risk

Contaminants: Methyl ethyl ketone 0.01 ppb DDD,4,4- 0.02 ppb Methoxychlor 0.05 ppb DDE,4,4- 0.08 ppb Arsenic (cancer) 0.11 ppb Anthracene 0.21 ppb Benzo[a]pyrene 0.55 ppb Chrysene 0.58 ppb Benz(a)anthracene 0.62 ppb Cadmium and compounds 0.62 ppb Benzo(b)fluoranthene 0.96 ppb Barium and compounds 0.96 ppb Lead 965.0 ppb

See more details...

Site ID: SITE 00021

GREAT LAKES NTC

Landfill

Cost

$382K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2014

This site is under ongoing monitoring until Mar 2045

Contaminated Areas

Soil: Medium Risk

Contaminants: Lead 2000.0 ppb

See more details...

Site ID: UST 000007

GREAT LAKES NTC

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Sep 2011

Contaminated Areas

Groundwater: Low Risk

Contaminants: Benzene 700.0 ppb Ethyl benzene 1400.0 ppb Benzene, methyl- 2550.0 ppb 1,4-Dimethylbenzene 5000.0 ppb 1,3-Dimethylbenzene 5000.0 ppb o-Xylene 5000.0 ppb Chrysene 23700.0 ppb Naphthalene 47400.0 ppb Benz(a)Anthracene 53800.0 ppb Benzo(def)Phenanthrene 532000.0 ppb

See more details...

Site ID: SITE 00023

GREAT LAKES NTC

Oil/Water Separator

Cost

$208K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Apr 2010

This site is under ongoing monitoring until Jan 2045

Site ID: SITE 00004

GREAT LAKES NTC

Above Ground Storage Tank

Cost

Unknown

Final Cleanup Action

Sep 2008

Contaminated Areas

Groundwater: Low Risk

Contaminants: Mercury (Inorganic) 380.0 ppb Chlorobenzene 3000.0 ppb Lead 5700.0 ppb Zinc 11900.0 ppb Acetone 12000.0 ppb Bis(2-ethylhexyl)phthalate (DEHP) 13000.0 ppb Methylene chloride 13000.0 ppb

Soil: Low Risk

Contaminants: Toluene 0.03 ppb Chlorobenzene 0.06 ppb Acetone 0.15 ppb Methylene chloride 0.22 ppb Fluoranthene 0.53 ppb Pyrene 0.87 ppb Phenanthrene 1.0 ppb Naphthalene 5.7 ppb Bis(2-ethylhexyl)phthalate (DEHP) 11.0 ppb Lead 299.0 ppb

Surface Water (Fresh): Low Risk

Contaminants: Benzene 2000.0 ppb Chrysene 3000.0 ppb Chlorobenzene 5000.0 ppb Bis(2-ethylhexyl)phthalate (DEHP) 11000.0 ppb Pyrene 11000.0 ppb Phenanthrene 22000.0 ppb Lead 38000.0 ppb Methylene chloride 96000.0 ppb Acetone 110000.0 ppb Fluorene 900000.0 ppb

Surface Water (Human): Low Risk

Contaminants: Benzene 2000.0 ppb Chrysene 3000.0 ppb Chlorobenzene 5000.0 ppb Bis(2-ethylhexyl)phthalate (DEHP) 11000.0 ppb Pyrene 11000.0 ppb Phenanthrene 22000.0 ppb Lead 38000.0 ppb Methylene chloride 96000.0 ppb Acetone 110000.0 ppb Fluorene 900000.0 ppb

See more details...

Site ID: SITE 00006

GREAT LAKES NTC

Storage Area

Cost

Unknown

Final Cleanup Action

Nov 1988

Contaminated Areas

Soil: Low Risk

Contaminants: DDE,4,4- 0.23 ppb DDD,4,4- 0.29 ppb DDT 2.8 ppb

See more details...

