| July 12, 1986 |
Southern Natural Gas Co |
0 |
0 |
$2.32M |
Miscellaneous Cause |
| Oct. 11, 1986 |
Alabama Gas Corporation |
0 |
1 |
$8,935 |
Third Party Excavation Damage |
| Feb. 19, 1987 |
Douglas Oil Purchasing Co Inc |
0 |
0 |
$0 |
Miscellaneous Cause |
| May 8, 1987 |
Alabama Gas Corporation |
0 |
1 |
$34.8K |
Miscellaneous Cause |
| Sept. 11, 1987 |
Alabama Gas Corporation |
0 |
1 |
$1,741 |
Miscellaneous Cause |
| Jan. 15, 1988 |
Alabama Gas Corporation |
0 |
1 |
$0 |
Unspecified Incorrect Operation |
| Feb. 3, 1988 |
South Alabama Utilities |
0 |
1 |
$0 |
Unspecified Incorrect Operation |
| Feb. 15, 1988 |
Dixie Pipeline Company Llc |
0 |
0 |
$0 |
Miscellaneous Cause |
| Feb. 15, 1988 |
Daphne Utility Dept, City Of |
0 |
1 |
$0 |
Third Party Excavation Damage |
| March 29, 1988 |
Cordova, Water Works & Gas Board Fo The City Of |
1 |
1 |
$127K |
External Corrosion |
| Dec. 7, 1988 |
Alabama Gas Corporation |
0 |
1 |
$128K |
Miscellaneous Cause |
| Jan. 4, 1989 |
Plantation Pipe Line Co |
0 |
0 |
$130K |
Third Party Excavation Damage |
| Jan. 14, 1989 |
Pleasant Grove Municipal Gas System, City Of |
2 |
0 |
$146K |
Unspecified Outside Force Damage |
| Sept. 28, 1989 |
Alabama Gas Corporation |
0 |
1 |
$179K |
Third Party Excavation Damage |
| March 1, 1990 |
Alabama Gas Corporation |
0 |
0 |
$287K |
Third Party Excavation Damage |
| Dec. 13, 1990 |
Dixie Pipeline Company Llc |
0 |
0 |
$3,024 |
Malfunction Of Control/Relief Equipment |
| May 24, 1991 |
Colonial Pipeline Co |
0 |
0 |
$4,531 |
Internal Corrosion |
| Oct. 9, 1991 |
Jacksonville Water Work, Gas & Sewer Board |
0 |
1 |
$75.5K |
Third Party Excavation Damage |
| Nov. 1, 1991 |
Mobile Gas Service Corp |
0 |
2 |
$0 |
Unspecified Incorrect Operation |
| Nov. 13, 1991 |
Colonial Pipeline Co |
0 |
0 |
$0 |
Miscellaneous Cause |
| Jan. 12, 1992 |
Alabama Gas Corporation |
0 |
1 |
$0 |
Miscellaneous Cause |
| June 24, 1992 |
Decatur Utilities Decatur Gas Department |
0 |
1 |
$295K |
Third Party Excavation Damage |
| July 16, 1992 |
Colonial Pipeline Co |
0 |
0 |
$7,366 |
Internal Corrosion |
| July 16, 1992 |
Hunt Refining Co |
0 |
0 |
$736 |
Operator/Contractor Excavation Damage |
| Sept. 29, 1992 |
Alabama Gas Corporation |
0 |
1 |
$0 |
Miscellaneous Cause |
| Oct. 5, 1992 |
Transcontinental Gas Pipe Line Company |
0 |
0 |
$2.74M |
Miscellaneous Cause |
| Nov. 19, 1992 |
Colonial Pipeline Co |
0 |
0 |
$7,366 |
Miscellaneous Cause |
| Nov. 25, 1992 |
Oneonta Gas Dept |
0 |
1 |
$0 |
Operator/Contractor Excavation Damage |
| May 27, 1993 |
Enstar Natural Gas Co |
0 |
0 |
$360K |
Unspecified Outside Force Damage |
| June 3, 1993 |
Transcontinental Gas Pipe Line Company |
0 |
1 |
$0 |
Unspecified Mat'l/Weld/Equip Failure |
| Jan. 12, 1994 |
Alabama Gas Corporation |
0 |
2 |
$0 |
Third Party Excavation Damage |
| June 29, 1994 |
Colonial Pipeline Co |
0 |
0 |
$7,051 |
