ARMY INSTALLATION ID: OH52118390NG00

JFHQ OH ARNG

columbus, Ohio

Cost So Far

$8.09M

Money already spent on the evaluation and cleanup of hazardous sites.

Expected Additional Cost

$16.3M

The estimated amount of money needed for evaluation and cleanup of hazardous sites at this installation.

Completion Date

2019

The date the DOD says cleanup of all sites was completed. Long term monitoring may continue after this date.

9 Hazardous Sites

Note: We are not showing a map of this installation's hazardous sites because we don't have location data for any of them. If you have more information, please contact us. The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.

6 Active Sites

Sites where military cleanup actions are still ongoing. The risk level of a site refers to a relative risk assessment made by the DOD, which prioritizes the cleanup of sites that pose greatest threat to safety, human health, and the environment.

Site ID: OHHQ-005-R-01

LAKE ERIE SHORELINE MRS

Unexploded Munitions and Ordnance Area

Cost

$14.3M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Jul 2019

This site is under ongoing monitoring until Jun 2049

Site ID: OHHQ-006-R-01

WEST SISTER ISLAND MRS

Unexploded Munitions and Ordnance Area

Cost

$367K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Oct 2017

This site is under ongoing monitoring until Sep 2047

Site ID: OHHQ-003-R-01

NDNODS CAMP ZALESKI RANGE

Site Funded Under Another Program

Cost

Unknown

Final Cleanup Action

Jan 2028

Site ID: OHHQ-001-R-01

NDNODS ASHTABULA RANGE

Site Funded Under Another Program

Cost

Unknown

Final Cleanup Action

Jan 2027

Site ID: OHHQ-002-R-01

NDNODS BOSTON MILLS TRAINING SITE

Site Funded Under Another Program

Cost

Unknown

Final Cleanup Action

Jan 2028

Site ID: OHHQ-005-R-02

LAKE ERIE SHORELINE MRS RESIDENTIAL

Unexploded Munitions and Ordnance Area

Cost

$1.67M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2018

This site is under ongoing monitoring until Sep 2048

3 Inactive Sites

Sites where military cleanup actions are complete, according to the DOD. Note that this status does not necessarily mean the site is no longer hazardous, as many of these sites are put under long-term monitoring or other restrictions.

Site ID: OHHQ-004-R-01

NDNODS SHREVE RANGE

Small Arms Range

Cost

Unknown

Final Cleanup Action

Sep 2012

Site ID: OHHQ-003-R-02

NDNODS CAMP ZALESKI RANGE

Small Arms Range

Cost

Unknown

Final Cleanup Action

Oct 2012

Site ID: OHHQ-004-R-02

NDNODS SHREVE RANGE

Small Arms Range

Cost

Unknown

Final Cleanup Action

Oct 2012

Update (Dec. 5, 2017): We have changed the source of the installation cost data after being notified by the Department of Defense that they erroneously reported their own cost figures on the DERP website. We are now displaying the costs the department says are the most accurate available, from the Pentagon’s DERP database that we received in a FOIA request.

Note: The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.

Data: All data comes from the Defense Environmental Restoration Program and the U.S. Army Corps of Engineers, and will be released soon at the ProPublica Data Store. Read our methodology »