Cost So Far
$136M
Money already spent on the evaluation and cleanup of hazardous sites.
Expected Additional Cost
$53.1M
The estimated amount of money needed for evaluation and cleanup of hazardous sites at this installation.
Expected Completion Date
2049
The date by which the DOD estimates cleanup of all sites will be complete. Long term monitoring may continue after this date.
56 Hazardous Sites
Below are the locations of hazardous sites associated with this military installation, according to the DOD. A site’s contamination may affect a much larger area, including public and private lands and the water supplies beneath them.
High Risk
Medium Risk
Low Risk
Risk Not Evaluated or Not Required
Response Complete
We haven't independently confirmed the location of every site. If you notice a site placed at the incorrect location, please contact us.
Not all sites in the DOD data include location information, so there may be sites listed below that are missing from the map. The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.
Land Controls & Restrictions
Many sites have been declared “clean” by the DOD but are still not safe for people. This military installation is safe only with the following conditions in place: deed restrictions, local use ordinances, fences. see more » local use ordinances notations in master plan zoning education programs construction permit fences signs environmental covenants dig permits deed restrictions deed notices prohibit or otherwise manage excavation prohibit human consumption of groundwater restrict withdrawal or use of groundwater without treatment prohibit, or otherwise manage excavation below a specified depth landfill restriction - restrict access to the site prohibit residential use prohibit sensitive use (e.g. hospital, daycare, school) prohibit agricultural-irrigation-livestock use of groundwater prohibit groundwater extraction that interferes with remedial action system « see less
25 Active Sites
Sites where military cleanup actions are still ongoing. The risk level of a site refers to a relative risk assessment made by the DOD, which prioritizes the cleanup of sites that pose greatest threat to safety, human health, and the environment.
Site ID: FGGM 33
BATTERY SHOP BLDG. 2283
Contaminated Buildings
Cost
$2,000
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Groundwater: High Risk
MONITORING WELL DATA REVEALS PLUME IS LEAVING SITE. POTENTIAL SITE IS IMMEDIATELY ABOVE THREE AQUIFERS USED EXTENSIVELY FOR COUNTY WATER SUPPLY. HOWEVER, NO WELL IS IMMEDIATELY DOWN GRADIENT OF THE SOURCE.
Contaminants: Lead 320.0 ug/L
Surface Water (Human): Medium Risk
SITE IS ABOVE THREE AQUIFERS USED EXTENSIVELY FOR COUNTY WATER SUPPLY. HOWEVER,NO WELL IS IMMEDIATELY DOWN GRADIENT OF THE SOURCE.
Contaminants: 1,2-Dichloroethylene (cis) 210.0 ug/L Carbon Dichloride 277.0 ug/L
Soil: Low Risk
MAY MIGRATE DOWN THROUGH SOIL MAY MIGRATE DOWN THROUGH SOIL.
Contaminants: Lead 200.0 mg/kg
Site ID: FGGM-96
MOTOR POOLS, WASHRACKS, BLDGS (FMR)
Maintenance Yard
Cost
$2.56M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Aug 2017
Contaminated Areas
Sediment (Fresh): High Risk
The pesticides detected have the potential to migrate off site. Because the contamination was detected in sediments and the relative ease with which these contaminants can travel through the different mediums, there is the potential these contaminants may migrate from the site and contaminate other mediums.
Contaminants: Heptachlor Epoxide 0.062 mg/kg
Groundwater: Low Risk
Due to the relative ease with which the detected contamination can travel within groundwater it has the potential to migrate offsite. Because the contamination has entered the ground water and the relative ease with which these contaminants can travel through the different mediums, there is the potential these contaminants may migrate from the site and contaminate drinking water aquifer
Contaminants: Arsenic 92.0 ug/L
Sediment (Human): Low Risk
The pesticide detected has the potential to migrate off site. Because the contamination was detected in sediments and the relative ease with which the contaminant can travel through the different mediums, there is the potential the contaminant may migrate from the site and contaminate other mediums.
Contaminants: Heptachlor Epoxide 0.062 mg/kg
Site ID: FGGM 83
TRAP AND SKEET RANGE
Contaminated Fill
Cost
$1.82M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Sep 2018
This site is under ongoing monitoring until Aug 2048
Contaminated Areas
Soil: High Risk
FORMER TRAPAND SKEET RANGE. MODERATE USE AREA FOR FISHING AND RECREATION.
