Recipient | Amount | Type | Description | Federal Dept./Agency | Date |
---|---|---|---|---|---|
NORTHWIND ENGINEERING, LLC | $656,624 | Contract | : Remodeling of a high elevation camp ground. | Agriculture, Department of / Forest Service | 8/04/2010 |
DJ&A, P.C. | $49,518 | Contract | : This contract provided reconstruction staking on Big Creek Road on the Idaho Panhandle National Forest. | Agriculture, Department of / Forest Service | 7/15/2010 |
HARVEY'S PLUMBING AND EXCAVATING LLC | $949,523 | Contract | : Forest Road Gravel Resurfacing for the Northern Half of the Green MOuntain National Forest | Agriculture, Department of / Forest Service | 8/11/2009 |
PUERTO RICO ALARM SYSTEMS INC | $127,949 | Contract | : IITF AND SABANA SECURITY CAMERAS | Agriculture, Department of / Forest Service | 5/27/2010 |
SHASTA SERVICES, INC. | $864,429 | Contract | : Construct new 2750 SF office building for the U.S.D.A. Forest Service in McCloud, CA | Agriculture, Department of / Forest Service | 7/21/2010 |
WOOD'S CRUSHING & HAULING INC | $275,598 | Contract | : Rock crushing and placing on Forest Service roads. Grading and placing gravel. We also put in a culvert and cleaned culverts. | Agriculture, Department of / Forest Service | 2/02/2010 |
THOMAS,ROBERT E | $162,892 | Contract | : Camp ground restoration at Lake Conasauga, Jacks River, Chestnut Mountain, Cottonwood and Houston Valley; Timber Border Installation at Jacks River | Agriculture, Department of / Forest Service | 6/23/2010 |
QUICKSILVER CONTRACTING COMPANY | $162,704 | Contract | : OPINE 4 - PRECOMMERCIAL TREE THINNING AND SLASH TREATMENT | Agriculture, Department of / Forest Service | 7/28/2010 |
THREE C CONSTRUCTION, INC. | $495,000 | Contract | : Empire CIM-05-03R ARRA Design/Build Services For Aquatic Organism Passage. Location: Plumas National Forest 159 Lawrence St., Quincy CA 95971 US | Agriculture, Department of / Forest Service | 7/23/2010 |
RICHARDSON ENTERPRISES, INC. | $170,294 | Contract | : Clearwater, North Fork Site Rehab | Agriculture, Department of / Forest Service | 9/23/2010 |
MCMAHAN & ASSOCIATES, P.A. | $24,350 | Contract | : Re-surveying, marking, signing, and painting U.S. Forest Service boundary lines. | Agriculture, Department of / Forest Service | 8/10/2010 |
NOBLE EXCAVATING, INC. | $395,138 | Contract | : Removal of 3 culverts and installation of 2 new bidges and 1 multi plate steel arch pipe. Work includes excavation, stream work, and road work. | Agriculture, Department of / Forest Service | 7/13/2010 |
ED INTERIORS CONTRACTOR, INC. | $267,067 | Contract | : RECOVERY - CIM-1201-05F IITF Deferred Maintenance - Construction, Rio Piedras, PR Consist in Repair exterior stairs, Painting of Entire building roof waterproofing andinsulation, replacement if Air Consitioning Units; Replace of Lighting fixtures; upgrad | Agriculture, Department of / Forest Service | 8/31/2010 |
MARKO CONSTRUCTION GROUP, INC. | $97,354 | Contract | : NORTH FORK PAVING, SIERRA NATIONAL FOREST | Agriculture, Department of / Forest Service | 8/05/2010 |
SCHLEGEL & SONS CONTRACTORS, INC | $46,084 | Contract | : Recovery Herrig Creek and Wild Bill Creek culvert replacement project. | Agriculture, Department of / Forest Service | 7/27/2010 |
WHITE SHIELD, INC. | $10,000 | Contract | : Road 23 Hazardous Materials Response and Testing for Olympic National Forest. Dig test holes and sample at three depths for apparent petroleum residues. Analyze samples and report within 48 hours with data summary and recommendations. | Agriculture, Department of / Forest Service | 9/21/2010 |
WEE HAUL TRANSPORTATION LLC | $24,500 | Contract | : Silvacultral Project Manager. | Agriculture, Department of / Forest Service | 5/05/2010 |
CONSTRUCTION SERVICES OF SOMERSET, INC. | $2,155,709 | Contract | : Greening and renovation of Connecticut Forest Service Research Facilities in Hamden and Ansonia, CT. This includes upgrading and replacing HVAC Systems & Finishes in the VBR Bldg 3 - Ansonia, Replacing Environmental Growth Chambers in both locations, Rep | Agriculture, Department of / Forest Service | 8/16/2010 |
ALGERINE WEST CONSTRUCTION | $53,974 | Contract | : Road recommisioning installed culvert pipes and rocked. Decommisioning other roads to natural state. | Agriculture, Department of / Forest Service | 7/22/2010 |
BMJS CONTRACTING, INC. | $151,090 | Contract | : Installation of new water well, controls, piping, and remodeling of existing pump house and water lines. | Agriculture, Department of / Forest Service | 8/05/2010 |
RAMOS REFORESTATION, INC. | $111,240 | Contract | : Thinning and Hand Piling | Agriculture, Department of / Forest Service | 6/02/2010 |
R & S EXCAVATION INC | $175,854 | Contract | : APALACHICOLA DRAINAGE REHABILITATION, NATIONAL FORESTS IN FLORIDA. REMOVE OLD PIPES AND INSTALLATION OF BITUMINOUS COATED CORRUGATED ARCH PIPES, VARIOUS SIZES. | Agriculture, Department of / Forest Service | 4/13/2010 |
VALLEY TIMBER RESOURCE INC | $195,164 | Contract | : Roadside Brushing,This work consists of cutting all vegetative growth, including trees and other vegetation less than 5 inches in diameter measured 6 inches above the ground, on roadway surfaces and roadsides. Danger Tree Slash clean up, This work consi | Agriculture, Department of / Forest Service | 7/07/2010 |
EDL CONSTRUCTION, INC. | $119,640 | Contract | : CAMINO REAL RANGER STATION PV SYSTEM | Agriculture, Department of / Forest Service | 9/24/2010 |
NORTHWEST TREE & RECLAMATION CO | $63,325 | Contract | : Noxious weed spraying along roadsides, district sites and log landings. | Agriculture, Department of / Forest Service | 5/17/2010 |
EAGLE DEER RESERVE LIMITED | $105,000 | Contract | : contract just awarded, no data yet | Agriculture, Department of / Forest Service | 4/14/2010 |
LANE & CO., INC. | $94,146 | Contract | : Conversion of 4 water well pumps to solar powered pumps with battery backups and water disinfecting treatment systems in 3 locations in the San Juan National Forest. | Agriculture, Department of / Forest Service | 6/01/2010 |
PACIFIC COAST CONTRACTING, INC. | $248,398 | Contract | : thinning of trees and hand piling in the woods | Agriculture, Department of / Forest Service | 7/13/2010 |
SUMMIT ENGINEERING CORPORATION | $62,318 | Contract | : Professional Surveying Services for the Clear Creek Cadastral Survey. | Agriculture, Department of / Forest Service | 1/15/2010 |
GRAYBACK FORESTRY, INC. | $1,087,759 | Contract | : Hand pile, slash and burning of multiple units on the Daimond Lake Ranger District by cutting down trees and brush and piling it into piles to burn later with gas and diesel fuel and matches. | Agriculture, Department of / Forest Service | 7/20/2010 |
WARM SPRINGS GEO VISIONS | $132,264 | Contract | : Manuscript/Digitize surve blocks from previous heritage inventory projects. Manuscripting will be completed using the protocols developed by the contractor under task order # AG-04M3-D-0129. The project requires specific tasks to be completed, wich incl | Agriculture, Department of / Forest Service | 7/25/2010 |
PERFORMANCE PLUMBING & MECHANICAL, INC. | $465,095 | Contract | : Water system improvements. Installed 2 20,000 water tanks and related piping along with telemetry system from well to monitor tank levels. | Agriculture, Department of / Forest Service | 9/01/2010 |
MUNOZ, AURELIO | $258,279 | Contract | : Hand Thinning | Agriculture, Department of / Forest Service | 7/19/2010 |
CENTRAL NEVADA SUPPLY LLC | $95,201 | Contract | : Esmeralda County Road improvement. Clearing and grubbing along designated areas. Roadway Excavation as required to construct one Low Water Crossing. Filling washouts along the edge of the Traveled Ways. Placing Riprap as indicated and Road Signs at de | Agriculture, Department of / Forest Service | 7/12/2010 |
G M C CONTRACTING INC | $1,160,331 | Contract | : Repair, correct drainage and resurface Snug Harbor Road #1030. The project included staking, road reconditioning, excavation, borrow, riprap, surfacing, drainage, culverts, steam pipes and signage. Subcontract awards were for construction surveying and ma | Agriculture, Department of / Forest Service | 1/21/2010 |
QUALITY DOOR & HARDWARE INC. | $24,449 | Contract | : MISCELLANEOUS CONSTRUCTION MATERIALS: SARGENT BRAND, DOOR LOCKS, WITH LEVER HANDLE, PRIVACY/BATHROOM TYPE FUNCTION OF DOOR LOCK. WILL BE MOUNTED ON DOOR TO OPEN, CLOSE, SECURE. | Agriculture, Department of / Forest Service | 9/16/2010 |
L B CONSTRUCTION | $240,000 | Contract | : Laguna Air Force Base Fencing Project | Agriculture, Department of / Forest Service | 4/13/2010 |
B C CONCRETE INC | $8,432 | Contract | : Supply parts for latrines in Bitterroot National Forest. | Agriculture, Department of / Forest Service | 6/11/2010 |
BIZZAK LOGGING | $1,806 | Contract | : Noxious Weed Treatment | Agriculture, Department of / Forest Service | 12/31/2009 |
WOOD, ANTHONY J | $1,097,197 | Contract | : brush removal along the sides of forest service roads with machines that cut and mulch the brush in the same manner as a lawn mower, followed by a fire crew with chain saws and a water truck to clean up large limbs and logs left by brushing machine, as we | Agriculture, Department of / Forest Service | 2/26/2010 |
BURNETTE, KYLE | $61,888 | Contract | : Work includes furnishing all materials, equipment, and labor required to rehabilitate approximately 1.4 miles of trail. Work includes installation of up to 16 trail bridges with curbs or rails, improvement of existing waterbars for easier access, adding a | Agriculture, Department of / Forest Service | 4/07/2010 |
ROADTECH INC | $118,808 | Contract | : Road 202 Resurfacing ARRA Forest wide BMPS | Agriculture, Department of / Forest Service | 4/29/2010 |
BELL & PHILLIPS SURVEYING, PLLC | $39,188 | Contract | : Cadastral survey of Tornado Salvage Area in Jones County, North Carolina, consisting of 2.10 miles, to include surveying, marking and signing boundary lines, verifying and perpetuating property corners, preparing a plat of the surveyed property Cadastr | Agriculture, Department of / Forest Service | 8/16/2010 |
WOODWORTH LOGGING INC | $85,680 | Contract | : Copper hand thinning and machine piling | Agriculture, Department of / Forest Service | 5/07/2010 |
SURV-KAP, LLC | $4,748 | Contract | : Type A Delineator Posts with holes and no tabs are designed for small signs, reflectors and object markers. | Agriculture, Department of / Forest Service | 8/20/2010 |
WOODSIDE, RAYMOND R | $22,560 | Contract | : This job included clearing trails of logs, sticks and rocks for the United States Forest Service in the Scapegoat Wilderness of Montana. The amount I billed and the amount of the original bid amount are not the same because some of the mileages on the bi | Agriculture, Department of / Forest Service | 5/06/2010 |
PAYNE & STALCUP CONSTRUCTION COMPANY,INC | $63,981 | Contract | : Trail Maintenance Services | Agriculture, Department of / Forest Service | 7/13/2010 |
HANGING ROCK EXCAVATION & CONSTRUCTION, INC. | $86,228 | Contract | : Haul/Stockpile/Place/Compact rock on various recreational sites | Agriculture, Department of / Forest Service | 8/07/2010 |
MOHAWK METAL COMPANY | $80,000 | Contract | : Single source re-fabrication of 80' EZ Bridge for US Forest Service. Plus Delivery to US Forest Service supply yard. | Agriculture, Department of / Forest Service | 9/09/2010 |
NORTH STAR CONSTRUCTION AND ENGINEERING, INC | $209,148 | Contract | : Design and Repair of the Crocker Guard Station in the Plumas National Forest. This project involves design work and construction required to repair and stabilize Crocker Guard Station including foundation repair and reconstruction, roof replacement, and s | Agriculture, Department of / Forest Service | 8/13/2010 |