Site ID: SITE 00007

GREAT LAKES NTC

Storage Area

Cost

Unknown

Final Cleanup Action

Jun 2003

Contaminated Areas

Soil: Medium Risk

Contaminants: Acetone 0.01 ppb Endrin 0.01 ppb Endosulfan I 0.01 ppb DDE,4,4- 0.02 ppb Tetrachloroethylene 0.03 ppb DDT 0.05 ppb Fluorene 0.1 ppb Carbazole 0.14 ppb Butyl benzyl phthalate 0.16 ppb Dibenz[ah]anthracene 0.17 ppb PCBs 0.19 ppb Anthracene 0.21 ppb Mercury 0.23 ppb Silver and compounds 0.24 ppb Beryllium and compounds 0.27 ppb di-n-Octyl phthalate 0.31 ppb Benzo[a]pyrene 0.71 ppb Chrysene 0.93 ppb Phenanthrene 1.2 ppb Acenaphthylene- 1.3 ppb Pyrene 1.4 ppb Selenium 1.4 ppb Fluoranthene 1.6 ppb Benzo[b]fluoranthene 1.8 ppb Antimony and compounds 2.0 ppb Cadmium and compounds 2.5 ppb Arsenic (III) 3.4 ppb Bis(2-ethylhexyl)phthalate 6.8 ppb Nickel and compounds 11.5 ppb Vanadium 12.6 ppb Chromium VI and compounds 34.9 ppb Barium and compounds 55.8 ppb Lead 211.0 ppb Copper and compounds 229.0 ppb Manganese 332.0 ppb Zinc 463.0 ppb Aluminum 3670.0 ppb Iron 11600.0 ppb

See more details...

Site ID: SITE 00008

GREAT LAKES NTC

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Sep 1990

Site ID: SITE 00010

GREAT LAKES NTC

Unexploded Munitions and Ordnance Area

Cost

Unknown

Final Cleanup Action

Dec 1989

Site ID: SITE 00011

GREAT LAKES NTC

Storage Area

Cost

Unknown

Final Cleanup Action

Mar 1986

Site ID: SITE 00013

GREAT LAKES NTC

Surface Disposal Area

Cost

Unknown

Final Cleanup Action

Mar 2001

Site ID: SITE 00015

GREAT LAKES NTC

Burn Area

Cost

Unknown

Final Cleanup Action

Sep 2001

Contaminated Areas

Soil: Medium Risk

Contaminants: Naphthalene 0.06 ppb Phenanthrene 0.1 ppb Methylnaphthalene,2 0.13 ppb Cadmium and compounds 2.0 ppb Bis(2-ethylhexyl)phthalate (DEHP) 2.2 ppb Beryllium and compounds 2.4 ppb Arsenic (noncancer) 10.3 ppb Chromium VI and compounds 21.4 ppb Lead 21.9 ppb Copper and compounds 31.0 ppb Barium and compounds 70.1 ppb Aluminum 11000.0 ppb Iron 22800.0 ppb

See more details...

Site ID: SITE 00017

GREAT LAKES NTC

Contaminated Sediments

Cost

Unknown

Final Cleanup Action

Apr 2014

Contaminated Areas

Sediment (Human): Medium Risk

Contaminants: Vinyl chloride 0.08 ppb DDE,4,4- 0.11 ppb DDT 0.12 ppb DDD,4,4- 0.17 ppb Acenaphthene 0.61 ppb Arochlor 1254 0.78 ppb Anthracene 0.91 ppb Mercury 1.1 ppb Phenol 6.8 ppb Silver and compounds 8.5 ppb Lead 5720.0 ppb Copper and compounds 20200.0 ppb Zinc 45100.0 ppb

Sediment (Fresh): Risk Not Evaluated

Surface Water (Fresh): Risk Not Evaluated

Surface Water (Human): Risk Not Evaluated

See more details...