Contaminants: Dibenz[ah]anthracene 29.0 mg/kg Indeno(1,2,3-cd)Pyrene 63.0 mg/kg Chrysene 110.0 mg/kg Benz(a)Anthracene 110.0 mg/kg Benzo(b)Fluoranthene 130.0 mg/kg Benzo(a)Pyrene 150.0 mg/kg Lead 1400.0 mg/kg
Site ID: FGGM 47
POST LAUNDRY (OPERABLE UNIT 4)
Contaminated Ground Water
Cost
$13.3M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Groundwater: High Risk
MONITORING WELL DATA REVEALS PLUME IS LEAVING SITE SITE IS ABOVE THREE AQUIFERS USED EXTENSIVELY FOR COUNTY WATER SUPPLY. HOWEVER,NO WELL IS IMMEDIATELY DOWN GRADIENT OF THE SOURCE.
Contaminants: Carbon Dichloride 31000.0 ug/L
Surface Water (Human): High Risk
IN WATER LEAVING SITE
Contaminants: Carbon Dichloride 277.0 ug/L
Site ID: FGGM 88
TANK MNT FAC. SHOP-1 (OP UNIT 4)
Maintenance Yard
Cost
$2,000
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Groundwater: High Risk
The existing contaminates from this site have the potential to continue to migrate offsite based on the fort meade ground water model Because the contamination has entered the ground water and the relative ease with which these contaminants can travel through the different mediums, there is the potential these contaminants may migrate from the site and contaminate drinking water aquifer
Contaminants: Arsenic 200.0 ug/L Lead 1600.0 ug/L Barium 3300.0 ug/L
Site ID: FGGM 92
HEAVY GUN CLEAN/REPAIR (OP UNIT 4)
Contaminated Ground Water
Cost
$2,000
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Groundwater: High Risk
The site is still under investigation to further assess migration and receptor information.
Contaminants: Vinyl Chloride 2.47 ug/L Trichloroethylene (TCE) 2.5 ug/L Benzene 3.47 ug/L Bis(2-Ethylhexyl)Phthalate 80.0 ug/L Arsenic 193.0 ug/L Lead 835.0 ug/L
Soil: Low Risk
The site is still under investigation to further assess migration and receptor information.
Contaminants: Arsenic 8.5 mg/kg
Site ID: FGGM 17
CLOSED SANITARY LANDFILL
Landfill
Cost
$5.26M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Aug 2017
Contaminated Areas
Groundwater: High Risk
MONITORING WELL DATA REVEALS PLUME IS LEAVING SITE. WELLS ARE IMMEDIATELY DOWN GRADIENT OF CONTAMINATION
Contaminants: Trichloroethylene (TCE) 6.1 ug/L Benzene 19.0 ug/L Arsenic 43.200001 ug/L Lead 44.0 ug/L Manganese and compounds 3440.0 ug/L
Surface Water (Human): High Risk
DATA SHOWS IT IS LEAVING SITE. WELLS ARE IMMEDIATELY DOWN GRADIENT.
Contaminants: Chlorobenzene 2.0 ug/L Arsenic 2.58 ug/L Zinc 64.800003 ug/L Boron 454.0 ug/L
Site ID: FGGM 94
TRAP AND SKEET RANGE 17
Small Arms Range
Cost
$707K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Sep 2016
This site is under ongoing monitoring until Dec 2044
Contaminated Areas
Soil: High Risk
not enough information is known hunters are exposed to soil
Contaminants: Lead 44000.0 mg/kg
Site ID: FGGM 74
ARCHITECT OF THE CAPITOL
Storage Area
Cost
$221K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Aug 2017
Contaminated Areas
Groundwater: High Risk
IRON AND DICHLOROETHENE ARE NOT ON LIST.THEIR CONCENTRATIONS ARE 57200 AND 12 PPB RESPECTIVELY. THEIR RATIOS ARE 190.67AND 2.61 RESPECTIVELY. MONITORING WELL SITE IS ABOVE THREE QUIFERS USED EXTENTSIVELY FOR COUNTY WATER SUPPLY. HOWEVER,NO WELL IS IMMEDIATELY DOWN GRADIENT OF THE SOURCE.