EDSAL MACHINE PRODUCTS, INC. | $29,785 | Contract | : MANUFACTURE OF ALUMINUM BOUNDARY POSTS | Agriculture, Department of / Forest Service | 9/22/2010 |
CHACON BROTHERS | $11,500 | Contract | : Contractor performed 103 acres of thinning & loft, and 6 acres of thinning and pile, which included ponderosa pine with some white fir and douglas. | Agriculture, Department of / Forest Service | 7/28/2010 |
SUNLAND BUILDERS INC | $100,175 | Contract | : Roadway repair | Agriculture, Department of / Forest Service | 8/04/2010 |
JOI FOREST, INC | $125,520 | Contract | : Precommercial Thinning | Agriculture, Department of / Forest Service | 9/22/2009 |
R. J. THOMAS MANUFACTURING COMPANY, INC. | $24,295 | Contract | : CAPITAL IMPROVEMENT & MAINTENANCE - MISC PREFABRICATED STRUCTURES | Agriculture, Department of / Forest Service | 9/17/2010 |
SIERRA ENGINEERS | $168,375 | Contract | : To construct and install a trail bridge across the south fork of the Salmon River in Northern California. | Agriculture, Department of / Forest Service | 8/27/2010 |
INDIAN EYES, LLC | $14,144 | Contract | : Support construction and maintenance services with requested rental equipment. | Agriculture, Department of / Forest Service | 1/15/2010 |
NORTH STAR PAVING & CONSTRUCTION INC | $1,699,517 | Contract | : Russian River Trail Accessibility Project. This project will design & construct approximately 1,000 LF of handicap accessible trail with a railing, a switchback, benches and rest areas. Construction of the trail will require construction of an upper and | Agriculture, Department of / Forest Service | 9/13/2010 |
CR LOGGING INC | $608,765 | Contract | : Stewardship authority would assist in the removal of non-merchantable materials within the project area and accomplish goals of reducing hazardous fuels, reducing the risk of mountain pine beetle infestation, and providing a sustainable supply of commerci | Agriculture, Department of / Forest Service | 5/24/2010 |
CUTTING EDGE FORESTRY, INC. | $17,464 | Contract | : NEPA READY HAZARDOUS FUELS TREATMENTS FOR TAOS COUNTY-LA JARA/FUELBREAK-HAND TREE THINNING AND LOP/SCATTER SLASH | Agriculture, Department of / Forest Service | 7/10/2010 |
G & L EXTERIORS INC | $91,995 | Contract | : REMOVE AND REPLACE SIDING REMOVE AND REPLACE BATHROOMS DOOR SAND AND PAINT OUT BUILDINGS MOVE BUILDING REMOVE AND REPLACE WOOD STOVE | Agriculture, Department of / Forest Service | 5/27/2010 |
AMERICAN INTEGRATED SERVICES, INC. | $195,038 | Contract | : Remove loose and flaky lead based paint and encapsulation from D building and carport. Minor asbestos removal. | Agriculture, Department of / Forest Service | 6/21/2010 |
GROVES, RAY ELLIS | $48,356 | Contract | : Hamby Fork Road 651 Shoulder Repairs | Agriculture, Department of / Forest Service | 7/30/2010 |
DEVILS LAKE ROCK COMPANY | $93,271 | Contract | : Drift Creek Falls Trailhead Parking Lot Reconsruction | Agriculture, Department of / Forest Service | 5/27/2010 |
PATRICK ALBIN CARLSON JOINT VENTURE, LLC | $1,670,750 | Contract | : The project includes design and construction of a trail bridge over the Placer River just northwest of the Spencer Glacier in Alaska. Estimated bridge length is between 250 and 300 feet. The PACJV shall design and build a single span bridge with abutments | Agriculture, Department of / Forest Service | 8/11/2010 |
DJ&A, P.C. | $19,928 | Contract | : This contract will provide construction management/program manager services for the Malheur National Forest. | Agriculture, Department of / Forest Service | 8/03/2010 |
KLB EXHIBITS | $18,108 | Contract | : Interpretive Sign Fabrication | Agriculture, Department of / Forest Service | 8/10/2010 |
FUTURE FOREST LLC | $388,868 | Contract | : Precommercial thinning and treatment of the Brushy Task Order | Agriculture, Department of / Forest Service | 9/28/2010 |
HAMMER LGC, INC. | $1,131,903 | Contract | : New trail construction to include clearing and grubbing with all necessary drainage structures,and trail restoration. | Agriculture, Department of / Forest Service | 8/05/2010 |
C-D PRODUCTS, INC | $22,075 | Contract | : signage for Nee-Me-Poo Trail Markers | Agriculture, Department of / Forest Service | 8/18/2010 |
PAYNE & STALCUP CONSTRUCTION COMPANY,INC | $31,195 | Contract | : Recreation Repair on the Andrew Pickens Ranger District. | Agriculture, Department of / Forest Service | 3/30/2010 |
PALEOWEST, L.L.C. | $109,864 | Contract | : The Apache/Sitgreaves National Forests proposes to remove small diameter ponderosa pine trees within the Mineral C Wildland Urban Interface (WUI) Project. The purpose of the project is to establish a buffer around private property adjacent to National For | Agriculture, Department of / Forest Service | 9/22/2010 |
IRON TRIANGLE LLC | $149,255 | Contract | : Project includes, but is not limited to reconstructing an existing parking lot and boat ramp, removing an existing vault toilet, installing a new vault toilet, constructing a simulated face concrete retaining wall, constructing a new AOA trail from the pa | Agriculture, Department of / Forest Service | 7/29/2010 |
ENGINEERING/REMEDIATION RESOURCES GROUP, INC. | $205,135 | Contract | : The scope of this contract is to complete the implementation of the time critical removal action being conducted by the Forest Service under its delegated CERCLA authorities, to remove lead contaminated mine tailings from the banks of Poorman Creek at the | Agriculture, Department of / Forest Service | 8/19/2010 |
ALFREDSON BROTHERS CONSTRUCTION COMPANY | $430,563 | Contract | : Replacement of metal culvert with new precast concrete box culvert. | Agriculture, Department of / Forest Service | 5/06/2010 |
CHAMPLAIN CONSTRUCTION COMPANY, INC. | $225,172 | Contract | : GMNF Road Resurface - North 3.0 miles of gravel resurfacing on fr 101 and fr55 in granville vermont | Agriculture, Department of / Forest Service | 9/14/2010 |
SPIESS CONSTRUCTION CO., INC. | $2,494,048 | Contract | : Lake Mary Bike Path Completion | Agriculture, Department of / Forest Service | 8/30/2010 |
KOOTENAI SAND & GRAVEL, INC. | $7,130 | Contract | : Aggregate and Delivery | Agriculture, Department of / Forest Service | 6/10/2010 |
JOI FOREST, INC | $30,660 | Contract | : Pre-Commercial Thinning | Agriculture, Department of / Forest Service | 8/12/2010 |
CURTIS A MADSON JR | $30,520 | Contract | : Timber Sale Prep | Agriculture, Department of / Forest Service | 5/28/2010 |
K.C. EQUIPMENT, INC. | $263,589 | Contract | : Summit District Recreation Site - Paving Trail Pavement Repair and Reconstruction | Agriculture, Department of / Forest Service | 9/07/2010 |
CONSOLIDATED LAND SERVICES INC | $12,900 | Contract | : Bearhead Project survey work for 5.75 miles of boundary line maintenance and maintenance of 20 corners on the Sylamore District in T16N, R11W, WFM-810-10-HF | Agriculture, Department of / Forest Service | 9/15/2010 |
ALBERTO LUNA CONSTRUCTION INC | $220,051 | Contract | : THIS PROJECT CONSISTS OF SITE IMPROVEMENTS AT MCGILL CAMPGROUND LOCATED ON MT. PINOS RANGER DISTRICT OF THE LOS PADRES NATIONAL FOREST. THE CONTRACT INCLUDES BUT IS NOT LIMITED TO: REMOVAL AND REPLACEMENT OF OLD FIRE RINGS, BARBECUES, PICNIC TABLES. SERVI | Agriculture, Department of / Forest Service | 7/07/2010 |
OLSON, JAY | $2,777 | Contract | : Weitas Window project. | Agriculture, Department of / Forest Service | 7/14/2010 |
DESCHUTES CONCRETE CONSTRUCTION | $278,625 | Contract | : Helicopter service. The helicopter was used to transport construction material to a remote wilderness location. | Agriculture, Department of / Forest Service | 5/26/2010 |
KOLA INC | $46,700 | Contract | : Recovery - Goose Lake Boat Ramp | Agriculture, Department of / Forest Service | 8/03/2010 |
TIDEWATER CONTRACTORS, INC. | $301,117 | Contract | : PAVING | Agriculture, Department of / Forest Service | 5/27/2010 |
RICK GARCIA CONSTRUCTION COMPANY | $878,040 | Contract | : Road Re-Surfacing | Agriculture, Department of / Forest Service | 8/17/2010 |
GROUP MACKENZIE ENGINEERING INCORPORATED | $135,722 | Contract | : Timberline Lodge Assessment | Agriculture, Department of / Forest Service | 3/12/2010 |
ROBERT OCHOA | $32,340 | Contract | : Pre-Commercial Thinning services in the Tonto National Forest. | Agriculture, Department of / Forest Service | 9/16/2010 |
CLEAR PACIFIC INC | $94,111 | Contract | : This award is for the ARRA Whitman Mechanical Fuels Task Order which is comprised of grapple piling and slashbusting. | Agriculture, Department of / Forest Service | 12/17/2009 |
DINK'S CONSTRUCTION, LLC | $57,150 | Contract | : Take out old culvert and replaced with new culvert and grade and replaced grass. | Agriculture, Department of / Forest Service | 10/21/2009 |
DARDAN ENTERPRISES INC | $129,020 | Contract | : Restore, refurbish, and update existing eastern historic timber framed picnic pavilion structure located at Shoshone Park. To include reinforcement of existing wood posts with steel posts hidden inside and installing new concrete footings and foundations | Agriculture, Department of / Forest Service | 8/09/2010 |
CONSERVATION CORPS, CALIFORNIA | $494,784 | Grant | Recovery Act of 2009: Wildland Fire Management: The project focus is to remove hazardous, fire prone vegetation and debris within the areas impacted by the timber flown down during the 2009/2010 winter. | Agriculture, Department of / Forest Service | 8/04/2010 |
ASPEN CONSTRUCTION COMPANY | $198,131 | Contract | : Construct 250 foot fish passage, remove and dispose of existing steel culver, concrete head wall and outlet control structure on the Pigeon River Impoundment in the Chippewa National Forest | Agriculture, Department of / Forest Service | 6/21/2010 |
DILLON FENCING & CONTRACTING, LLC | $24,310 | Contract | : Bridge rehabilitation on the San Juan NF - Remove, replace bridge timbers, paint bridge, install approach ramps | Agriculture, Department of / Forest Service | 3/15/2010 |
LILLY TREE FARM | $182,793 | Contract | : The purpose of this project is to reduce hazardous fuels at Midewin National Tallgrass Prairie. The goal is to reduce the amount of woody vegetation that fire cannot kill and to help control the spread of invasive woody vegetation such as Autumn Olive, Bu | Agriculture, Department of / Forest Service | 5/06/2010 |
MARSHFIELD FOREST SERVICE, INC | $124,624 | Contract | : This award is for the treatment of non-native invasivve spieces within Francis Marion National Forest. | Agriculture, Department of / Forest Service | 8/27/2010 |
GRANT EQUIPMENT | $178,711 | Contract | : Olreans Lower Parking Lot Paving | Agriculture, Department of / Forest Service | 2/01/2010 |
WHEELER LUMBER, L.L.C. | $7,076 | Contract | : ARRA Hunter Campground - Timber. ACQ Treated Timber. | Agriculture, Department of / Forest Service | 6/24/2010 |
BIG J CONSTRUCTION, INC. | $263,250 | Contract | : Lake Almanor Bike Trail Chipseal. Chipseal Biketrail at Lake Almanor, CA | Agriculture, Department of / Forest Service | 5/03/2010 |
INTERIOR WEST CONSULTING, LLC | $29,995 | Contract | : Contracted by USDA Forest Service to complete various cultural resource inventories on the Pagosa Ranger District, San Jan National Forest. | Agriculture, Department of / Forest Service | 7/09/2010 |
CMEC, INCORPORATED | $40,532 | Contract | : Replace historic cabin foundation and improve drainage. | Agriculture, Department of / Forest Service | 5/18/2010 |
ALDRIDGE BROTHERS, INC | $623,846 | Contract | : Bridge replacement and maintenance of Forest Service bridge on Shoal Creek road. | Agriculture, Department of / Forest Service | 8/30/2010 |
ECLIPSE ENGINEERING INC | $99,117 | Contract | : Fire Lookout Tower structural review and condition assessment. Structural analysis and as-built drawings of existing towers | Agriculture, Department of / Forest Service | 7/08/2010 |