Operator/Contractor Excavation Damage |
| Jan. 1, 1995 |
Exxon Co Usa New Orleans Production Organization |
0 |
0 |
$290K |
Miscellaneous Cause |
| Jan. 9, 1995 |
Exxon Co Usa New Orleans Production Organization |
0 |
0 |
$152K |
Miscellaneous Cause |
| Nov. 2, 1995 |
Enterprise Products Co |
0 |
0 |
$22.5K |
Miscellaneous Cause |
| Dec. 6, 1995 |
Marshall County Gas District |
0 |
1 |
$0 |
Miscellaneous Cause |
| June 24, 1996 |
Hunt Refining Co |
0 |
0 |
$0 |
External Corrosion |
| Aug. 30, 1996 |
Marshall County Gas District |
1 |
0 |
$0 |
Earth Movement |
| Oct. 17, 1996 |
Alabama Gas Corporation |
0 |
1 |
$0 |
Third Party Excavation Damage |
| Dec. 23, 1996 |
Koch Gateway Pipeline Co |
0 |
0 |
$110K |
Third Party Excavation Damage |
| Jan. 2, 1997 |
Transcontinental Gas Pipe Line Company |
0 |
0 |
$101K |
Third Party Excavation Damage |
| March 12, 1997 |
Trussville, Utilities Board, City Of |
0 |
1 |
$133K |
Third Party Excavation Damage |
| April 8, 1997 |
Southern Natural Gas Co |
0 |
1 |
$0 |
Miscellaneous Cause |
| Nov. 11, 1997 |
Mobile Gas Service Corp |
0 |
1 |
$0 |
Miscellaneous Cause |
| July 15, 1998 |
Conecuh Monroe Counties Gas Dist |
0 |
1 |
$224K |
Third Party Excavation Damage |
| Oct. 15, 1998 |
Fultondale Gas Board |
0 |
1 |
$0 |
Unspecified Incorrect Operation |
| Jan. 22, 1999 |
Bridgeport Utilities Board |
4 |
5 |
$0 |
Third Party Excavation Damage |
| May 1, 1999 |
Southeast Alabama Gas District |
0 |
1 |
$117K |
Third Party Excavation Damage |
| March 17, 2000 |
Alabama Gas Corporation |
0 |
0 |
$509K |
Third Party Excavation Damage |
| Aug. 3, 2000 |
Alabama Gas Corporation |
0 |
0 |
$127K |
Miscellaneous Cause |
| Aug. 16, 2000 |
Childersburg Gas Board |
1 |
0 |
$636 |
Miscellaneous Cause |
| Sept. 28, 2000 |
Marshall County Gas District |
1 |
0 |
$0 |
Third Party Excavation Damage |
| Oct. 2, 2000 |
Alabama Gas Corporation |
0 |
1 |
$63.7K |
Third Party Excavation Damage |
| Nov. 1, 2000 |
Alabama Gas Corporation |
0 |
1 |
$0 |
Miscellaneous Cause |
| Jan. 9, 2001 |
Alabama Gas Corporation |
0 |
0 |
$103K |
Unspecified Mat'l/Weld/Equip Failure |
| Jan. 16, 2001 |
Southern Natural Gas Co |
0 |
0 |
$271K |
External Corrosion |
| Jan. 10, 2002 |
Shell Chemical Co |
0 |
0 |
$232K |
Third Party Excavation Damage |
| June 28, 2002 |
Transcontinental Gas Pipe Line Company |
0 |
0 |
$612K |
Joint/Fitting/Component |
| Sept. 20, 2002 |
Florida Gas Transmission Co |
0 |
0 |
$196K |
Fillet Weld |
| April 7, 2003 |
Plantation Pipe Line Co |
0 |
0 |
$332K |
Joint/Fitting/Component |
| June 4, 2003 |
Plantation Pipe Line Co |
0 |
0 |
$301K |
Third Party Excavation Damage |
| Oct. 6, 2003 |
Mobile Gas Service Corp |
0 |
1 |
$2,405 |
Third Party Excavation Damage |
| Oct. 20, 2003 |
Transmontaigne Operating Company L.P. |
0 |
0 |
$12.5K |
Unspecified Incorrect Operation |
| Nov. 19, 2003 |
Alabama Gas Corporation |