Site ID: SITE 00018

GREAT LAKES NTC

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Sep 2006

Contaminated Areas

Soil: High Risk

Contaminants: Radium-226 63000.0 ppb Thorium-232 100000.0 ppb

Sediment (Human): Medium Risk

Contaminants: Radium-226 17000.0 ppb Thorium-Natural 63000.0 ppb

Groundwater: Risk Not Evaluated

Sediment (Fresh): Risk Not Evaluated

Surface Water (Fresh): Risk Not Evaluated

Surface Water (Human): Risk Not Evaluated

See more details...

Site ID: UST 000008

GREAT LAKES NTC

Underground Storage Tanks

Cost

$168K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Aug 2010

This site is under ongoing monitoring until Sep 2026

Contaminated Areas

Groundwater: Low Risk

Contaminants: Lead 124000.0 ppb

See more details...

Site ID: UST 000011

GREAT LAKES NTC

Underground Storage Tanks

Cost

$434K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Aug 2011

This site is under ongoing monitoring until Sep 2025

Contaminated Areas

Groundwater: Low Risk

Contaminants: Benzene 83500.0 ppb Lead 365000.0 ppb Ethyl benzene 925100.0 ppb

See more details...

Site ID: UST 000001

GREAT LAKES NTC

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Dec 2005

Contaminated Areas

Groundwater: Low Risk

Contaminants: Ethyl benzene 1000.0 ppb

Soil: Low Risk

Contaminants: Benzene, 1,1'-oxybis(2,3,4,5,6-pentabromo-(9Cl) 0.21 ppb Ethyl benzene 33.3 ppb

See more details...

Site ID: SITE 00016

GREAT LAKES NTC

Contaminated Buildings

Cost

Unknown

Final Cleanup Action

Oct 2004

Contaminated Areas

Soil: High Risk

Contaminants: Lead 2080.0 ppb

See more details...

Site ID: UST 000004

GREAT LAKES NTC

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Sep 2011

Contaminated Areas

Groundwater: Low Risk

Contaminants: Benzo(a)Pyrene 10.0 ppb

Soil: Low Risk

Contaminants: Acenaphthene 0.45 ppb Dibenz[ah]anthracene 1.5 ppb Anthracene 1.7 ppb Phenol 2.8 ppb Indeno[1,2,3-cd]pyrene 3.2 ppb Benzo[a]pyrene 4.7 ppb Chrysene 6.2 ppb Fluorene 690.0 ppb

See more details...

Site ID: UST 000005

GREAT LAKES NTC

Underground Tank Farm

Cost

Unknown

Final Cleanup Action

Aug 2007

Contaminated Areas

Groundwater: Low Risk

Contaminants: Ethenylbenzene 41000.0 ppb Xylene 190000.0 ppb Benzene, 1,1'-oxybis(2,3,4,5,6-pentabromo-(9Cl) 300000.0 ppb Toluene 430000.0 ppb

See more details...

Site ID: UST 000009

GREAT LAKES NTC

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Oct 2004

Contaminated Areas

Groundwater: Low Risk

Contaminants: Benzene, methyl- 1690.0 ppb Ethenylbenzene 3000.0 ppb Benzene 4000.0 ppb Dimethylbenzene 7000.0 ppb

See more details...

Site ID: UST 000010

GREAT LAKES NTC

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Sep 2011

Contaminated Areas

Groundwater: Low Risk

Contaminants: Ethyl benzene 3000.0 ppb Benzene, methyl- 4000.0 ppb Benzene 4000.0 ppb Dimethylbenzene 7000.0 ppb

See more details...