A A A THUNDERDERBOLT FIRE SERVICE INC | $11,130 | Contract | : Emigrant Creek District, Project 17, Stand management, thinning and pullback of conifers in the Malhuer National Forest | Agriculture, Department of / Forest Service | 8/11/2010 |
MARK AGEE EXCAVATION | $81,450 | Contract | : RECOVERY Forest-Wide Traffic Control Devices - Sign Installation | Agriculture, Department of / Forest Service | 3/09/2010 |
HCI CONSTRUCTION COMPANY | $409,036 | Contract | : repair and restoration of walking, offroad vehical trails and restoration of wash-out along roadway | Agriculture, Department of / Forest Service | 9/17/2010 |
BATES CONSTRUCTION | $848,700 | Contract | : Furnish non-government supplied materials, labor, and equipment to rehabilitate and reconstruct 16 bridges in the Sequoia National Forest. | Agriculture, Department of / Forest Service | 8/06/2010 |
HARRINGTON CONSTRUCTION INC | $2,175 | Contract | : Additional work for the Houle Creek/Kreis Pond Rock Placement under OHV Trail Rehabilitation, Lolo National Forest | Agriculture, Department of / Forest Service | 8/30/2010 |
NORTHSTAR TECHNOLOGY CORP | $50,000 | Contract | : INSPECTION SERVICES | Agriculture, Department of / Forest Service | 9/16/2010 |
MILLER TIMBER SERVICES INC | $797,465 | Contract | : Tree thinning services - marking trees, harvesting and removing saw logs and biomass to mills | Agriculture, Department of / Forest Service | 8/12/2010 |
INLAND CONCTRUCTION INC | $154,870 | Contract | : Virginia Creeper Trail Restoration | Agriculture, Department of / Forest Service | 5/24/2010 |
APEX CONSTRUCTION SERVICE, LLC | $209,047 | Contract | : Rehabilitation of an existing steel truss bridge | Agriculture, Department of / Forest Service | 8/18/2010 |
B T O LOGGING INC | $413,132 | Contract | : BTO Logging is engaged in logging operations that thin the forest and reduce the potential for fires by reducing dead wood and potential fire hazard. | Agriculture, Department of / Forest Service | 6/18/2010 |
ROCKART SIGNS & MARKERS | $18,561 | Contract | : Panel Information Boards | Agriculture, Department of / Forest Service | 5/26/2010 |
HALL, STEWART A | $24,397 | Contract | : VISTOR FACILTY 99 26 | Agriculture, Department of / Forest Service | 7/28/2010 |
TROPICAL CONTRACTING, LLC | $985,057 | Contract | : work includes Supply all labor and materials to construct decelaration lanes along Colorado State HWY 9, and construction of approximately 1,000 LF of connector road as a part of relocating the intersection of Cow Creek South Campground | Agriculture, Department of / Forest Service | 9/24/2010 |
ALLEN, J. F. COMPANY (INC) | $318,724 | Contract | : Road and Trail Maintenance on Spruce Knob Lake in the Monongahela National Forest. | Agriculture, Department of / Forest Service | 5/14/2010 |
TRINITY VENTURES LLC | $335,864 | Contract | : Preparation, paving and striping of road and parking stalls; construction of sediment basins/ditches lined with class 1 riprap; boulder placement/removal; 6 layer of compacted aggregate surfacing on 6' wide foot paths to be constructed. Construction of 2 | Agriculture, Department of / Forest Service | 7/06/2010 |
CLARENCE MCREYOLDS | $20,116 | Contract | : Purchase and deliver 17 interpretation signs. Purchase or produce, haul, deliver, and stockpile 126 Cu yards of grading D1 gravel to trail site. | Agriculture, Department of / Forest Service | 6/21/2010 |
BATEMAN FOREST MANAGEMENT INCORPORATED | $26,190 | Contract | : Work consists of installation of Berm Barricades, installation of non-driveable waterbars, culvert removals, full slope pullback, seeding and seeding and mulching. Minor blowdown, slides, fill failures and rocks may beed to be moved to access work sites. | Agriculture, Department of / Forest Service | 4/07/2010 |
RNR CONSTRUCTION INC | $874,839 | Contract | : The purpose of the issuance and award of this contract was to: 1. Benefit the public safety of visitors and residents of the Eldorado Forest area, 2. Provide increased public convenience with better and easier access to area resources 3. Provide environme | Agriculture, Department of / Forest Service | 7/10/2010 |
WOODRING BROTHERS | $13,650 | Contract | : antley creek trailhead | Agriculture, Department of / Forest Service | 9/09/2009 |
A A A THUNDERDERBOLT FIRE SERVICE INC | $96,494 | Contract | : Prairie City Ranger District Thin and Treat - Project #1 | Agriculture, Department of / Forest Service | 2/05/2010 |
TIMBERLAND FORESTRY SERVICES, LLC | $20,088 | Contract | : old trailhead information signs'removal & disposal; and installation of replacement trailhead information sign frames & signboards which were supplied by the Forest. | Agriculture, Department of / Forest Service | 5/26/2010 |
E R C MANUFACTURING INC | $1,127,245 | Contract | : IITF SABANA DORMITORY AND CIM-1201-04F WOODSHOP, LUQUILLO, PR. This project consist of the construction of a dormitory for the staff engage in doing laboratory work in the area. The wood shop is been constructed for the purpose of providing a shop for the | Agriculture, Department of / Forest Service | 9/17/2010 |
J. R. CONKEY & ASSOCIATES, INC. | $256,682 | Contract | : CIM05-07F: Mono Lake visitor center heavy maintenance design and install photovoltaic system with smartmeter. | Agriculture, Department of / Forest Service | 7/26/2010 |
NORTHWEST DESIGN GROUP INC | $63,859 | Contract | : Construction Inspection Services, Hiawatha National Forest - Inspection of the replacement of the North Light Creek Trail Bridge and various East Rim Trail Culverts on Grand Island, Lake Superior. | Agriculture, Department of / Forest Service | 4/02/2010 |
EAC FENCING | $68,887 | Contract | : AG-82B1-S-10-0071/Ag-82B1-C-10-0073 MotorizedTrail Signing,Salmon-Challis National Forest. Trail signs matching GPS locations and mapping for General Public. | Agriculture, Department of / Forest Service | 12/30/2009 |
KOMADA, LLC | $2,396,000 | Contract | : Design/BuildBeckworth Fire Station at Nervino Airport. | Agriculture, Department of / Forest Service | 9/01/2010 |
THOMAS,ROBERT E | $269,626 | Contract | : Recreational Facility Maintenance on the Blue Ridge Ranger District of the Chattahoochee-Oconee National Forest. | Agriculture, Department of / Forest Service | 8/02/2010 |
COOK & SON CONSTRUCTION | $307,453 | Contract | : RECOVERY Fish Creek Loop | Agriculture, Department of / Forest Service | 8/05/2010 |
STONE RIDGE CONSTRUCTION, INC | $228,274 | Contract | : Work involves the removal of 2 existing culverts and the replacement with new Trideck beam bridges. Improvements consist of but are not limited to structural excavation, excavation and reshaping of the channel, placement of in-stream step pool structures | Agriculture, Department of / Forest Service | 3/10/2010 |
BENSON FARMS, INC. | $23,258 | Contract | : Recovery Excess Seed Purchase of Forest Service Source Identified Species Propagation of Native Seed | Agriculture, Department of / Forest Service | 7/27/2010 |
RESTORATION SOLUTIONS LLC | $285,061 | Contract | : Skid and Deck 2008 TSI Units - 683 acres of skidding and decking in the Cibola National Forest | Agriculture, Department of / Forest Service | 1/14/2010 |
BLAIR TREE FARM | $99,999 | Contract | : This contract was for the purchase and installation of fence at the Shawnee National Forest. | Agriculture, Department of / Forest Service | 8/31/2010 |
NATIONAL SOLAR TECHNOLOGIES INC | $8,814 | Contract | : Manufacture and Supply Solar Powered Lighting Systems | Agriculture, Department of / Forest Service | 9/09/2010 |
S&K ENVIRONMENTAL, LLC | $149,468 | Contract | : Teepee Creek Bridge Replacement-Flathead Nation Forest | Agriculture, Department of / Forest Service | 7/28/2010 |
ZEKE RANSOM EXCAVATING | $23,334 | Contract | : SPOT GRAVELLING OF BIRDSEYE TRAIL ON THE HOOSIER NATIONAL FOREST. | Agriculture, Department of / Forest Service | 8/09/2010 |
FRONTIER WEST, LLC | $224,410 | Contract | : Removal of the existing bridge and construct A new Bulb-tee beam bridge. Includes new riprap and approaches.New timber bridge railing. | Agriculture, Department of / Forest Service | 9/21/2010 |
MESCALERO APACHE TRIBE | $317,395 | Contract | : Tater Commercial Timber Sale | Agriculture, Department of / Forest Service | 4/06/2010 |
R. J. THOMAS MANUFACTURING COMPANY, INC. | $20,127 | Contract | : PRODUCE AND DELIVER ADA PICNIC TABLES, FIRE RINGS & ANCHOR SYSTEMS | Agriculture, Department of / Forest Service | 6/01/2010 |
TWO SHOES, INC. | $183,750 | Contract | : Clearing and Trail Features Construction, Apache National Forest | Agriculture, Department of / Forest Service | 8/12/2010 |
SAPPER WEST, INC. | $139,070 | Contract | : Paving of San Antonio ADA Trail | Agriculture, Department of / Forest Service | 8/26/2010 |
KAP CONSTRUCTION INC | $168,350 | Contract | : Restroom replacement and campsite improvements | Agriculture, Department of / Forest Service | 6/21/2010 |
A&E ARCHITECTS, P.C. | $23,028 | Contract | : To provide inspection and construction administration services on a Time & Material basis for the Lolo Pass Visitor's Center. | Agriculture, Department of / Forest Service | 8/20/2010 |
JIM TURIN AND SONS, INC. | $4,758 | Contract | : RECOVERY GRAVEL | Agriculture, Department of / Forest Service | 3/19/2010 |
RON SCHEIDING, INC. | $284,731 | Contract | : Hiawatha National Forest, Clear Lake Educational Center, Accessibility and Erosion Control Project. | Agriculture, Department of / Forest Service | 6/01/2010 |
NATIVE ENERGY & TECHNOLOGY, INC. | $119,800 | Contract | : TS::12 1102::TASRECOVERY - Green Mountain Reservoir Photovoltaic Systems Delivery: 10/30/2010 Ordering Greentow Trailer to the Forest Service. This equipment is a mobile solar panel to power equipment in remote locations in in the event of an emergency. | Agriculture, Department of / Forest Service | 9/14/2010 |
LIGHTHOUSE FOR THE BLIND, THE | $6,328 | Contract | : Provide tree marking paint to the Forest Service in support of their activities. This includes procuring raw material, packaging the paint and preparing for shipment. This activity takes only a few hours to complete. | Agriculture, Department of / Forest Service | 1/18/2010 |
KENTUCKY SURVEYS | $68,115 | Contract | : CADASTRAL SURVEY | Agriculture, Department of / Forest Service | 5/25/2010 |
KETCHAM FENCING INC | $82,317 | Contract | : SUPPLY AND INSTALL FENCE FOR DEER CONTROL | Agriculture, Department of / Forest Service | 5/18/2010 |
NELSON, ROB | $12,299 | Contract | : Non-Wilderness Trail Maintenance | Agriculture, Department of / Forest Service | 4/08/2008 |
PAYNE CONSTRUCTION | $17,300 | Contract | : Demo | Agriculture, Department of / Forest Service | 7/22/2010 |
BOISE CASCADE, L.L.C. | $359,298 | Contract | : The object of this project is to reduce fules in order to protect and at-risk community that includes homes, structures, and forest resources to provide for public and firefighter safety. Treatment will include reducing understory fuel laddering and incr | Agriculture, Department of / Forest Service | 9/10/2010 |
WOODRING BROTHERS | $10,500 | Contract | : install signs for flathead national forest | Agriculture, Department of / Forest Service | 6/04/2010 |
ACA PRODUCTS, INC. | $162,370 | Contract | : RECOVERY RIOGRANDE NATIONAL FOREST COMMERCIAL GRAVEL SUPPLY | Agriculture, Department of / Forest Service | 3/24/2010 |
SUMMITT FORESTS INC. | $172,548 | Contract | : 2010 RECOVERY FUNDS-STIMULUS IAS LWT39E-SELECTIVE SLASHING/THINNING AND YARD SLASH /MECHANICAL PILING ON THE WASHAKIE R.D. OF THE SHOSHONE N.F. | Agriculture, Department of / Forest Service | 8/27/2010 |
TORQHOIST, INC. | $3,321 | Contract | : RIGGING EQUIPMENT | Agriculture, Department of / Forest Service | 6/29/2010 |
NORTH IDAHO CRUSHING, INC | $283,823 | Contract | : Vassar Aggregate Resurfacing Project | Agriculture, Department of / Forest Service | 11/03/2009 |