Contaminants: Lead 14.399999 ug/L Naphthalene 16.0 ug/L Benzene 48.0 ug/L Toluene 96.0 ug/L Carbon Dichloride 180.0 ug/L Manganese and compounds 310.0 ug/L Chromium 344.0 ug/L Aluminum 26900.0 ug/L
Site ID: FGGM 07
DRMO DRUM SITE (OPERABLE UNIT 5)
Storage Area
Cost
$6.11M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Aug 2019
Contaminated Areas
Groundwater: High Risk
MONITORING WELL DATA REVEALS PLUME IS LEAVING SITE SITE IS ABOVE THREE AQUIFERS USED EXTENSIVELY FOR COUNTY WATER SUPPLY. HOWEVER, NO WELL IS IMMEDIATELY DOWN GRADIENT OF THE SOURCE.
Contaminants: 1,1-Dichloroethylene 12.0 ug/L Lead 19.4 ug/L Carbon Dichloride 180.0 ug/L Chromium 344.0 ug/L Aluminum 26900.0 ug/L
Soil: Low Risk
SURFACE/SUBSURFACE SOIL CONTAMINATION REMAINS ONSITE AND WILL BE COVERED BY NEW CONSTRUCTION UNTIL REMEDIATION IS COMPLETE, POTENTIALFOR EXPOSURE TO CONSTRUCTION WORKERS AN AND OCCUPING PERSONNEL.
Contaminants: Chlorinated Biphenyl 25.0 mg/kg
Site ID: FGGM 91
MISSILE REPAIR SHOP (OP UNIT 4)
Storage Area
Cost
$2,000
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Groundwater: Medium Risk
The site is still under investigation to further assess migration and receptor information.
Contaminants: Tetrachloroethylene 13.0 ug/L Arsenic 160.0 ug/L Lead 230.0 ug/L
Soil: Low Risk
The site is still under investigation to further assess migration and receptor information.
Contaminants: Arsenic 20.0 mg/kg
Site ID: FGGM 87
NIKE CONTROL SITE (OPERABLE UNIT 3)
Contaminated Ground Water
Cost
$2.27M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Aug 2018
This site is under ongoing monitoring until Aug 2048
Contaminated Areas
Groundwater: Medium Risk
Due to the relative ease with which the detected contamination can travel within groundwater and the close, it has the potential to migrate offsite. Because the contamination has entered the ground water and the relative ease with which these contaminants can travel through the different mediums, there is the potential these contaminants may migrate from the site and contaminate drinking water aquifer
Contaminants: Cadmium and compounds 45.3 ug/L Trichloroethylene (TCE) 49.1 ug/L Lead 349.0 ug/L Arsenic 429.0 ug/L
Soil: Low Risk
Because of the levels of contaminants found, and due to the known levels within the groundwater, there is the potential for further contamination and migration of these contaminants from the soil to the groundwater. Because the contamination has entered the ground water and the relative ease with which these contaminants can travel through the different mediums, there is the potential these contaminants may migrate from the site and contaminate drinking water aquifer
Contaminants: Arsenic 9.64 mg/kg Bis(2-Ethylhexyl)Phthalate 1400.0 mg/kg
Site ID: FGGM 90
TANK CLEANING SUPPLY (OP UNIT 4)
Storage Area
Cost
$2,000
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Groundwater: Medium Risk
The site is still under investigation to further assess migration and receptor information.
Contaminants: Trichloroethylene (TCE) 24.3 ug/L Bis(2-Ethylhexyl)Phthalate 26.3 ug/L Arsenic 110.0 ug/L Lead 250.0 ug/L Tetrachloroethylene 736.0 ug/L
Site ID: FGGM 37
KIMBROUGH ARMY HOSPITAL
Incinerator
Cost
$1.83M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Nov 2017
This site is under ongoing monitoring until Dec 2048
Contaminated Areas
Groundwater: Medium Risk
Limited potential for a complete exposure pathway as the site is highly developed. Limited potential for a receptor exposure. Drinking water supplied by public source and the site is highly developed.
Contaminants: Arsenic 38.0 ug/L
Soil: Low Risk
Limited potential for a complete exposure pathway as the site is highly developed. Limited potential for a receptor exposure as the site is highly developed.
