DEFENSE LOGISTICS AGENCY INSTALLATION ID: VA397152075100

DSC RICHMOND

richmond, Virginia

Cost So Far

$75.2M

Money already spent on the evaluation and cleanup of hazardous sites.

Expected Additional Cost

$47.1M

The estimated amount of money needed for evaluation and cleanup of hazardous sites at this installation.

Expected Completion Date

2064

The date by which the DOD estimates cleanup of all sites will be complete. Long term monitoring may continue after this date.

33 Hazardous Sites

Note: We are not showing a map of this installation's hazardous sites because we don't have location data for any of them. If you have more information, please contact us. The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.

Land Controls & Restrictions

Many sites have been declared “clean” by the DOD but are still not safe for people. This military installation is safe only with the following conditions in place: deed restrictions, fences, signs. see more » fences deed restrictions notations in master plan other engineering control signs « see less

3 Active Sites

Sites where military cleanup actions are still ongoing. The risk level of a site refers to a relative risk assessment made by the DOD, which prioritizes the cleanup of sites that pose greatest threat to safety, human health, and the environment.

Site ID: 034

OU 6, AREA 50 GROUNDWATER

Contaminated Ground Water

Cost

$19M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Oct 2015

This site is under ongoing monitoring until Sep 2065

Contaminated Areas

Groundwater: High Risk

IT HAS BEEN DETERMINED THE CONTAMINATION HAS MOVED OFF-SITE AND APPEARS TO BE DISCHARGING INTO THE SURFACE WATER. THE POTENTIAL EXISTS FOR CONTAMINATION TO ENTER TO A RECEPTOR THROUGH GROUNDWATER AND SURFACE WATER.

Contaminants: ARSENIC 2.6 ug/L 1,2-DICHLOROETHANE (EDC) 27.7 ug/L CHLOROFORM 70.2 ug/L NAPHTHALENE 72.0 ug/L VINYL CHLORIDE 117.0 ug/L 1,4-DICHLOROBENZENE 150.0 ug/L TETRACHLOROETHYLENE 229.0 ug/L CHLOROBENZENE 381.0 ug/L TRICHLOROETHYLENE (TCE) 1900.0 ug/L CIS-DICHLOROETHYLENE 2380.0 ug/L

Sediment (Marine): High Risk

THE MIGRATION PATHWAY IS KNOWN TO BE COMPLETE. BIOTA ARE KNOWN TO EXIST IN THE STREAM BED.

Contaminants: BENZO(A)PYRENE 9.5 mg/kg BENZO(A)ANTHRACENE 10.0 mg/kg ZINC 94.0 mg/kg

Surface Water (Fresh): High Risk

THE MIGRATION PATHWAY IS KNOWN TO BE COMPLETE. FISH ARE KNOWN TO EXIST IN THE STREAM.

Contaminants: IRON 22800.0 ug/L

Surface Water (Human): High Risk

MATERIAL IN THE SOURCE AREA(S) HAVE BEEN DETECTED IN SURFACE WATERS. HUMAN RECEPTORS ARE LOCATED ALONG THE STREAM.

Contaminants: CHRYSENE 0.12 ug/L VINYL CHLORIDE 6.1 ug/L VANADIUM 7.2 ug/L ARSENIC 12.4 ug/L LEAD 35.8 ug/L STYRENE 120.0 ug/L ALUMINUM 4270.0 ug/L

Sediment (Human): Medium Risk

THE MIGRATION PATHWAY IS KNOWN TO BE COMPLETE. HUMAN RECEPTORS ARE KNOWN TO BE ALONG THE STREAM.

Contaminants: CHLORDANE 0.006 mg/kg DDD 0.018 mg/kg ARSENIC 31.0 mg/kg LEAD 77.6 mg/kg MANGANESE AND COMPOUNDS 138.0 mg/kg

See more details...

Site ID: 032

OU 7, FORMER FIRE TRAINING PIT GROUNDWATER

Contaminated Ground Water

Cost

$7.92M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Jan 2014

This site is under ongoing monitoring until Sep 2065

Contaminated Areas

Groundwater: High Risk

MATERIAL HAS BEEN DETECTED IN BOTH THE UPPER AND LOWER AQUIFERS. MOVEMENT HAS NOT BEEN DETECTED IN THE LOWER AQUIFER. THERE ARE NO KNOWN GROUNDWATER USERS DOWN GRADIENT OF THE CONTAMINATED PLUME. THE POTENTIAL DOES EXIST HOWEVER.