HILLS MATERIALS COMPANY | $205,405 | Contract | : REVA GAP CAMPGROUND ROAD AND IMPROVEMENTS | Agriculture, Department of / Forest Service | 8/30/2010 |
SAN DIEGO PERSONNEL & EMPLOYMENT AGENCY, INC. | $1,189,986 | Contract | : Provide temporary staffing to Shasta Trinity National Forest seasonally for Wildlife Fire Management | Agriculture, Department of / Forest Service | 7/15/2010 |
A & K CONSTRUCTION INC | $600,379 | Contract | : Install culverts on a road in the Clearwater National Forest. This includes some logging, placing riprap and gravel.Install gabion basket along roadsides near the insatlled culverts. | Agriculture, Department of / Forest Service | 8/13/2010 |
JOHNSON, BOB CONSTRUCTION | $1,012,121 | Contract | : Road construction | Agriculture, Department of / Forest Service | 7/26/2010 |
V MOUNTAIN CONSTRUCTION, INC. | $133,400 | Contract | : RECOVERY CIM-0301-16T Rim Vista Trail - Asphalt Paving and construction. construct 6200' of asphalt trail for extension of trail, sub-base,placement of crushed rock, and paving | Agriculture, Department of / Forest Service | 3/15/2010 |
WESSLEN CONSTRUCTION, INC. | $132,461 | Contract | : Eagle Point Lookout Repairs | Agriculture, Department of / Forest Service | 7/14/2010 |
NELSON CONSTRUCTION CO OF LA POINTE INCORPORATED | $39,935 | Contract | : Provide dredging for the Ottawa National Forest at Black River Harbor in Gogebic County, Michigan. | Agriculture, Department of / Forest Service | 3/04/2010 |
TFAB GROUND SYSTEMS, LLC | $149,621 | Contract | : CLIN 1 - Mendenhall Visitor Center Repairs - Theater air conditioner design, clean mold and mildew, replace main indoor stairs lights, repair door hinges, repair leak sensor. Replaced carpet CLIN 2 - Replace Restroom Fixtures - | Agriculture, Department of / Forest Service | 9/17/2010 |
ENTERPRISE RENT-A-CAR GOVERNMENT PROCUREMENT, INC | $28,000 | Contract | : PASSENGER MOTOR VEHICLES | Agriculture, Department of / Forest Service | 5/28/2010 |
R. & J. JOY, INC. | $422,394 | Contract | : Replacing existing water line with new desing build at Lake Davis Grizzly and Grasshoper camp grounds, no significant deliverable | Agriculture, Department of / Forest Service | 8/17/2010 |
UNIVERSITY OF OREGON | $7,548 | Grant | Recovery Act of 2009: Wildland Fire Management: This Joint Venture Agreement (JVA) is supported by American Reinvestment and Recovery Act (ARRA) funds. The goal of this JVA is to create or retain jobs in Lane and Multhomah Counties by hiring University of Oregon (UO) students and faculty to perform m wo... Show more | Agriculture, Department of / Forest Service | 8/23/2010 |
SHAVER, PAULA JANE | $8,457 | Contract | : Cattleguard | Agriculture, Department of / Forest Service | 7/30/2010 |
KESLER CONSTRUCTION, INC. | $137,635 | Contract | : FISHER CR ROAD REPAIR - replacing culverts and resurfacing road. | Agriculture, Department of / Forest Service | 9/21/2010 |
ASM AFFILIATES INC | $546,699 | Contract | : This Heritage Survey facilitates the implementation of the Healthy Forest Initiative. The results of the survey will assist land managers in managing the resource within the boundaries of the Great Basin Province. Antelope Vegetation Management Survey | Agriculture, Department of / Forest Service | 7/23/2010 |
SIMJAN, INC. | $243,119 | Contract | : This award is for the building and replacement of docks on the Smith, Bruah, and Sinclair Lakes. | Agriculture, Department of / Forest Service | 3/29/2010 |
EAGLE DEER RESERVE LIMITED | $123,800 | Contract | : Restore , roof and paint | Agriculture, Department of / Forest Service | 3/30/2010 |
KIDSTUFF PLAYSYSTEMS, INC. | $25,443 | Contract | : supply and deliver playground equipment | Agriculture, Department of / Forest Service | 9/24/2010 |
NORTHWIND ENGINEERING, LLC | $99,378 | Contract | : Wayne National Forest Ironton District Non Native Invasive Species reduction project (clearing forest fire fuels) | Agriculture, Department of / Forest Service | 7/29/2010 |
NATIONAL WILD TURKEY FEDERATION, INC., THE | $156,665 | Grant | Recovery Act of 2009: Wildland Fire Management: The project is located on the Baldwin/White Cloud Ranger District of the Huron-Manistee National Forest. Work areas include the Savanna/Barrens Restoration and Karner Blue Butterfly (KBB) Habitat Restoration analysis areas, four KBB metapopulation areasas a... Show more | Agriculture, Department of / Forest Service | 8/17/2010 |
ELSHOLZ CONTRACTING INC. | $87,660 | Contract | : This Project was to do maintenance on 22 dams in the Huron- Manistee National Forest located in Michigan. Work included mowing, brush and tree removal, topsoil areas needed and turf re-establishment, placement of riprap, stop log replacement, Repair and r | Agriculture, Department of / Forest Service | 3/15/2010 |
WOOD PRODUCT SIGNS/RECYCLE PLUS, INC. | $37,571 | Contract | : ROUTED US FOREST SERVICE SIGNS FOR CAMPGROUNDS, RECREATION AREAS | Agriculture, Department of / Forest Service | 6/03/2010 |
MOUNT SAINT HELENS REFORESTATION INC | $27,777 | Contract | : Reforestation | Agriculture, Department of / Forest Service | 10/28/2009 |
THOMAS J. MOYLE, JR., INCORPORATED | $227,106 | Contract | : The purpose of this contract is to initially close nine old abandoned mine openings, remove old wooden posts and fences at eight locations and replace fences and posts at two locations thru the Ottawa National Forest. As more funding became available, tw | Agriculture, Department of / Forest Service | 6/24/2010 |
CHACON BROTHERS | $5,244 | Contract | : Contractor performed 77 acres of thinning, logging, spreading of slash which included ponderosa pine with some white firs and douglas fir to silvicultural prescription. The number of cut trees during the treatment is estimated to range from 200 tp 1000 t | Agriculture, Department of / Forest Service | 8/12/2010 |
BLUE DIAMOND BUILDERS | $25,640 | Contract | : Demolish and remove to an approved landfill, a 600 SF guard shack located at the Val Verde campgrounds in the Rio Grande Ntl Frst, 16 miles south of Monte Vista, CO | Agriculture, Department of / Forest Service | 7/06/2010 |
UNIVERSITY OF OREGON | $27,874 | Grant | Recovery Act of 2009: Wildland Fire Management: This Joint Venture Agreement (JVA) is supported by American Reinvestment and Recovery Act (ARRA) funds. The goal of this JVA is to create or retain jobs in Lane and Multhomah Counties by hiring University of Oregon (UO) students and faculty to perform m wo... Show more | Agriculture, Department of / Forest Service | 8/23/2010 |
RMC CONSULTANTS, INC. | $230,753 | Contract | : Contractor to provide all labor, material, transportation, and equipment necessary to perform remediation services on Santa Rita abandoned mine lands in accordance with the statement of work and all attachments. | Agriculture, Department of / Forest Service | 7/13/2010 |
PACIFIC COAST CONTRACTING, INC. | $58,432 | Contract | : Thinning of trees in the woods, hand piling the slash piles and then burn the piles to reduce the fuel load in the Woods. | Agriculture, Department of / Forest Service | 3/15/2010 |
HOULIHAN, INC. | $58,353 | Contract | : REPLACE 6,250 LF OF SPLIT RAIL FENCE. PLACEMENT AND ANCHORING OF GLASS FIBER REINFORCED CONCRETE BOULDERS, HOLLOW LOGS, HALF LOGS, HALF LOG BENCHES, HALF LOG BALANCE BEAM AND CLIMBING BOULDER. | Agriculture, Department of / Forest Service | 3/26/2010 |
WEXCO INTERNATIONAL CORPORATION | $1,954 | Contract | : Award is for a portable water quality test meter. | Agriculture, Department of / Forest Service | 4/16/2010 |
TRI-COUNTY BUILDERS CO INC | $288,942 | Contract | : Tipsaw/Indian Road Reconstruction, re-asphalt roads | Agriculture, Department of / Forest Service | 9/21/2010 |
STERTZ, MICHAEL | $29,999 | Contract | : Replace propane heater/exhaust vent; replace exteriod siding/trim, paint exterior windows/walls; install wooden framed screen door; repaint interior; r.eplace window screens, refurbish shutters; replace door cover; relocate propane tank; reputty; jack up | Agriculture, Department of / Forest Service | 5/17/2009 |
MALLETT EXCAVATING INC | $58,703 | Contract | : Backhoe Services contract in the Rio Grande National Forest | Agriculture, Department of / Forest Service | 3/23/2010 |
WEBER CONSTRUCTION, INC. | $102,633 | Contract | : Recovery Evergreen Road Repair and Maintenance project | Agriculture, Department of / Forest Service | 3/16/2010 |
FIRESTORM WILDLAND FIRE SUPPRESSION INC | $150,000 | Contract | : Hazardous fuel reduction mechanical chipping along Forest Service roads on the Shasta Trinity National Forest. Firestorm crews drive a truck towing a chipper along Forest Service roads and chip brush that has previously been cut by the Forest Service. T | Agriculture, Department of / Forest Service | 6/29/2010 |
FERGUSON MANAGEMENT COMPANY | $83,120 | Contract | : Recovery Fuel Reduction Crew Task Order - Wallowa Whitman Nat'l Forest - Wallowa Fire zone. | Agriculture, Department of / Forest Service | 12/14/2009 |
TOM STEVENS CONSTRUCTION LLC | $32,280 | Contract | : This is a contract for cutting back the brush that is over growing existing roads that are part of a system of groomed snowmobile trails in winter. Most of this is a pay per mile, but has a portion that is an hourly rate due to brush density. | Agriculture, Department of / Forest Service | 7/30/2010 |
ANDERSON ELECTRIC | $3,595 | Contract | : INSTALL NEW BEDROOM LIGHTING IN BEDROOMS AT DORMS CANYON RANGER STATION. INSTALL GROUND FAULT CIRCUITS IN FIRE CACHE BUILDING-CORRECT CODE VIOLATIONS IN WIRING FOR LIGHT SWITCHING FIRE CACHE. | Agriculture, Department of / Forest Service | 9/13/2010 |
QUERCUS CONSULTANTS, INC. | $123,842 | Contract | : This project was a stand inventory, particularly of white pine species, in the Golden Trout Wilderness of the Western Divide Ranger District of the Sequoia National Forest empahsizing the presence and abundance of diseases, particularly white pine blister | Agriculture, Department of / Forest Service | 7/14/2010 |
EASTERN OREGON ENVIRONMENTAL RECOVERY LLC | $22,307 | Contract | : Prepare site and install new toilets. | Agriculture, Department of / Forest Service | 5/28/2010 |
STREET LEGAL INDUSTRIES, INC | $193,895 | Contract | : Uwharrie National Forest Dickey Belle Trail Bridge Construction. A 60ft steel frame concrete abutement creek crossing to support recreational and emergency access to the forest. | Agriculture, Department of / Forest Service | 6/01/2010 |
PINE CREEK PACK STATION | $23,336 | Contract | : Debris removal from Rex Montis mine | Agriculture, Department of / Forest Service | 7/26/2010 |
REDMOND FENCING | $5,000 | Contract | : fencing materials | Agriculture, Department of / Forest Service | 9/23/2010 |
SWINERTON BUILDERS | $15,000 | Contract | : INACCORDANCE WITH SECTION M, A STIPEND WILL BE PROVIDED TO DEFRAY THE COST OF PARTICIPATION IN PHASE II. EACH PHASE I OFFEROR THAT IS SELECTED FOR PHASE II WILL BE PFFERED A STIPEND OF $15,000 IF NOT SELECTED FOR CONTRACT AWARD. | Agriculture, Department of / Forest Service | 9/15/2010 |
STROUP, ROBERT | $10,122 | Contract | : Flat Poly bags | Agriculture, Department of / Forest Service | 11/03/2009 |
BUSBY CONSTRUCTION CO., INC. | $358,000 | Contract | : Beaver Pond Dam Design-Build, Phase II;Design and Reconstruction of earthen dam located in White Mountain National Forest, Woodstock, NH | Agriculture, Department of / Forest Service | 3/01/2010 |
CLEARWAY SERVICES LLC | $156,043 | Contract | : Wilderness trail restoration including clearing of downed trees and brushy vegetation, restoring trail tread to new like condition, adding additional drainage to prevent further damage. | Agriculture, Department of / Forest Service | 6/09/2010 |
