Cost So Far
$2.98M
Money already spent on the evaluation and cleanup of hazardous sites.
Expected Additional Cost
$3.51M
The estimated amount of money needed for evaluation and cleanup of hazardous sites at this installation.
Expected Completion Date
2027
The date by which the DOD estimates cleanup of all sites will be complete. Long term monitoring may continue after this date.
11 Hazardous Sites
Below are the locations of hazardous sites associated with this military installation, according to the DOD. A site’s contamination may affect a much larger area, including public and private lands and the water supplies beneath them.
High Risk
Medium Risk
Low Risk
Risk Not Evaluated or Not Required
Response Complete
We haven't independently confirmed the location of every site. If you notice a site placed at the incorrect location, please contact us.
Not all sites in the DOD data include location information, so there may be sites listed below that are missing from the map. The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.
7 Active Sites
Sites where military cleanup actions are still ongoing. The risk level of a site refers to a relative risk assessment made by the DOD, which prioritizes the cleanup of sites that pose greatest threat to safety, human health, and the environment.
Site ID: MMR-009-R-01
OTIS GUN CLUB
Small Arms Range
Cost
$252K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Jan 2027
Site ID: MMR-010-R-01
FORMER AMMUNITION SUPPLY POINT WEST
Storage Area
Cost
$43K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Oct 2015
Site ID: MMR-011-R-01
FORMER AMMUNITION SUPPLY POINT EAST
Storage Area
Cost
$113K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Apr 2016
Site ID: MMR-003-R-01
OLD GRENADE COURTS
Unexploded Munitions and Ordnance Area
Cost
$305K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
May 2022
Site ID: MMR-008-R-01
DEMO 1 OFF-SITE GW CONTAMINATION
Contaminated Ground Water
Cost
$2.71M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Apr 2016
This site is under ongoing monitoring until Oct 2029
Site ID: MMR-001-R-01
MOCK VILLAGE
Unexploded Munitions and Ordnance Area
Cost
$117K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Jan 2022
Site ID: MMR-004-R-01
OLD K RANGE
Unexploded Munitions and Ordnance Area
Cost
$265K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Apr 2022
4 Inactive Sites
Sites where military cleanup actions are complete, according to the DOD. Note that this status does not necessarily mean the site is no longer hazardous, as many of these sites are put under long-term monitoring or other restrictions.
Site ID: MMR-005-R-01
OTIS TARGET BUTT
Small Arms Range
Cost
Unknown
Final Cleanup Action
Jun 2010
Site ID: MMR-006-R-01
SMALL ARMS RANGE
Small Arms Range
Cost
Unknown
Final Cleanup Action
Jun 2010
Site ID: MMR-002-R-01
OLD G RANGE
Small Arms Range
Cost
Unknown
Final Cleanup Action
Jun 2010
Site ID: MMR-007-R-01
STABLES AREA
Unexploded Munitions and Ordnance Area
Cost
Unknown
Final Cleanup Action
Jun 2010
Update (Dec. 5, 2017): We have changed the source of the installation cost data after being notified by the Department of Defense that they erroneously reported their own cost figures on the DERP website. We are now displaying the costs the department says are the most accurate available, from the Pentagon’s DERP database that we received in a FOIA request.
Note: The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.
Data: All data comes from the Defense Environmental Restoration Program and the U.S. Army Corps of Engineers, and will be released soon at the ProPublica Data Store. Read our methodology »