14
Incidents
0Fatalities
0Injuries
Find Pipeline Incidents
Or see incidents by year:
Date | Location | Fatalities | Injuries | Property Damage | Cause |
---|---|---|---|---|---|
Nov. 11, 1987 | Wyoming | 0 | 0 | $7,837 | Unspecified Pipe Body Or Seam |
Oct. 12, 1992 | Wyoming | 0 | 0 | $176,806 | Third Party Excavation Damage |
March 1, 1993 | Montana | 0 | 0 | $21,610 | Unspecified Pipe Body Or Seam |
Feb. 18, 2000 | Wyoming | 0 | 0 | $25,466 | Operator/Contractor Excavation Damage |
March 3, 2000 | Wyoming | 0 | 0 | $38,199 | External Corrosion |
June 10, 2003 | Montana | 0 | 0 | $7,819 | Non Threaded Connection Failure |
March 3, 2005 | Wyoming | 0 | 0 | $3,518 | Third Party Excavation Damage |
Jan. 11, 2008 | North Dakota | 0 | 0 | $6,156 | Operator/Contractor Excavation Damage |
July 15, 2008 | Wyoming | 0 | 0 | $39,657 | Internal Corrosion |
Aug. 10, 2009 | Wyoming | 0 | 0 | $38,184 | Unspecified Incorrect Operation |
Nov. 13, 2011 | North Dakota | 0 | 0 | $40,343 | Third Party Excavation Damage |
Nov. 14, 2011 | Wyoming | 0 | 0 | $335,801 | Non Threaded Connection Failure |
Dec. 6, 2011 | North Dakota | 0 | 0 | $21,232 | Third Party Excavation Damage |
Dec. 9, 2011 | North Dakota | 0 | 0 | $59,525 | Third Party Excavation Damage |