PACIFIC COAST CONTRACTING, INC. | $130,140 | Contract | : Burning of slash piles in the woods to reduce the fuel load in the woods. | Agriculture, Department of / Forest Service | 3/03/2010 |
THOMPSON CONTRACTING, INC. | $262,373 | Contract | : Kootenai Culverts installation of multi-plate culverts | Agriculture, Department of / Forest Service | 7/01/2010 |
JOI FOREST, INC | $30,660 | Contract | : Thinning and Handpiling | Agriculture, Department of / Forest Service | 8/12/2010 |
MOBILE MINI, INC. | $9,845 | Contract | : Lease Storage and Office Trailer | Agriculture, Department of / Forest Service | 3/05/2010 |
DOLORES, COUNTY OF | $35,650 | Grant | Recovery Act of 2009: Capital Improvement and Maintenance: Dolores County will place Magnesium Lignin on gravel surface Dolores/Norwood Road. | Agriculture, Department of / Forest Service | 2/18/2011 |
FIBRECON PACIFIC INTL, LLC | $59,132 | Contract | : Ramona Bridge | Agriculture, Department of / Forest Service | 5/04/2010 |
HAYS, DONALD R JR | $441,581 | Contract | : Build 2008 meters of trail and associated boardwalks | Agriculture, Department of / Forest Service | 8/26/2010 |
GROSSHENING INC | $300,300 | Contract | : INFRASTRUCTURE DEMOLITION AND REMOVAL OF CONCRETE BUILDING AT MIDEWIN NATIONAL TALLGRASS, IN WILMINGTON IL. | Agriculture, Department of / Forest Service | 5/28/2010 |
BONNEVILLE ASPHALT & REPR LLC | $609,899 | Contract | : This award is to do asphalt patching and sealing cracks in the Aquarius & Road 247 in Clearwater National Forest. | Agriculture, Department of / Forest Service | 8/13/2010 |
ENVIRO TRAC, LLC | $156,265 | Contract | : Understory mechanical fuels reduction; pre-commercial thinning; white pine site preparation. The overall purpose of the work being performed is to reduce wildfire fuels and to improve the health of the forest to promote growth of desired trees in the for | Agriculture, Department of / Forest Service | 6/01/2010 |
ALPHA SERVICES, LLC | $23,040 | Contract | : National Resource Managment & Conservation | Agriculture, Department of / Forest Service | 8/25/2010 |
J P PRINZ CO. LLC | $400,186 | Contract | : USFS-Malheur National Forest-Recreational Rental Upgrades including but not limited to roofing,painting,flooring, doors, windows, concrete, cabinets, decks,plumbing and electrical changes and/or upgrades | Agriculture, Department of / Forest Service | 7/12/2010 |
BRYSON HOPKINS | $269,145 | Contract | : This contract is for Forest Service Road Maintenance in Boise, Idaho. | Agriculture, Department of / Forest Service | 11/23/2009 |
ERPS, CLAUDE CONSTRUCTION INC | $100,535 | Contract | : Restoration of Cascades Trail in Pembroke, VA. | Agriculture, Department of / Forest Service | 6/01/2010 |
COASTAL CAROLINA THERAPY,LLC | $45,173 | Contract | : Restore Two Rifle Ranges | Agriculture, Department of / Forest Service | 5/11/2010 |
ORICA USA INC. | $32,500 | Contract | : EXPLOSIVE PRODUCT SALES IN North Carolina | Agriculture, Department of / Forest Service | 9/10/2010 |
M & M SERVICES, LLC | $65,369 | Contract | : VARNEY CREEK CULVERT REPLACEMENT | Agriculture, Department of / Forest Service | 5/28/2010 |
TRULOVE DIRT WORKS, L.L.C. | $137,250 | Contract | : RECOVERY-EQUIPMENT RENTAL FOR HAZARDOUS FUELS REDUCTION, BIG PINEY AND SYLAMORE RANGER DISTRICTS, OZARK ST. FRANCIS NATIONAL FOREST | Agriculture, Department of / Forest Service | 6/01/2010 |
CUTTING EDGE CONCRETE SERVICES, INC | $1,798,739 | Contract | : Water system improvements replacing and/or repairing water lines, valves, well heads, and water tanks throughout San Bernardino and Riverside County. | Agriculture, Department of / Forest Service | 7/28/2010 |
K W EMERSON INC | $189,909 | Contract | : THIS PROJECT INVOLVES PERFORMING ROAD MAINTENANCE AT EIGHT SEPARATE LOCATIONS WITHIN THE STANISLAUS NATIONAL FOREST. THE WORK INCLUDES GRADING AND PLACING ROCK TO REPAIR AND RESTORE EXISTING ROADBEDS, RESTORE DRAINAGE FEATURES AND PLACING GEO-TEXTILE FABR | Agriculture, Department of / Forest Service | 7/09/2010 |
AIKEN-FORD LUMBER CO. | $4,612 | Contract | : 5510 LUMBER BASIC TREATED TO REPAIR BOARDWALK | Agriculture, Department of / Forest Service | 7/28/2010 |
SUG ROGERS CONSTRUCTION, LLC | $6,000 | Contract | : Supply: Aggregate - stockpile material for use on Nutrioso WUI2 | Agriculture, Department of / Forest Service | 8/24/2010 |
MICHAEL HOBBS | $393,680 | Contract | : Installation of Flow Meters ansd Chlorinators at various work stations and camp grounds to monitor water use and provide chlorination of domestic water | Agriculture, Department of / Forest Service | 9/02/2010 |
CUTTING EDGE FORESTRY, INC. | $164,710 | Contract | : CANYON FUELS REDUCTION PROJECT 2; BLUE MOUNTAIN RANGER DISTRICT-PRECOMMERCIAL THINNING, HAND PILING SLASH, AND BURNING OF SLASH PILES ON THE MALHUER N.F. | Agriculture, Department of / Forest Service | 5/07/2010 |
PROFESSIONAL HEATING & COOLING INC | $420,750 | Contract | : Installation of Energy Efficient heating, ventialtion, and air conditioning systems in 28 locations for Malhuer National Forest. All labor, materials, supplies, and equiptment required to perform this award is included. | Agriculture, Department of / Forest Service | 7/13/2010 |
WES COLE LAND SURVEYING PA | $19,095 | Contract | : 2.52 Miles of Boundary Line Surveying for the US Forest Service in North Carolina. Verify and perpetuate corners, prepare corner cards, surveyor's report, and plat of survey. | Agriculture, Department of / Forest Service | 8/16/2010 |
TFAB GROUND SYSTEMS, LLC | $579,457 | Contract | : Discovery Center Biomass Conversion- 50 Main Street (downtown ) Ketchikan, AK. This project is to provide a wood fired boiler, wood storage, all appurtenances and connections for use as primary heat source for entire Discovery Center building. | Agriculture, Department of / Forest Service | 9/14/2010 |
A & S PAVING, INC. | $484,567 | Contract | : NFSR 150 SURFACING AGGREGATE, GILA NATIONAL FOREST. WE CRUSHED, HAULED, SPREAD AND COMPACTED BASE COURSE ON APPROXIMATELY 12 MILES OF FOREST ROAD 150 MILES NORTH OF SILVER CITY, N.M. | Agriculture, Department of / Forest Service | 8/09/2010 |
JASON STOKES CONSTRUCTION | $62,621 | Contract | : Construction of two trail bridges on the Cascade Trail in the Plumas National Forest. | Agriculture, Department of / Forest Service | 6/07/2010 |
AM EXCAVATING, LLC | $383,520 | Contract | : SOUTHZONE MAINTENANCE- REPAIR CRACKS OR CHUCKHOLES IN ASPHALT- REPLACE DAMAGED CULVERTS | Agriculture, Department of / Forest Service | 7/09/2010 |
TRAIL DYNAMICS LLC | $28,500 | Contract | : Maintenance of 5.1 miles of mountain biking, equestrian, and hiking trails to bring them up to current USDA FS trail standards.Modification includes a Phase I archaeological survey including subsurface testing to determine presence or absence of NRHP elig | Agriculture, Department of / Forest Service | 6/24/2010 |
SEXTON'S EXCAVATING | $24,980 | Contract | : EMERGENCY SHOULDERING ON TOWNSHIP ROAD AT WAYNE NATIONAL FOREST ***THIS PROJECT WAS COMPLETED IN SEPTEMBER 2010 | Agriculture, Department of / Forest Service | 7/09/2010 |
CENTURION GROUP, INC., THE | $83,631 | Contract | : Swartz Cabin Renovation and Roberts Cabin new roof | Agriculture, Department of / Forest Service | 8/26/2010 |
BOXLEY AGGREGATES OF WEST VIRGINIA, L.L.C. | $202,999 | Contract | : PROVIDE ALL LABOR, MATERIALS AND SUPERVISION FOR IDIQ- SOUTH ZONE AGGREGATE IN THE MONONGAHELA NATIONAL FOREST IN WV | Agriculture, Department of / Forest Service | 5/20/2010 |
ROCKART SIGNS & MARKERS | $11,834 | Contract | : Winter Trail Signs | Agriculture, Department of / Forest Service | 6/10/2010 |
BC CONCRETE, INC. | $6,653 | Contract | : Build and deliver a vault and floor slab for a vault toilet. | Agriculture, Department of / Forest Service | 8/02/2010 |
BBH CONSULTING, INC. | $169,845 | Contract | : North Kaibab Cabin Renovations - maintenance, repair or alteration of real property | Agriculture, Department of / Forest Service | 8/06/2010 |
DESERT MOUNTAIN, INC. | $10,439 | Contract | : Dust Control | Agriculture, Department of / Forest Service | 12/15/2009 |
JONES TOWNSHIP | $308,342 | Grant | Recovery Act of 2009: Capital Improvement and Maintenance: Reconstruction and resurfacing of 6.9 miles of Jones Township Road T359-Seven Mile Road and 0.1 miles of T435, Clarion Street. | Agriculture, Department of / Forest Service | 8/31/2010 |
DOT CONSTRUCTION, INC. | $149,074 | Contract | : Contract was to demolish the existing bathroom building and construct a new, larger bathroom facility in the Croatan National Forest, provide sidewalk from existing parking to new restroom building, restripe handicap parking spaces. | Agriculture, Department of / Forest Service | 4/26/2010 |
PRINEVILLE SAWMILL COMPANY, INC. | $111,010 | Contract | : Upper Grande Ronde Tree and Boulder Haul Project - watershed restoration on Upper Grande Ronde River. This contract requires removing, hauling, unloading and placement of logs, boulders, and cut trees. Movement of over 225 logs/trees and 425 boulders ar | Agriculture, Department of / Forest Service | 4/06/2010 |
WARM SPRINGS GEO VISIONS | $25,670 | Contract | : Conduct recording of 6 new sites and 28 new isolates on the Jane site and record 10 new sites on Soda Bear. Provide session reports, field inventory notes, complete site and isolate records prepare final report for MNF and State Historic Preservation Off | Agriculture, Department of / Forest Service | 7/25/2010 |
DOMINGUEZ ARCHEOLOGICAL RESEARCH GROUP INC. | $138,826 | Grant | Recovery Act of 2009: Capital Improvement and Maintenance: Dominguez Archaeological Research Group will partner with the San Juan National Forest to rehabilitate the historic Glade Guard Station on the Dolores Ranger District. This project will create approximately nine jobs in the historic buildingng restoration ... Show more | Agriculture, Department of / Forest Service | 9/09/2010 |
BRINK BROTHERS INC. | $19,038 | Contract | : Mulching for butterfly habitat | Agriculture, Department of / Forest Service | 2/22/2010 |
ROEN, PAUL | $167,257 | Contract | : It is intended to enhance Aspen areas by removing the majority of encroaching conifers. There is approximately 1593.8 CCF of combined saw timber and non-saw timber. | Agriculture, Department of / Forest Service | 9/17/2010 |
M R PRIEST, INC | $75,608 | Contract | : WOOD AND ALUMINUM SIGNS | Agriculture, Department of / Forest Service | 7/15/2010 |
NORTHSTAR TECHNOLOGY CORP | $60,900 | Contract | : ARRA LPNF INSPRCTION SERVICES | Agriculture, Department of / Forest Service | 6/25/2010 |
COMSTOCK SEED | $8,202 | Contract | : We supplied seed for a forest fire restoration project. | Agriculture, Department of / Forest Service | 4/09/2010 |
SAYLES, ROGER EXCAVATING INC | $13,774 | Contract | : clean ditches | Agriculture, Department of / Forest Service | 12/07/2009 |
PUERTO RICO CONSERVATION TRUST FUND | $40,990 | Contract | : Produce 10,000 seedlings of trees and/or shrubs from wildings or seeds for The Native Material Project on El Yunque National Forest. | Agriculture, Department of / Forest Service | 3/29/2010 |
BRADFORD CONSULTING ENGINEERS, INC. | $11,500 | Contract | : PE Reviews for McKenzie River Offices. | Agriculture, Department of / Forest Service | 5/07/2010 |
LA PLATA COUNTY | $192,123 | Grant | Recovery Act of 2009: Wildland Fire Management: Recovery Act Participating Agreement between La Plata County and the U.S. Forest Service, San Juan National Forest for inventory and treatment of noxious weeds. | Agriculture, Department of / Forest Service | 5/28/2010 |
ESPINDOLA, JOSE M | $63,556 | Contract | : This project is fully funded by and issued under the ARRA and all requirements of the Act apply. This solicitation has been issued as a Total Small Business Set-Aside. The NAICS is 115310, Support Activities of Forestry, Fuels Management Services. The pur | Agriculture, Department of / Forest Service | 8/06/2010 |