Contaminants: TETRACHLOROETHYLENE 23200.0 ug/L VINYL CHLORIDE 35600.0 ug/L TRICHLOROETHYLENE (TCE) 208000.0 ug/L

Surface Water (Human): Low Risk

KINGSLAND CREEK INTERSECTS THE LEADING EDGE OF THE OU-7 GROUNDWATER PLUME. PHYSICAL CHARACTERISTICS OF THE CREEK ARE NOT READILY SUITABLE FOR HUMAN RECREATIONAL USE.

Contaminants: BENZENE 6.7 ug/L METHYL TERT-BUTYL ETHER 12.3 ug/L

See more details...

Site ID: 036

OU 8, ACID NEUTRALIZATION PIT GROUNDWATER

Contaminated Ground Water

Cost

$20.2M

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Jun 2008

This site is under ongoing monitoring until Sep 2050

Contaminated Areas

Groundwater: High Risk

PATHWAY EVIDENT. POTENTIAL RECEPTOR.

Contaminants: VINYL CHLORIDE 0.773 ug/L 1,2-DICHLOROETHENE 5.7 ug/L CIS-DICHLOROETHYLENE 170.0 ug/L TRICHLOROETHYLENE (TCE) 539.0 ug/L TETRACHLOROETHYLENE 820.0 ug/L

See more details...

30 Inactive Sites

Sites where military cleanup actions are complete, according to the DOD. Note that this status does not necessarily mean the site is no longer hazardous, as many of these sites are put under long-term monitoring or other restrictions.

Site ID: 014

OU 12, PESTICIDES STORAGE AND MIXING FACILITY

Spill Site Area

Cost

$245K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Jan 2007

This site is under ongoing monitoring until Sep 2045

Site ID: 026

PART OU-3

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Sep 1993

Site ID: 002

OU 11, TRANSITORY SHELTER 202

Storage Area

Cost

$245K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

May 2008

This site is under ongoing monitoring until Sep 2045

Site ID: 018

CAP-2

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Apr 1996

Site ID: 019

IAG-6

Underground Storage Tanks

Cost

Unknown

Final Cleanup Action

Jun 1995

Site ID: 021

IAG-7

Mixed Waste Area

Cost

Unknown

Final Cleanup Action

Oct 1990

Site ID: 022

IAG-8

Storage Area

Cost

Unknown

Final Cleanup Action

Oct 1990

Site ID: 023

MISC-1

Pistol Range

Cost

Unknown

Final Cleanup Action

May 1996

Site ID: 024

IAG-9

Storage Area

Cost

Unknown

Final Cleanup Action

Oct 1990

Site ID: 025

IAG-10

Burn Area

Cost

Unknown

Final Cleanup Action

Oct 1990

Site ID: 027

OU-5

Disposal Pit and Dry Well

Cost

Unknown

Final Cleanup Action

Mar 2005

This site is under ongoing monitoring until Dec 2012

Site ID: 029

ESI-2

Surface Impoundment/Lagoon

Cost

Unknown

Final Cleanup Action

Sep 1994

Site ID: 030

PART OU-4

Above Ground Storage Tank

Cost

Unknown

Final Cleanup Action

Sep 1999

Site ID: 004

OU 1: MALATHION CONTAMINATION SITE

Spill Site Area

Cost

$235K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Oct 2004

This site is under ongoing monitoring until Sep 2045

Site ID: 006

OU 10, BUILDING 68 POLYCHLORINATED BIPHENYL (PCB) STORAGE

Spill Site Area

Cost

$245K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Jun 2008

This site is under ongoing monitoring until Sep 2045

Site ID: 001

OU 11, TRANSITORY SHELTER 202

Storage Area

Cost

Unknown

Final Cleanup Action

May 2008

This site is under ongoing monitoring until Dec 2014

Site ID: 033

CAP-1

Underground Storage Tanks

Cost

$241K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Nov 2008

This site is under ongoing monitoring until Sep 2045

Site ID: 037

OU 13, POLYCYCLIC AROMATIC HYDROCARBON AREA

Contaminated Fill

Cost

$235K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Oct 2013

This site is under ongoing monitoring until Sep 2045

Contaminated Areas

Soil: Low Risk

DATA COLLECTED FOR THE RI CONCLUDED THAT THE WASTES ARE NOT IN THE GROUNDWATER. THE MATERIAL IS BURIED AND NOT MOVING AWAY FROM THE SITE.