Contaminants: Arsenic 11.0 mg/kg
Site ID: FGGM 45
CALIBRATION LAB BUILDING 2220
Contaminated Buildings
Cost
$2,000
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Groundwater: Low Risk
Limited potential for a complete exposure pathway as the site is supplied with public water. Limited potential for a receptor exposure as the site is supplied by public water.
Contaminants: Naphthalene 9.0 ug/L
Soil: Low Risk
Limited potential for a complete migration pathway as the site is highly developed. Limited potential for a receptor exposure as the site is highly developed.
Contaminants: Arsenic 3.0 mg/kg
Site ID: FGGM 51
BUILDING 2217
Spill Site Area
Cost
$2,000
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Soil: Low Risk
Limited potential for a complete exposure pathway as the site is highly developed and no longer used. Limited potential for a receptor exposure as the site is highly developed and no longer used.
Contaminants: Arsenic 14.0 mg/kg
Site ID: FGGM 89
TANK MAIN. FAC. SHOP-2 (OP UNIT 4)
Maintenance Yard
Cost
$2,000
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Soil: Low Risk
The site is still under investigation to further assess migration and receptor information.
Contaminants: Arsenic 14.0 mg/kg
Site ID: CCFGGM-97
CELL 3
Contaminated Fill
Cost
$12.1M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Oct 2017
This site is under ongoing monitoring until Oct 2049
Contaminated Areas
Soil: Low Risk
Due to the type and levels of contaminants detected at the surface, there is the potential for contaminant migration to adjacent soil, surface water, and groundwater. Although the contaminants are not generally considered highly mobile (under usual conditions) the potnetial for exposure cannot be ruled out.
Contaminants: Dioxin (2,3,7,8-TCDD) 1.79e-05 mg/kg Indeno(1,2,3-cd)Pyrene 0.3 mg/kg Benzo(b)Fluoranthene 0.8 mg/kg Benz(a)Anthracene 0.9 mg/kg PCBs 1.0 mg/kg Antimony and compounds 4.5 mg/kg Arsenic 6.8 mg/kg Vanadium 22.0 mg/kg Chromium 89.0 mg/kg Lead 576.0 mg/kg
Site ID: FGGM 18
ASP#2
Storage Area
Cost
Unknown
Final Cleanup Action
Apr 2016
Contaminated Areas
Soil: Low Risk
Limited potential for a complete exposure pathway. There is no data on ASP 2 so the data on ASP 1 which is reported to have contained the same material is used here. Limited potential for a receptor exposure. There is no data on ASP 2 so the data on ASP 1 which is reported to have contained the same material is used here.
Contaminants: Cobalt 4.66 mg/kg
Site ID: FGGM 86
MOTORPOOL FAC (OPERABLE UNIT 4)
Disposal Pit and Dry Well
Cost
$2,000
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Groundwater: Low Risk
Because the contamination has entered the ground water and the relative ease with which these contaminants can travel through the different mediums, there is the potential these contaminants may migrate from the site. Fort Meade is continually in the process of construction and demolition activities. Therefore, there is a potential for this soil to be encountered by grounds personnel or construction workers during routine utility line placement, minor constuction and
Contaminants: 1,1,2,2-Tetrachloroethane 7.86 ug/L Benzene 8.38 ug/L 1,2,4-Trimethylbenzene 29.6 ug/L
Soil: Low Risk
Arsenic levels with in the fort meade area are exceptionally high and potential exists for these contaminants to reach the groundwater and migrate offsite The site is still under investigation to further assess migration and receptor information.
Contaminants: Arsenic 17.8 mg/kg
Site ID: FGGM 08
COMP AMMO SUPPLY POINT #1
Storage Area
Cost
Unknown
Final Cleanup Action
Oct 2016
Contaminated Areas
Sediment (Human): Low Risk
Several metals (chromium, cobalt and iron) detected in elevated concentrations in sediment samples. The risk of exposure is limited. The risk to potential receptors is low as the site is controlled (fenced) and the concentrations of metals were low.
Contaminants: Chromium 34.1 mg/kg Iron 21700.0 mg/kg
Soil: Low Risk
Various metals exceeded their Residential screening and/or background levels; most notably arsenic and chromium. Limited risk to receptors under most future use scenerios.