TANNER LOGGING, INC | $183,450 | Contract | : Stewardship Project: Removal of designated small commercial trees from forest stand and thin pre-commercial trees by description; biomass | Agriculture, Department of / Forest Service | 2/08/2010 |
BURKEL CONSTRUCTION INC | $112,700 | Contract | : UNITED STATES DEPARTMENT OF AGRICULTURE FOREST SERVICE. MOMMOTH SPRINGS, GOLDEN EDNA, JOHNSON SINK, ROADRUNNER MINING CLAIMS. WORK CONSIST OF REMOVAL OF ABANDONED EQUIPMENT, ROAD OBLITERATION, PORTAL CLOSURES AND NOXIOUS WEED ERADICATION. | Agriculture, Department of / Forest Service | 8/12/2010 |
HEART OF OREGON CORPS, INC. | $120,335 | Contract | : ARRA-Summer Youth Employment Program/Fuels Reduction, as project under Reducing Threat of Wildfires in Central and Southwest Oregon. To provide youth and young adults, ages 16-18 with meaningful work experience designed to foster the growth of skills tha | Agriculture, Department of / Forest Service | 6/16/2009 |
S & S GENERAL CONTRACTORS & EQUIPMENT RENTAL, INC. | $1,140,904 | Contract | : Perform maintenance grading work on 107 miles of National Forest roads. Construct 10 bridges. | Agriculture, Department of / Forest Service | 3/24/2010 |
JWM ENGINEERING INC | $240,291 | Contract | : BOUNDARY SURVEYING, CORNER MONUMENTATION, BOUNDARY LINE AND CORNER MONUMENTATION, BOUNDARY LINE AND CORNER MAINTENANCE, ROUTE LOCATION AND MONUMENTATION, SITE AND OTHER MISCELLANEOUS WORK. | Agriculture, Department of / Forest Service | 6/10/2010 |
PW CONSTRUCTION, INC. | $14,301,493 | Contract | : Design and construct new two story 22,000 sf Angeles National Forest Supervisor's Office Building and Courtyard area, including new parking lot, emergency generator and radio equip building. Relocate existing telecommunications and radio equipment. Demoli | Agriculture, Department of / Forest Service | 8/03/2010 |
PEACEPIPE CONSTRUCTION FABRICATION INC | $461,712 | Contract | : Kelly Dahl Campground Toilet Replacement - Boulder/Gilpin Counties, Colorado - The toilet construction would include, but not limited to, quality control, clearing and grubbing, removal and disposal of toilet buildings, excavation, bedding, backfilling, & | Agriculture, Department of / Forest Service | 9/23/2010 |
A&E ARCHITECTS, P.C. | $125,000 | Contract | : To provide inspection and construction administration services on a Time and Material basis for the Camp Crook project in SD. | Agriculture, Department of / Forest Service | 3/22/2010 |
RAMIREZ & ZENO, INC. | $44,857 | Contract | : IITF COMPLEX PHYSICAL IMPROVEMENTS; I | Agriculture, Department of / Forest Service | 9/14/2010 |
MARK SWANSON LOGGING | $665,578 | Contract | : Biomass Removal: The project is removal of forest trees killed by forest fires. The benefit is the utilization of valuable forest products and forest management. | Agriculture, Department of / Forest Service | 7/26/2010 |
WILLIAM E CARLES | $28,662 | Contract | : trail construction and reconstruction | Agriculture, Department of / Forest Service | 8/02/2010 |
WENDT CONSTRUCTION CO, INC | $34,982 | Contract | : ROAD BRUSHING | Agriculture, Department of / Forest Service | 9/23/2010 |
S G ENTERPRISES INC | $112,378 | Contract | : tHINNING | Agriculture, Department of / Forest Service | 6/14/2010 |
CACI INC FEDERAL | $3,579,785 | Contract | : Acquisition Support Services to consolidate the on-going support of 3 US Forest Service Economic Recovery Operations Centers (EROCs). This is the final report. As of 31 Mar 2012 there is no longer anyone working on this contract. The personnel in Vallej | Agriculture, Department of / Forest Service | 9/24/2010 |
DE ARTEAGA, INC. | $261,243 | Contract | : Waupee Creek Crossing. Culvert Removal and bridge installation - To replace three existing 5 round culverts with a precast concrete span arch bridge. | Agriculture, Department of / Forest Service | 4/02/2010 |
LARRANAGA TRUCKING INC. | $110,467 | Contract | : Blading & brushing for the maintenance of roads on the Modoc Ntl Forest. Blading area includes turnouts, widened roads & cattle guards. Maintain existing cross slope, crown, dips, lead off ditches & drainage structures upon completion of blading. Brush | Agriculture, Department of / Forest Service | 6/10/2010 |
HYDRA ENGINEERING, LLC | $214,221 | Contract | : Apalachicola Bridge Maintenance: Guardrail repair, graveling approach roads, wingwall repair, deck repair, erosion control measures | Agriculture, Department of / Forest Service | 6/30/2010 |
CLARENCE MCREYOLDS | $558,676 | Contract | : Construct trail for use by hikers and pedestrians. Centerline staking, erosion and pollution control, clearing and grubbing, excavation, construction and installation of drainage structures, turnpike construction, construct log retaining walls, double pla | Agriculture, Department of / Forest Service | 7/14/2010 |
M & S ELECTRIC, INC. | $8,783 | Contract | : LIGHTING RETROFIT FOR ENERGY SAVINGS | Agriculture, Department of / Forest Service | 6/01/2010 |
RAMOS REFORESTATION, INC. | $259,170 | Contract | : TAS RECOVERY ARRA DES NF, JET FUELS HAND THINNING. | Agriculture, Department of / Forest Service | 7/13/2010 |
K W EMERSON INC | $128,633 | Contract | : THE PROJECT IS RECONSTRUCTION AND MAINTENANCE OF A FOREST ROAD IN THE MIWUK CA RANGER DISTRICT. THE WORK INCLUDES SLOPE REPAIR, ROADWAY EXCAVATION, CULVERT REPAIR AND REPLACEMENT, GRADING AND PLACING ROCK WILL ALSO BE PERFORMED. | Agriculture, Department of / Forest Service | 9/03/2010 |
DOUBLE TREE FOREST MANAGEMENT, LLC | $1,500 | Contract | : Site Visit | Agriculture, Department of / Forest Service | 9/29/2010 |
SOUTHERN RESOURCE MANAGEMENT, L.L.C. | $137,200 | Contract | : Equipment Rental for Hazardous Fuel Reduction, Ozark-St. Francis National Forest, Russellville, AR | Agriculture, Department of / Forest Service | 5/27/2010 |
ALPINE EXCAVATION AND CONSTRUCTION COMPA | $51,060 | Contract | : NFSR 26 Rd. culvert,surfacing & soil Stabilzation | Agriculture, Department of / Forest Service | 11/18/2009 |
RIO CONTRACTING, L.L.C. | $193,367 | Contract | : Removal/Restoration of Existing Wood Windows and installation of wooden storm windows on two offices, one shed, one garage, and one warehouse. It also consists of the repair and limited replacement of all exterior woodwork on these five buildings. This pr | Agriculture, Department of / Forest Service | 8/30/2010 |
JARVIS ROADS LLC | $39,590 | Contract | : Recovery-Road 4270 Aggregate Surfacing, Deschutes National Forest | Agriculture, Department of / Forest Service | 5/27/2010 |
LES SCHLEGEL ENTERPRISES, INC. | $148,544 | Contract | : Culvert replacements on Flathead National Forest | Agriculture, Department of / Forest Service | 5/27/2010 |
WESTERN CAROLINA SURVEYORS P A INC | $21,563 | Contract | : National Forest in N.C. - Project:Cadastral Land Surveying - Old Fort II Area | Agriculture, Department of / Forest Service | 8/13/2010 |
ZEKE RANSOM EXCAVATING | $8,975 | Contract | : INDIAN DAM ACCESS ROAD MAINTENACE. PRODUCT/SERVICE CODE AD61. SERVICE DESCRIPTION CONSTRUCTION | Agriculture, Department of / Forest Service | 10/20/2009 |
NORTHWEST CASCADE, INC. | $4,388 | Contract | : Monthly portable toilet rental and service | Agriculture, Department of / Forest Service | 6/02/2010 |
RED RIVER TRAILS | $25,770 | Contract | : Deferred trail maintenance, logging and brushing wilderness and non-wilderness trails. | Agriculture, Department of / Forest Service | 9/17/2010 |
KADIX SYSTEMS, LLC | $465,259 | Contract | : To perform procurement acquisition and processing and grant and agreements tracking and distribution. The Procurement Technician works on various aspects of procurement such as creating contract files, maintain data for contract reporting purposes, and s | Agriculture, Department of / Forest Service | 9/24/2010 |
MESCALERO APACHE TRIBE | $357,240 | Contract | : George Unit, Service | Agriculture, Department of / Forest Service | 4/06/2010 |
CONSERVATION CORPS, CALIFORNIA | $89,500 | Grant | Recovery Act of 2009: Capital Improvement and Maintenance: Project consists of idecommissioning recreational facilities at Bass Lake Ranger District and High Sierra Ranger District. | Agriculture, Department of / Forest Service | 8/06/2010 |
DON ABEL BUILDING SUPPLIES, INC. | $17,660 | Contract | : Delivered building Materials:110pcs-wire fencing,110pcs-4x6-12'cedar,100pcs-2x6-16'cedar,2x4-16'cedar,200pcs-1x4-16'cedar,75pcs-1x6-16'cedar. | Agriculture, Department of / Forest Service | 7/30/2010 |
CONCO CONCRETE SPECIALISTS, L.L.C. | $773,469 | Contract | : install shower building at campground | Agriculture, Department of / Forest Service | 7/07/2010 |
ANDERSON LAND DEVELOPMENT | $31,218 | Contract | : 54 Miles of ATV & Snowmobile Trail Brushing in the Superior National Forest. Located on the Tomahawk Trail, Deep Water Trail & ATV User Route 179. Cutting and masticating brush and trees up to 3 inches in diameter along both sides of specified trails. Cut | Agriculture, Department of / Forest Service | 5/20/2010 |
GREAT DIVIDE FORESTRY | $53,700 | Contract | : tree thinning services | Agriculture, Department of / Forest Service | 8/27/2010 |
BACKLUND LOGGING CO | $150,100 | Contract | : Hand slash piling on the Knox timber sale and FR16 of the Prairie City Ranger District of the Malheur National Forest | Agriculture, Department of / Forest Service | 8/23/2010 |
WATERS CRAFTSMAN I, INC | $223,083 | Contract | : Masonry Work at Grey Towers National Historic Site, Milford, PA masonry restoration of historic stone walls and replication and replacement of blue stone coping stones. | Agriculture, Department of / Forest Service | 5/27/2010 |
DOT CONSTRUCTION, INC. | $462,937 | Contract | : Provide design and rehabilitation of a 93 ft span pony truss bridge over the Davidson River. | Agriculture, Department of / Forest Service | 5/28/2010 |
MESCALERO APACHE TRIBE | $708,286 | Contract | : Perk-Grindstone Cut and Hand Pile Unit. TAS::12 1118::TAS RECOVERY, PURPOSE OF TASK ORDER IS TO PROVIDE HAZARDOUS FUEL REDUCTION BY CUT AND HAND PILEING TREES. | Agriculture, Department of / Forest Service | 4/06/2010 |
MANAGEMENT ENGINEERING ASSOCIATES LLC | $197,719 | Contract | : Energy Efficiency Project | Agriculture, Department of / Forest Service | 3/15/2010 |
BONNEVILLE ASPHALT & REPR LLC | $304,840 | Contract | : This contract is to do crack sealing and asphalt patching in select areas in Lochsa-Pierce Ranger District, Clearwater National Forest. | Agriculture, Department of / Forest Service | 7/14/2010 |
HAMILTON & SONS EXCAVATING | $411,812 | Contract | : Improvements to NFSRs 420-4,420-5,420-6 and including reconstructing roadbed, linear grading, surfacing, drainage improvements including two large bottomless arch installations, relief culvert installations,ditch construction, and rollinng dip constructio | Agriculture, Department of / Forest Service | 5/28/2010 |
LEDFORD & PARKER, INC. | $55,369 | Contract | : Fires Creek Trail Head Rehabilitation. Project consists of the reconstruction of the existing asphalt paved picnic area access trails and paving a section of the existing gravel parking lot, installing signage and pavement markings. | Agriculture, Department of / Forest Service | 7/09/2010 |
LANPACIFIC, INC. | $3,881,150 | Contract | : TAS::12 1102::TAS RECOVERY-MCKENZIE RIVER DISTRICT OFFICE RENOVATION, MCKENZIE BRIDGE, OREGON. TWO-PHASE, DESIGN-BUILD PROJECT TO INTEGRATE EXISTING, PARTIAL RENOVATION AND NEW CONSTRUCTION INTO THE CURRENT FACILITY. PROJECT INCLUDES ALTERNATIVE ANALYSIS | Agriculture, Department of / Forest Service | 12/23/2009 |
MERCURY CONSTRUCTORS, INC. | $12,782 | Contract | : We graded and watered the existing road (NFSR 26) to prepare it for the new gravel surface, cleaned the existing culverts and drainage ditches for storm water run-off and did general cleanup along the roadway. Then gravel surfacing was dumped on the prep | Agriculture, Department of / Forest Service | 12/17/2009 |