0 |
1 |
$5,491 |
Third Party Excavation Damage |
| Nov. 23, 2003 |
Southern Natural Gas Co |
0 |
1 |
$0 |
Non Threaded Connection Failure |
| Dec. 10, 2003 |
El Paso Field Services |
0 |
1 |
$32.2K |
Vehicle Not Engaged In Excavation |
| Jan. 13, 2004 |
Gulf South Pipeline Company, Lp |
0 |
0 |
$131K |
Unknown Cause |
| Jan. 20, 2004 |
Alabama Gas Corporation |
1 |
0 |
$148K |
Miscellaneous Cause |
| Jan. 26, 2004 |
Mobile Gas Service Corp |
0 |
0 |
$119K |
Third Party Excavation Damage |
| March 21, 2004 |
Alabama Gas Corporation |
1 |
0 |
$22K |
Third Party Excavation Damage |
| Oct. 5, 2004 |
Marshall County Gas District |
0 |
1 |
$0 |
Joint/Fitting/Component |
| Oct. 21, 2004 |
Plantation Pipe Line Co |
0 |
0 |
$0 |
Unspecified Incorrect Operation |
| Dec. 27, 2004 |
Hunt Refining Co |
0 |
0 |
$821K |
Third Party Excavation Damage |
| Jan. 18, 2005 |
Colonial Pipeline Co |
0 |
0 |
$61.9K |
Miscellaneous Cause |
| Oct. 10, 2005 |
Alabama Gas Corporation |
3 |
0 |
$58.6K |
Unknown Cause |
| May 16, 2006 |
Enterprise Products Operating Llc |
0 |
0 |
$78.8K |
Lightning |
| Aug. 13, 2006 |
Colonial Pipeline Co |
0 |
0 |
$150K |
Malfunction Of Control/Relief Equipment |
| Jan. 2, 2007 |
Enterprise Products Operating Llc |
0 |
0 |
$56.2K |
Lightning |
| Jan. 23, 2007 |
Southern Natural Gas Co |
0 |
0 |
$1.47M |
Butt Weld |
| Feb. 1, 2007 |
Alabama Gas Corporation |
0 |
0 |
$271K |
Miscellaneous Cause |
| Sept. 12, 2007 |
Colonial Pipeline Co |
0 |
0 |
$260K |
Non Threaded Connection Failure |
| Sept. 19, 2007 |
Transcontinental Gas Pipe Line Company |
0 |
0 |
$329K |
External Corrosion |
| Dec. 21, 2007 |
Southern Natural Gas Co |
0 |
0 |
$622K |
External Corrosion |
| Jan. 26, 2008 |
Southern Natural Gas Co |
0 |
0 |
$196K |
Body Of Pipe |
| March 14, 2008 |
Southern Natural Gas Co |
0 |
0 |
$144K |
Butt Weld |
| Nov. 20, 2008 |
Colonial Pipeline Co |
0 |
0 |
$121K |
Unspecified Incorrect Operation |
| Dec. 29, 2008 |
Bp Pipeline (North America) Inc. |
0 |
0 |
$1.64M |
Lightning |
| March 29, 2009 |
Dekalb Cherokee Counties Gas District |
0 |
1 |
$175K |
Unknown Cause |
| Oct. 1, 2009 |
Dcp Midstream |
0 |
0 |
$1.47M |
Miscellaneous Cause |
| Dec. 31, 2009 |
Southern Natural Gas Co |
0 |
0 |
$271K |
Body Of Pipe |
| Jan. 29, 2010 |
Florence Gas Dept, City Of |
0 |
1 |
$91.8K |
Vehicle Not Engaged In Excavation |
| April 29, 2010 |
Mobile Gas Service Corp |
0 |
1 |
$0 |
Unknown Cause |
| Oct. 28, 2010 |
Southern Natural Gas Co |
0 |
0 |
$236K |
Miscellaneous Cause |
| Jan. 1, 2011 |
Alabama Gas Corporation |
0 |
0 |
$707K |
Mechanical Fitting |
| Feb. 18, 2011 |
Southern Natural Gas Co |
0 |
0 |
$173K |
Construction, Installation Or Fabrication Related |
| Dec. 3, 2011 |
Transcontinental Gas Pipe Line Company |
0 |
0 |
$7.66M |
External Corrosion |
| Dec. 6, 2011 |
Colonial Pipeline Co |
0 |
0 |
$833K |
Incorrect Installation |