Contaminants: TCDD 0.005414 mg/kg FLUORENE 70.0 mg/kg INDENO(1,2,3-CD)PYRENE 100.0 mg/kg BENZ(A)ANTHRACENE 220.0 mg/kg ARSENIC 237.0 mg/kg BENZO(K)FLUORANTHENE 740.0 mg/kg BENZO(A)PYRENE 760.0 mg/kg BENZO(B)FLUORANTHENE 960.0 mg/kg FLUORANTHENE 1000.0 mg/kg

See more details...

Site ID: 010

IAG-1

Storage Area

Cost

Unknown

Final Cleanup Action

Oct 1990

Site ID: 011

IAG-2

Storage Area

Cost

Unknown

Final Cleanup Action

Oct 1990

Site ID: 012

IAG-3

Storage Area

Cost

Unknown

Final Cleanup Action

Oct 1990

Site ID: 013

IAG-4

Storage Area

Cost

Unknown

Final Cleanup Action

Oct 1990

Site ID: 015

IAG-5

Surface Disposal Area

Cost

Unknown

Final Cleanup Action

Oct 1990

Site ID: 017

PART OU-4

Fire/Crash Training Area

Cost

Unknown

Final Cleanup Action

Sep 2005

This site is under ongoing monitoring until Dec 2012

Site ID: 038

CAP-3

Underground Tank Farm

Cost

Unknown

Final Cleanup Action

Mar 1998

Site ID: 028

OU 1: OPEN STORAGE AREA

Storage Area

Cost

$235K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Oct 1992

This site is under ongoing monitoring until Sep 2045

Site ID: 008

OU 1: RECOUPMENT AREA

Storage Area

Cost

$235K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Oct 1992

This site is under ongoing monitoring until Sep 2045

Site ID: 031

OU 3, NATIONAL GUARD AREA

Spill Site Area

Cost

$277K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Sep 2005

This site is under ongoing monitoring until Sep 2045

Site ID: 009

OU 2, AREA 50 LANDFILL

Landfill

Cost

$235K

Cost in 2015 plus expected future cost of cleanup

Final Cleanup Action

Nov 2009

This site is under ongoing monitoring until Sep 2045

Contaminated Areas

Soil: High Risk

STUDIES INDICATE THAT SEMI-VOLATILES AND METALS ARE CONTAINED WITHIN THE AREA. VOLATILES HAVE BEEN FOUND IN THE GROUNDWATER. (SEE OU-6 & OU-9) BOTH HUMAN AND ECOLOGICAL RECEPTORS ARE IMPACTED VIA CONTAMINANT MOVEMENT IN BOTH GROUNDWATER AND SURFACE WATER.

Contaminants: 2,4-DIMETHYLPHENOL 7.4 mg/kg ARSENIC 41.0 mg/kg PCBS 47.0 mg/kg TRICHLOROETHYLENE (TCE) 53.4 mg/kg 1,4-DICHLOROBENZENE 92.0 mg/kg INDENO(1,2,3-CD)PYRENE 180.0 mg/kg BENZO(A)PYRENE 240.0 mg/kg BENZ(A)ANTHRACENE 360.0 mg/kg BENZO(B)FLUORANTHENE 540.0 mg/kg PYRENE 900.0 mg/kg

See more details...

Site ID: 020

ESI-1

Disposal Pit and Dry Well

Cost

Unknown

Final Cleanup Action

May 1994

Update (Dec. 5, 2017): We have changed the source of the installation cost data after being notified by the Department of Defense that they erroneously reported their own cost figures on the DERP website. We are now displaying the costs the department says are the most accurate available, from the Pentagon’s DERP database that we received in a FOIA request.

Note: The risk level of a site refers to a relative risk assessment made by the DOD to prioritize the cleanup of sites.

Data: All data comes from the Defense Environmental Restoration Program and the U.S. Army Corps of Engineers, and will be released soon at the ProPublica Data Store. Read our methodology »