Site ID: UXO 000001

GREAT LAKES NTC

Unexploded Munitions and Ordnance Area

Cost

Unknown

Final Cleanup Action

Mar 2003

Site ID: UXO 000002

GREAT LAKES NTC

Unexploded Munitions and Ordnance Area

Cost

Unknown

Final Cleanup Action

Mar 2003

Site ID: UXO 000003

GREAT LAKES NTC

Unexploded Munitions and Ordnance Area

Cost

Unknown

Final Cleanup Action

Mar 2003

Site ID: UXO 000005

GREAT LAKES NTC

Firing Range

Cost

Unknown

Final Cleanup Action

Mar 2003

Site ID: UXO 000006

GREAT LAKES NTC

Firing Range

Cost

Unknown

Final Cleanup Action

Sep 2013

Contaminated Areas

Soil: High Risk

Contaminants: 2-Methylnaphthalene 0.072 ppb Acenaphthene 0.141 ppb Benzo(k)Fluoranthene 2.73 ppb Dibenz[ah]anthracene 2.79 ppb Fluoranthene 4.69 ppb Pyrene 8.06 ppb Benz(a)Anthracene 8.34 ppb Benzo(b)Fluoranthene 9.56 ppb Chrysene 13.3 ppb Benzo(a)Pyrene 15.1 ppb Arsenic 19.6 ppb Lead 1460.0 ppb

Sediment (Fresh): Low Risk

Contaminants: Anthracene 0.0018 ppb Pyrene 0.00312 ppb Antimony and compounds 2.4 ppb Lead 204.0 ppb

Sediment (Human): Low Risk

Contaminants: Anthracene 0.0174 ppb Pyrene 0.0307 ppb Antimony and compounds 0.321 ppb Lead 23.5 ppb

See more details...

Site ID: UST 000006

GREAT LAKES NTC

Underground Storage Tanks

Cost

$79K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2009

This site is under ongoing monitoring until May 2025

Contaminated Areas

Groundwater: Low Risk

Contaminants: Benzo(a)Pyrene 6100.0 ppb Indeno(1,2,3-cd)Pyrene 7900.0 ppb Benz(a)Anthracene 45000.0 ppb

See more details...

Site ID: SITE 00019

GREAT LAKES NTC

Small Arms Range

Cost

$312K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2009

This site is under ongoing monitoring until Sep 2045

Contaminated Areas

Soil: Medium Risk

Contaminants: Lead 1800.0 ppb

Groundwater: Risk Not Evaluated

See more details...

Site ID: UST 000002

GREAT LAKES NTC

Underground Storage Tanks

Cost

$433K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Jul 2012

This site is under ongoing monitoring until Mar 2032

Contaminated Areas

Groundwater: Low Risk

Contaminants: p-Chloronitrobenzene 10.0 ppb

Soil: Low Risk

Contaminants: Lead 0.01 ppb

See more details...

Site ID: SITE 00022

GREAT LAKES NTC

Spill Site Area

Cost

$147K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2007

This site is under ongoing monitoring until Jun 2045

Contaminated Areas

Groundwater: Medium Risk

Contaminants: cis-1,2-Dichloroethylene 1300000.0 ppb 1,1,2,2-Tetrachloroethane 7400000.0 ppb

Soil: Low Risk

Contaminants: Trichloroethylene (TCE) 0.0007 ppb cis-1,2-Dichloroethylene 0.82 ppb 1,1,2,2-Tetrachloroethane 20.0 ppb

See more details...

Site ID: UST 000003

GREAT LAKES NTC

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Apr 2011

Contaminated Areas

Groundwater: Low Risk

Contaminants: Benzene 700.0 ppb Ethyl benzene 1400.0 ppb Benzene, methyl- 1590.0 ppb 1,4-Dimethylbenzene 5000.0 ppb 1,3-Dimethylbenzene 5000.0 ppb o-Xylene 5000.0 ppb

See more details...