REC SOLAR, INC. | $1,084,894 | Contract | : Design and build a grid connected solar photovoltaic system for the San Dimas (CA)Technology & Development Center. | Agriculture, Department of / Forest Service | 7/22/2010 |
GRAY BEAR CONSTRUCTION CO. | $104,592 | Contract | : Fire Lookout Catwalk Replacement, Roof Replacement, Floor Replacement - Malheur National Forest | Agriculture, Department of / Forest Service | 8/31/2010 |
CELIA HEADLEY | $6,900 | Contract | : Collection and delivery of native plant seed | Agriculture, Department of / Forest Service | 9/09/2009 |
ALGERINE WEST CONSTRUCTION | $201,408 | Contract | : Culvert upgrades on Rock Creek Road- Consisting of removing existing culverts, structurally reinforce with concrete footings and headwalls. Concrete and install new corrugated culvert pipes. | Agriculture, Department of / Forest Service | 7/13/2010 |
CXT INCORPORATED | $82,241 | Contract | : TAS::12 1102::TAS- Toilet Replacements | Agriculture, Department of / Forest Service | 4/26/2010 |
NORTHERN MOUNTAIN CONSTRUCTORS, INC | $20,671 | Contract | : Supply Concrete and Mortar Sand - Camino Real Ranger District | Agriculture, Department of / Forest Service | 3/22/2010 |
SOLARGLASS WINDOW & DOOR INC | $56,486 | Contract | : Supply replacement windows | Agriculture, Department of / Forest Service | 8/04/2010 |
STATEWIDE CONTRACT SERVICES, LLC | $83,419 | Contract | : Rd 1912 timber sale rd repairs, realignment of existing rd, surveying and construction staking, clearing and grubbing, excavation and end hauling of excavated material, roadway reconditioning and supply and placement of aggregate and placement of pit run | Agriculture, Department of / Forest Service | 6/24/2010 |
CARVER, ANGELA R | $23,647 | Contract | : Project 4-FW Deferred Maintenance-Palouse Housing | Agriculture, Department of / Forest Service | 7/28/2010 |
GORDON PAVING COMPANY, INC. | $43,518 | Contract | : Crush gravel/aggregate for the Cassia, Idaho Division | Agriculture, Department of / Forest Service | 5/13/2010 |
KOMADA, LLC | $2,924,354 | Contract | : Design/Build Scott Valley Helibase Fire Station. This project includes the design and construction of the fire station, a garage, and a barracks. | Agriculture, Department of / Forest Service | 8/17/2010 |
CIVIL CONSTRUCTION COMPANY INC | $476,180 | Contract | : North Fork John Day River Bridge Replacement | Agriculture, Department of / Forest Service | 7/28/2010 |
ENVIRONMENTAL LAND CLEARING | $708,480 | Contract | : BUNDLED MECHANICAL WUI ON PRESCOTT NATIONAL FOREST | Agriculture, Department of / Forest Service | 6/25/2010 |
A&H CONTRACTING, LLC | $41,156 | Contract | : Upgrading existing signs on Superior national forest roads. | Agriculture, Department of / Forest Service | 5/20/2010 |
BENCHMARK ENGINEERING INC | $61,050 | Contract | : Investigate specified sites, collect user data and compliance regulations, and prepare sanitary and condition surveys and O&M plans for various water/waste water systems on the Chippewa and Superior National Forests. | Agriculture, Department of / Forest Service | 1/27/2010 |
HAMILTON & SONS EXCAVATING | $538,345 | Contract | : Improvements to Davis Creek Road to include:Clearing, grubbing, removal of culverts, roadway excavation, embankment construction, drainage excavation, ditch & rolling dip construction, blasting, roadway obliberation, placed rip-rap, aggregate base install | Agriculture, Department of / Forest Service | 5/28/2010 |
WATERLOO COAL COMPANY, INC. | $180,000 | Contract | : A contract to provide limestone to Wayne National | Agriculture, Department of / Forest Service | 5/27/2010 |
RESTORATION SOLUTIONS LLC | $447,552 | Contract | : Bundled Mechanical WUI Treatment Project - Mechanical cutting, mastication, and mulching treatment with the objective of developing a fuelbreak system on Prescott National Forest lands. | Agriculture, Department of / Forest Service | 6/24/2010 |
HOOD, JUDI | $11,275 | Contract | : RECYCLED PLASTIC LUMBER | Agriculture, Department of / Forest Service | 6/02/2010 |
STOR-MOR SYSTEMS, INC. | $7,900 | Contract | : Furnish and install a 12x14 storage shed. | Agriculture, Department of / Forest Service | 5/07/2010 |
JACOBSON GRENFELL INC | $6,021 | Contract | : Large and Small Reflective Forest Service Signs | Agriculture, Department of / Forest Service | 8/03/2010 |
JOHN JUMP TRUCKING INC | $70,921 | Contract | : McCall Biomass Removal - Grinding of remaining logging slash piles into hogfuel (biomass) and removing the biomass materials from the jobsite and taking it to area mills. | Agriculture, Department of / Forest Service | 12/29/2009 |
STRATA SERVICES, INC. | $18,918 | Contract | : This award included the installation of the wastewater nitrification trenches at the Little Oak Campground--Hemlock Loop in the Cherokee National Forest. Distribution systems were Infiltrator Quik4 standard chambers from Public Drainage Supply. Clearing | Agriculture, Department of / Forest Service | 4/20/2010 |
LIBERTY ROOFING LLC | $319,150 | Contract | : North Fork & Trimmer roof replacement. CIM-05-03F | Agriculture, Department of / Forest Service | 9/01/2010 |
SIDEHILL MUGWUNT PROTECTION SOCIETY INC | $8,880 | Contract | : Restoration of Glade Guard Stattion Windows, San Juan National Forest | Agriculture, Department of / Forest Service | 10/19/2009 |
CLAY, COUNTY OF | $1,180,319 | Contract | : Provide public sewer service to Jackrabbit Recreational Area. They will install 26,000 linear feet of 4' forcemain and 2 sewer pump stations to transmit the flow from the campground to the Clay County water & sewer district's system. This project will eli | Agriculture, Department of / Forest Service | 2/11/2010 |
COASTAL CAROLINA THERAPY,LLC | $138,991 | Contract | : Renovation of historic Pisgah Fire Towers, Pisgah National Forest, NC | Agriculture, Department of / Forest Service | 5/26/2010 |
MACAULEY CONSTRUCTION | $55,166 | Contract | : El Dorado Culvert | Agriculture, Department of / Forest Service | 8/26/2010 |
HARTLAND CONSTRUCTION, INC. | $280,520 | Contract | : historical site renovation to include renovation of 7 buildings | Agriculture, Department of / Forest Service | 6/15/2010 |
CHELF LUMBER CO, INC | $3,973 | Contract | : Building Materials | Agriculture, Department of / Forest Service | 12/15/2009 |
SCHLEGEL & SONS CONTRACTORS, INC | $12,370 | Contract | : Reconstruction Trail Head in South Fork of Flathead | Agriculture, Department of / Forest Service | 9/20/2009 |
SWINERTON BUILDERS | $3,649,671 | Contract | : RECOVERY Project for the Angeles National Forest to construct Rincon Fire Station and Barracks. | Agriculture, Department of / Forest Service | 9/15/2010 |
CHELF LUMBER CO, INC | $11,182 | Contract | : Building Materials | Agriculture, Department of / Forest Service | 3/16/2010 |
TERRA TECH, LLC | $9,020 | Contract | : tubes and bamboo | Agriculture, Department of / Forest Service | 7/23/2010 |
TURNKEY CONSTRUCTION SERVICES, INC. | $145,790 | Contract | : ARRA Union Flat Water System Rehab | Agriculture, Department of / Forest Service | 8/23/2010 |
HACIENDA HOME CENTERS, INC. | $45,865 | Contract | : provide building materials | Agriculture, Department of / Forest Service | 5/17/2010 |
K-CON, INC. | $96,347 | Contract | : Removal and replacement of three other glass doors at the employee entrance which shall be installed with a handicap door operator and two doors at the driveway/smokers entrance. | Agriculture, Department of / Forest Service | 9/22/2010 |
ENVIROGRIND,LLC | $72,525 | Contract | : Fuels Reduction-Mulching & Chainsaw Felling, Talladega Ranger District, National Forests in Alabama | Agriculture, Department of / Forest Service | 4/28/2010 |
L & S CONTRACTING | $412,250 | Contract | : THINNING CONTRACT | Agriculture, Department of / Forest Service | 7/19/2010 |
ECOABITAT, CORP. | $221,354 | Contract | : Trail Repairs at El Yunque National Forest | Agriculture, Department of / Forest Service | 5/11/2010 |
ACEVEDO, MARISA A | $501,189 | Contract | : Wildland Fire Management Services to mechanically thin conifers, brush cutting, and fuels reduction. | Agriculture, Department of / Forest Service | 6/28/2010 |
WALT MYERS CONSTRUCTION | $204,934 | Contract | : Bessey National Forest showerhouse and pool demolision and showerhouse replacement, Scott Tower renovation | Agriculture, Department of / Forest Service | 5/25/2010 |
BATEMAN FOREST MANAGEMENT INCORPORATED | $1,575 | Contract | : This project will consist of ripping approximately 1100 linear feet of existing campground road surfaces with an Excavator. | Agriculture, Department of / Forest Service | 12/29/2009 |
ROBERT DOMINIKUS GENERAL ENGINEERING | $465,529 | Contract | : Hey Joe Road and Bridge Repair | Agriculture, Department of / Forest Service | 8/10/2010 |
JOHN JUMP TRUCKING INC | $163,650 | Contract | : New Meadows Biomass Removal - Grinding of remaining logging slash piles into hogfuel (biomass) and removing the biomass materials from the jobsite and taking it to area mills. | Agriculture, Department of / Forest Service | 12/29/2009 |
TEMPLE & TEMPLE EXCAVATING & PAVING INC | $92,881 | Contract | : Jeffery Cemetery Road Reconstruction | Agriculture, Department of / Forest Service | 9/10/2010 |
WESTERN RECLAMATION, INC. | $15,700 | Contract | : Western Reclamation, Inc. is under contract with the Forest Service to compete for the production of native seed species. Western Reclamation became one of the bidders for contracts after completing an arduous Solicitation which essentially described our | Agriculture, Department of / Forest Service | 7/27/2010 |
ADVANCED WASTEWATER ENGINEERING, P.C. | $22,383 | Contract | : Installation of water line to serve Cabin at park. Install new pump and controls for well. New building and piping for controls | Agriculture, Department of / Forest Service | 9/10/2010 |
GARY RINDERLE CONSTRUCTION INC | $5,000 | Contract | : RENTAL OF 1 PLATE COMPACTOR FOR DIVIDE RANGER DISTRICT FOR 4 MONTHS (JUNE-SEPTEMBER 2010) RENTAL OF 1 PLATE COMPACTOR FOR CONEJOS PEAK RANGER DISTRICT FOR 4 MONTHS (JUNE-SEPTEMBER 2010) RENTAL OF 1 PLATE COMPACTOR FOR SAGUACHE RANGER DISTRICT FOR 3 MONT | Agriculture, Department of / Forest Service | 12/23/2009 |
KEETON EXCAVATING, INC. | $249,517 | Contract | : TAS::12 1102::TAS CIM-0802-37R RECOVERY - REPLACEMENT OF CULVERTS, DANIEL BOONE NATIONAL FOREST, KY | Agriculture, Department of / Forest Service | 6/01/2010 |
GENERAL WELDING & REPAIR | $3,736 | Contract | : Delivered iron product to Anaconda Job Corp Center | Agriculture, Department of / Forest Service | 12/01/2009 |
RJK LOGGING LLC | $80,400 | Contract | : Thinning, slashing, piling and removal of included timber. 629 CCF of nonsaw logs. 199 CCF of deliverable saw logs | Agriculture, Department of / Forest Service | 5/05/2010 |
INTERMOUNTAIN DISPOSAL, INC. | $3,988 | Contract | : DELIVERY AND REMOVAL 4 - 40 CUBIC YARD CONTAINERS | Agriculture, Department of / Forest Service | 7/30/2010 |
DALEY, ARTHUR M | $6,506 | Contract | : Apache Zone Recreation Hazard Tree Removal | Agriculture, Department of / Forest Service | 7/13/2010 |
SUPPLYFORCE.COM, LLC | $13,051 | Contract | : Plumbing Supplies for Forest Service - Southwestern Region Location. Project: Camino Real Office Makeover Project, New Mexico. Total Small Business Set Aside. | Agriculture, Department of / Forest Service | 7/26/2010 |
ROSS SPARKS BUILDERS, INC. | $229,633 | Contract | : Interior and Exterior Painting of Building and Installation of Owner furnished Carpet | Agriculture, Department of / Forest Service | 6/03/2010 |
KICKIN ASPHALT PAVING AND SEALING LLC | $40,539 | Contract | : ASPHALT PAVING OF WALKING TRAILS... MASSANUTTEN STORYBOOK & DISCOVERY WAY | Agriculture, Department of / Forest Service | 12/22/2009 |