Contaminants: Arsenic 2.75 mg/kg Chromium 14.5 mg/kg
Site ID: FGGM-95
LANDFILL SITES (FORMER)
Landfill
Cost
$2.47M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Aug 2017
Contaminated Areas
Groundwater: Low Risk
Due to the relative ease with which the detected contamination can travel within groundwater it has the potential to migrate offsite. Because the contamination has entered the ground water and the relative ease with which these contaminants can travel through the different mediums, there is the potential these contaminants may migrate from the site and contaminate drinking water aquifer
Contaminants: Arsenic 92.0 ug/L
Soil: Low Risk
Because of the levels of contaminants found there is the potential for further contamination and migration of these contaminants from the soil to the groundwater. Because of the relative ease with which these contaminants can travel through the different mediums, there is the potential these contaminants may migrate from the site and potentially contaminate drinking water aquifers.
Contaminants: Arsenic 0.0075 mg/kg Benzo(a)Pyrene 0.21 mg/kg
Site ID: FGGM 36
PHOTO LAB'S BLDG 4553, 6530
Contaminated Buildings
Cost
$3.35M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Nov 2017
This site is under ongoing monitoring until Oct 2048
Contaminated Areas
Soil: Low Risk
Limited potential for a complete exposure pathway to arsenic in soil; site highly developed. Limited; site highly developed.
Contaminants: Arsenic 7.1 mg/kg
Site ID: FGGM 49
DOL BUILDINGS 2286, 2246
Contaminated Buildings
Cost
$2,000
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2017
Contaminated Areas
Soil: Low Risk
Limited potential for a complete exposure pathway as the site is highly developed. Limited potential for a receptor exposure as the site is highly developed.
Contaminants: Arsenic 9.9 mg/kg
Site ID: FGGM 13
PEST. SHOP BLDG. 6621
Pesticide Shop
Cost
$1.52M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Dec 2014
This site is under ongoing monitoring until Aug 2043
31 Inactive Sites
Sites where military cleanup actions are complete, according to the DOD. Note that this status does not necessarily mean the site is no longer hazardous, as many of these sites are put under long-term monitoring or other restrictions.
Site ID: FGGM 20
ORDNANCE DEMO AREA
Explosive Ordnance Disposal Area
Cost
$1.02M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Nov 2002
This site is under ongoing monitoring until Dec 2030
Site ID: PBC AT MEADE
PBCS AT FORT MEADE
Site Never Existed
Cost
Unknown
Final Cleanup Action
Jan 2014
Site ID: FGGM-003-R-01
MORTAR RANGE
Unexploded Munitions and Ordnance Area
Cost
$374K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Jun 2014
This site is under ongoing monitoring until Jun 2043
Site ID: FGGM 85
UNEXPLODED ORDNANCE TIPTON ARMY AIRFIELD
Unexploded Munitions and Ordnance Area
Cost
$1.04M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Nov 1989
This site is under ongoing monitoring until Dec 2045
Site ID: FGGM 81
CLEAN FILL DUMP
Landfill
Cost
$921K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Sep 2000
This site is under ongoing monitoring until Dec 2028
Site ID: FGGM-002-R-01
HE IMPACT AND DISPOSAL
Unexploded Munitions and Ordnance Area
Cost
$298K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Aug 2001
This site is under ongoing monitoring until Dec 2045
Site ID: FGGM 93
MANOR VIEW DUMP SITE
Landfill
Cost
$1.87M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Oct 2014
This site is under ongoing monitoring until Jul 2045
Site ID: FGGM 71
BLDG 6522 EX INDR RNG
Contaminated Buildings
Cost
Unknown
Final Cleanup Action
Mar 2015