Site ID: SITE 00001

GREAT LAKES NTC

Landfill

Cost

$4.34M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2008

This site is under ongoing monitoring until Sep 2045

Contaminated Areas

Soil: High Risk

Contaminants: DDD,4,4- 0.01 ppb Endosulfan I 0.01 ppb Phenol 0.03 ppb Chlordane, alpha- (2) 0.03 ppb DDE,4,4- 0.03 ppb Dibutyl phthalate 0.03 ppb Butyl benzyl phthalate 0.05 ppb DDT 0.08 ppb Acenaphthylene- 0.09 ppb Bis(2-ethylhexyl)phthalate (DEHP) 0.1 ppb Naphthalene 0.42 ppb Pentachlorophenol 0.7 ppb Silver and compounds 1.1 ppb Beryllium and compounds 1.2 ppb Arochlor 1254 1.5 ppb Acenaphthene 1.5 ppb Selenium 1.6 ppb Antimony and compounds 1.7 ppb Cadmium and compounds 1.7 ppb Fluorene 1.8 ppb Mercury and compounds (inorganic) 2.4 ppb Thallium 3.0 ppb Carbazole 3.3 ppb Anthracene 4.5 ppb Chromium VI and compounds 8.2 ppb Dibenz[ah]anthracene 8.3 ppb Arsenic (cancer) 9.9 ppb Indeno[1,2,3-cd]pyrene 15.0 ppb Benzo[a]pyrene 28.0 ppb Nickel and compounds 29.2 ppb Chrysene 30.0 ppb Phenanthrene 30.0 ppb Benzo[b]fluoranthene 37.0 ppb Vanadium 37.0 ppb Fluoranthene 59.0 ppb Pyrene 63.0 ppb Barium and compounds 151.0 ppb Lead 429.0 ppb Methylnaphthalene,2 430.0 ppb Copper and compounds 497.0 ppb Zinc 654.0 ppb Manganese 1500.0 ppb Aluminum 16000.0 ppb Iron 29400.0 ppb

See more details...

Site ID: SITE 00020

GREAT LAKES NTC

Contaminated Ground Water

Cost

Unknown

Final Cleanup Action

Sep 2008

Contaminated Areas

Soil: Medium Risk

Contaminants: Radium-226 750000.0 ppb

See more details...

Site ID: UST 000012

GREAT LAKES NTC

Underground Storage Tanks

Cost

$160K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2002

This site is under ongoing monitoring until Sep 2026

Site ID: SITE 00003

GREAT LAKES NTC

Landfill

Cost

$3.65M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Apr 1997

This site is under ongoing monitoring until Sep 2045

Contaminated Areas

Groundwater: High Risk

Contaminants: Lead 60000.0 ppb Iron 3100000.0 ppb Chloride 515000000.0 ppb

See more details...

Site ID: SITE 00014

GREAT LAKES NTC

Storage Area

Cost

Unknown

Final Cleanup Action

Mar 1986

Contaminated Areas

Surface Water (Marine): Medium Risk

Contaminants: Arsenic (cancer) 1400.0 ppb Toluene 4000.0 ppb Xylene 4000.0 ppb Chromium (III) 10000.0 ppb Zinc 44000.0 ppb Aluminum 350000.0 ppb

Sediment (Human): Low Risk

Contaminants: Chlordane, alpha- (2) 0.02 ppb Silver and compounds 0.02 ppb Arsenic (noncancer) 0.03 ppb Methylnaphthalene,2 0.1 ppb Nickel-65 0.1 ppb DDT 0.12 ppb Copper and compounds 0.19 ppb DDE,4,4- 0.2 ppb Carbazole 0.2 ppb Naphthalene 0.29 ppb Fluorene 0.36 ppb DDD,4,4- 0.5 ppb Acenaphthene 0.5 ppb Lead 0.83 ppb PCBs 1.2 ppb Benzo[b]fluoranthene 1.3 ppb Benzo[k]fluoranthene 1.3 ppb Pyrene 1.8 ppb Zinc phosphide 2.2 ppb Bis(2-ethylhexyl)phthalate (DEHP) 3.0 ppb Fluoranthene 3.2 ppb Phenanthrene 3.2 ppb Carbon dichloride 20.0 ppb

See more details...

Update (Dec. 5, 2017): We have changed the source of the installation cost data after being notified by the Department of Defense that they erroneously reported their own cost figures on the DERP website. We are now displaying the costs the department says are the most accurate available, from the Pentagon’s DERP database that we received in a FOIA request.

Note: The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.

Data: All data comes from the Defense Environmental Restoration Program and the U.S. Army Corps of Engineers, and will be released soon at the ProPublica Data Store. Read our methodology »