« Money as a Folded Flag

Detailed Record

Commander's Small Scale Projects

Planned Start Month

Oct. 2011

Estimated Cost

$30,000

Status

Completed

Province

Paktiya

Regional Command

RC-East

Project Description

No project description provided.

Project Goals

Projects will include condolence payments of no more than $2500.00 and small impact projects of no more than $5000.00 Funds may also be used to make battle damage and hero payments as may be required in the event that operations cause damage to civilian property or loss of civilian life.

Results

With the completion of all the projects, the Team was able to create a much better relationship with the local villagers.

Updates

16 Sep 2011: PR&C request for $30K approved by CJ8 for 01 Oct.

25 Sep 2011: ToA conducted between PA's, from Harkins to Meredith.

02 Oct 2011: Drew $30K US @ 47.2 = 1,416.000 AFG.

22 Oct 2011: New corrected PR&C uploaded into Media.

3 Nov 2011: Agriculture project, CERPRCE2A016ZZ-01, in the amount of 236,000 AFG, was completed.

 

3 Nov 2011: Transportation project, CERPRCE2A016ZZ-02, in the amount of 236,000 AFG, was completed.

 

3 Nov 2011: Agriculture project, CERPRCE2A016ZZ-03, in the amount of 236,000 AFG, was completed.

5 Nov 2011: HERO Payment project, CERPRCE2A016ZZ-04, in the amount of 118,000 AFG, was completed.

15 Nov 2011: Agriculture project, CERPRCE2A016ZZ-05, in the amount of 118,000 AFG, was completed.

04 Dec 2011: RM clearing Memo received from CJ8.

06 Dec 2011: Pay Agents cleared through J8.

08 Dec 2011: Submitting for closure.
SOURCES

Illustrations: Sarah Way for ProPublica. Data: Assembled from several different Department of Defense databases by the Special Inspector General for Afghanistan Reconstruction and provided to ProPublica under a Freedom of Information Act Request.