Site ID: FGGM 05
TROOP BOILER PLT (OPERABLE UNIT 2)
Spill Site Area
Cost
Unknown
Final Cleanup Action
Jan 1997
This site is under ongoing monitoring until Sep 2013
Site ID: FGGM 31
INACTIVE LANDFILLS 2 AND 3 - TIPTON
Landfill
Cost
$113K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Jun 1999
This site is under ongoing monitoring until Dec 2022
Site ID: FGGM-006-R-01
PISTOL RANGE B
Small Arms Range
Cost
Unknown
Final Cleanup Action
Apr 2007
Site ID: FGGM 19
ADV. WASTEWATER TREATMENT FACILITY
Waste Treatment Plant
Cost
Unknown
Final Cleanup Action
Jun 2012
Site ID: FGGM 73
MAINT. SHOPS BUILDINGS 85 AND 90
Contaminated Buildings
Cost
Unknown
Final Cleanup Action
Oct 1992
Site ID: FGGM 10
INACTIVE LANDFILL #1- TIPTON
Landfill
Cost
$122K
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Sep 1999
This site is under ongoing monitoring until Dec 2019
Site ID: FGGM 14
HAZARDOUS WASTE STORAGE (FORMER)
Contaminated Buildings
Cost
Unknown
Final Cleanup Action
Sep 2011
Site ID: FGGM 75
UNDERGROUND STORAGE TANKSS PRIOR TO 1984
Soil Contamination After Tank Removal
Cost
Unknown
Final Cleanup Action
Feb 2012
Site ID: FGGM 70
BLDG 6513 INDOOR RANGE
Contaminated Buildings
Cost
Unknown
Final Cleanup Action
Mar 2015
Site ID: FGGM 72
98 POL STORAGE TANK'S
Underground Storage Tanks
Cost
Unknown
Final Cleanup Action
Jan 1997
Site ID: FGGM-001-R-01
CLEAN FILL DUMP
Unexploded Munitions and Ordnance Area
Cost
Unknown
Final Cleanup Action
Jun 2003
This site is under ongoing monitoring until Sep 2019
Site ID: FGGM-003-R-02
TRAINING AREA MRS
Training and Maneuver Area
Cost
Unknown
Final Cleanup Action
Jan 2014
This site is under ongoing monitoring until Jan 2044
Site ID: FGGM 03
WATER TREATMENT PLANT (MEVA)
Spill Site Area
Cost
Unknown
Final Cleanup Action
Jul 2012
Site ID: FGGM-004-R-01
GRENADE & BAYONET RANGE
Unexploded Munitions and Ordnance Area
Cost
Unknown
Final Cleanup Action
Apr 2007
Site ID: FGGM-005-R-01
PISTOL RANGE A
Small Arms Range
Cost
Unknown
Final Cleanup Action
Apr 2007
Site ID: FGGM-007-R-01
INACTIVE LANDFILL 2
Unexploded Munitions and Ordnance Area
Cost
$2.87M
Cost in 2015 plus expected future cost of cleanup
Final Cleanup Action
Jun 2000
This site is under ongoing monitoring until Mar 2045
Site ID: FGGM 82
UNEXPLODED ORDNANCE REMOVAL
Unexploded Munitions and Ordnance Area
Cost
Unknown
Final Cleanup Action
Apr 1997
This site is under ongoing monitoring until Sep 2001
Site ID: FGGM 101
SITE M PARCEL 8
Landfill
Cost
Unknown
Final Cleanup Action
Dec 2007
Site ID: FGGM 11
GAS TRAINING BUILDING (FORMER)
Surface Disposal Area
Cost
Unknown
Final Cleanup Action
Mar 2015
Site ID: FGGM 21
MEDICAL WASTE SITE
Unknown Site Type
Cost
Unknown
Final Cleanup Action
Jun 1997
Site ID: FGGM 32
FIRE TRAINING AREA
Fire/Crash Training Area
Cost
Unknown
Final Cleanup Action
Aug 1998
Site ID: FGGM 78
GRANITE NIKE
Leach Field
Cost
Unknown
Final Cleanup Action
Dec 2001
This site is under ongoing monitoring until Jan 2004
Site ID: FGGM 80
HELICOPTER HANGAR 90
Maintenance Yard
Cost
Unknown
Final Cleanup Action
Dec 1998
Update (Dec. 5, 2017): We have changed the source of the installation cost data after being notified by the Department of Defense that they erroneously reported their own cost figures on the DERP website. We are now displaying the costs the department says are the most accurate available, from the Pentagon’s DERP database that we received in a FOIA request.
Note: The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.
Data: All data comes from the Defense Environmental Restoration Program and the U.S. Army Corps of Engineers, and will be released soon at the ProPublica Data Store. Read our methodology »