BIG PINE CONSTRUCTION LLC | $60,840 | Contract | : Rock removal of Protruding rocks from an ATV Trail. Trail reconstruction and trail bridge replacement. | Agriculture, Department of / Forest Service | 3/22/2010 |
TROPICAL CONTRACTING, LLC | $644,390 | Contract | : Cow Creek South Campground Improvements Project. Road Rehabilitation | Agriculture, Department of / Forest Service | 9/24/2010 |
REM CONSTRUCTION | $290,683 | Contract | : Remove and dispose of lead paint. Repair any damage and repaint the 3 west side bridges | Agriculture, Department of / Forest Service | 7/06/2010 |
TILDEN-COIL CONSTRUCTORS, INC. | $15,000 | Contract | : Tilden-Coil Constructors was given a stipend to bid on construction work for the Angeles National Forest Design Build Project. Tilden-Coil was not the contractor of choice, thus received only a stipend to offset part of the cost associated with bidding th | Agriculture, Department of / Forest Service | 9/23/2010 |
LOS PADRES OUTFITTER | $30,960 | Contract | : TAS::12 1102::TAS RECOVERY - PACK SUPPORT FOR SANTA LUCIA RANGER DISTRICT CY 2011 CAPITAL IMPROVEMENT. Pack Mules with supplies for Forest Service Rangers. | Agriculture, Department of / Forest Service | 7/09/2010 |
TERRA TECH, LLC | $15,970 | Contract | : tubes and bamboo | Agriculture, Department of / Forest Service | 4/16/2010 |
FORSTAT INC | $4,483 | Contract | : Slash Pile Paper for the Kootenai National Forest | Agriculture, Department of / Forest Service | 6/04/2010 |
HOUCK, RONALD C | $68,434 | Contract | : hazardous fuel reduction | Agriculture, Department of / Forest Service | 4/22/2010 |
GRAY LUMBER COMPANY, INC | $39,120 | Contract | : We provided treated sign posts for use in the parks to facilitate the installation of signage that would showcase services and ammenities available to the public and enhance their experience. | Agriculture, Department of / Forest Service | 6/03/2010 |
JACK BROWN & SON, INC | $113,850 | Contract | : Cutting and mulching the smaller and weaker trees to give the bigger and healthier trees a boost. We also mow the brush to reduce the fire hazard. | Agriculture, Department of / Forest Service | 5/19/2010 |
KOOTENAI INSULATION | $7,300 | Contract | : Install Insulation at the Sylvanite Ranger Station | Agriculture, Department of / Forest Service | 9/16/2010 |
ORICA USA INC. | $8,507 | Contract | : EXPLOSIVE PRODUCT SALES IN VIRGINIA | Agriculture, Department of / Forest Service | 3/26/2010 |
TM CONSTRUCTION, INC. | $674,000 | Contract | : The purpose of this contract is to create wildlife habitat by going back in to areas that were logged twenty to thirty years ago and thinning out the second growth timber that has grown. This is to encourage the under growth (shrubs and bushes) to grow, | Agriculture, Department of / Forest Service | 8/09/2010 |
EVERGREEN ALASKA INC | $476,400 | Contract | : Hazardous fuels reduction around community of Hope, AK. | Agriculture, Department of / Forest Service | 12/29/2009 |
FISCHER CORP. | $31,475 | Contract | : Break up and obliterate road beds and level and restore to natural draining and establish natural vegetation habitat. Removal and disposal of structures. Placement of 21 boulders. Establish water bars and rolling dips. Apply wildflower seeds and mulch to | Agriculture, Department of / Forest Service | 1/27/2010 |
PONDEROSA REFORESTATION, INC. | $388,424 | Contract | : Tree thinning in rural forest areas. Thin dead branches to avoid forest fires, then dead branches are piled up to be picked up or burn. | Agriculture, Department of / Forest Service | 7/09/2010 |
KODIAK-KENAI CABLE COMPANY, LLC | $1,500 | Contract | : Job Proposal flat fees for the Discovery Center Biomass, Discovery Center Deferred Maintenance Repairs, and the MGVC Deferred Maintenance Repairs. ($500.00/ea x 3 = $1,500.00) | Agriculture, Department of / Forest Service | 9/09/2010 |
ENTRIX, INC. | $483,462 | Contract | : TAS::12 1102::TAS 2010 RECOVERY FUNDS--Dixie ARRA Cultural Surveys WFM-0407-04HF | Agriculture, Department of / Forest Service | 9/16/2010 |
ALLEN COMPANY, INC., THE | $57,617 | Contract | : RECOVERY: TAS12 1102::TAS, CIM-0802-37R. Furnish, Haul and spread stone aggregate Forest Service roads located on the Daniel Boone National Forest, Kentucky | Agriculture, Department of / Forest Service | 12/15/2009 |
WESTERN PROCESSING INC | $30,620 | Contract | : Bitterroot Roadside Brushing Bitterroot National Forest Mechanical Roadside Brushing Task Order AG-82B1-D-10-0080 Period of Performance: May 24,2011 to September 30,2011 | Agriculture, Department of / Forest Service | 2/17/2010 |
ALPHA SERVICES, LLC | $23,628 | Contract | : Replace + maintain vexar tubing for newly planted seedlings | Agriculture, Department of / Forest Service | 12/24/2009 |
NORTHERN TIMBERLANDS, INC. | $394,806 | Contract | : Contract Name: Huron Jack Pine Fuels Stewardship Recovery Project Currently, removal of undergrowth and brush for the purpose of prevention of forest fires and for the purpose of stimulating new growth is being performed on this property. | Agriculture, Department of / Forest Service | 9/17/2010 |
GE FORESTRY, INC | $61,000 | Contract | : Pre-commercial Thinning | Agriculture, Department of / Forest Service | 2/09/2010 |
TRINITY COUNTY FAIR ASSOCIATION | $7,140 | Contract | : Rental of Fairground campground with shower usage for CCC crew. | Agriculture, Department of / Forest Service | 3/30/2010 |
LAND & MOWING SOLUTIONS | $76,190 | Contract | : hazardous feul reduction or woody debris reduction using a brontosaurus tree mulcher. | Agriculture, Department of / Forest Service | 9/03/2010 |
ECES INC. | $52,329 | Contract | : Tuskegee NFSR 906 culvert replacement: This project is designed to demolish and replace an existing culvert and raise the roadbed on NFSR 906 Tuskegee. | Agriculture, Department of / Forest Service | 12/10/2009 |
HOPKINS FORESTRY AND I/TACK | $98,678 | Contract | : Forest Service Road Maintence | Agriculture, Department of / Forest Service | 9/19/2009 |
IDAHO FOREST GROUP LLC | $307,852 | Contract | : To reduce hazardous fuels on 216 acres in the Payette National Forest; Reduce erosion through road reconstruction on 2.9 miles; contribute to woody biomass utilization by removing slash from National Forest lands. | Agriculture, Department of / Forest Service | 12/28/2009 |
CMEC, INCORPORATED | $58,208 | Contract | : Paint 17 buildings @ Lake Ranger Station. Pressure wash all buildings to prep for new primer and paint. Apply caulking to all gaps, cracks and seals. All paint chips must be cleaned up and disposed of properly. | Agriculture, Department of / Forest Service | 8/16/2010 |
PLANT CONSTRUCTION COMPANY LP | $11,178,760 | Contract | : Design Build contract for two District Ranger Stations at the Los Padres National Forest, Frazier Park, CA and King City, CA | Agriculture, Department of / Forest Service | 8/25/2010 |
WEBER CONSTRUCTION, INC. | $42,371 | Contract | : Recovery - Hansen Creek Pipe Replacement | Agriculture, Department of / Forest Service | 3/10/2010 |
KAY & KAY CONTRACTING, LLC | $51,349 | Contract | : Furnish and deliver aggregate for various US forest service roads | Agriculture, Department of / Forest Service | 12/15/2009 |
LANDSTAR DEVELOPMENT | $211,500 | Loan | Recreation Resource Management: Construct new trail bridges to be used for pedestrian and pack horse traffic. The bridges are constructed with lumber, and span approximately 40 feet. This contract includes 3-bridges and is specifically named Rock Creek Trail Bridges #2 & #4 and St. Pau | Agriculture, Department of / Forest Service | 7/27/2010 |
GRANITE EXCAVATION, INC. | $146,424 | Contract | : Rosebud Culvert Replacement | Agriculture, Department of / Forest Service | 3/02/2010 |
BONNEVILLE ASPHALT & REPR LLC | $706,910 | Contract | : THIS AWARD WAS FOR ASPHALT CRACKSEAL AND PATCHING AT UPPER NORTH FORK RANGER DISTRICT, CLEARWATER NATIONAL FOREST. | Agriculture, Department of / Forest Service | 8/23/2010 |
MORRIS,STEVE | $8,000 | Contract | : mule packing trail crew supplies ventana wilderness los padres National forest | Agriculture, Department of / Forest Service | 7/08/2010 |
BOB'S YARD INC | $5,800 | Contract | : PROVIDE PORTABLE TOILETS AND HAND WASH STATIONS FOR CONSTRUCTION SITE FOR THE PENASCO RANGER STATION | Agriculture, Department of / Forest Service | 3/11/2010 |
THOMPSON CONTRACTING, INC. | $894,830 | Contract | : Forest Road reconditioning crushing aggrigate, haul, place and finish grade material. then apply dust seal | Agriculture, Department of / Forest Service | 9/09/2010 |
PACIFIC HIDE & FUR DEPOT | $7,100 | Contract | : Culverts | Agriculture, Department of / Forest Service | 10/03/2010 |
BIG PINE CONSTRUCTION LLC | $73,250 | Contract | : Antley Creek Bridge Receplacements, Flathead National Forest | Agriculture, Department of / Forest Service | 8/13/2010 |
SUMCO ECO-CONTRACTING, LLC | $107,375 | Contract | : Chittenden Brook Trail Bridge Reconstruction | Agriculture, Department of / Forest Service | 5/07/2010 |
LOS PADRES OUTFITTER | $61,530 | Contract | : TAS::12 1102::TAS - RECOVERY - CCC SESPE WILDERNESS STOCK PACKING - CAPITAL IMPROVEMENT AND MAINTENANCE (TRAIL MAINTENANCE & DECOMMISSIONING). | Agriculture, Department of / Forest Service | 7/22/2010 |
NORTH, ERIC | $8,400 | Contract | : Endangered/Threatened Species Surveys (Biology) Chryxus Arctic Butterfly | Agriculture, Department of / Forest Service | 10/19/2009 |
HINSON CONSTRUCTION | $76,578 | Contract | : small campgrounds improvements for three water wells with hand pumps on concrete slabs | Agriculture, Department of / Forest Service | 6/16/2010 |
THOMPSON CONTRACTING, INC. | $230,652 | Contract | : CULVERT AND ROAD RECONDITIONING Spread Creek Drainage. Road surface upgrade and drainage. | Agriculture, Department of / Forest Service | 7/21/2010 |
DALEY, ARTHUR M | $14,145 | Contract | : Hazard Tree removals in West Fork Campground, Alpine Ranger District on Apache-Sitgreaves N.F. | Agriculture, Department of / Forest Service | 6/15/2010 |
ATHERLY CONTRACTING, LLC | $210,230 | Contract | : Tree thinning and hand piling in the Malheur National Forest. | Agriculture, Department of / Forest Service | 6/02/2010 |
ERA MARINE | $13,370 | Contract | : Floating Dock and Ramp | Agriculture, Department of / Forest Service | 1/27/2010 |
SPECIALIZED TREE SERVICE | $6,300 | Contract | : remove hazordus trees from with in use of recreation | Agriculture, Department of / Forest Service | 9/02/2010 |
LIGHTHOUSE FOR THE BLIND, THE | $6,872 | Contract | : Provide tree marking paint to the Forest Service in support of their activities. This includes procuring raw material, packaging the paint and preparting for shipment. THis activity takes only a few hours to complete. | Agriculture, Department of / Forest Service | 10/20/2009 |
TYLER RENTAL, INC. | $11,400 | Contract | : Rental of 2 earthmovers (w/o operator) on rubber tracks for Trail of Time located at the Mendenhall Glacier Visitor Center. Rental items were returned prior to the 60 day original rental period stated on the award. Therefore, amount invoiced is less than | Agriculture, Department of / Forest Service | 5/20/2010 |
W W LAND SURVEYING PC | $25,397 | Contract | : USDA - US Forest Service Pisgah Ranger District Reed Cove. Retracement survey of a portion of USFS Tracts P-V-1, P-V-12, and P-203 | Agriculture, Department of / Forest Service | 8/19/2010 |
PONDEROSA REFORESTATION, INC. | $1,557,392 | Contract | : Recovery upper hellgate #7 and Galice #10 Fuel Reduction | Agriculture, Department of / Forest Service | 5/26/2010 |
TOM MAHON LOGGING INC | $657,883 | Contract | : IRSC Contract for Summit Gulch Stewardship. We are required to: Thin, Lop, and remove 4.5 foot tall to 7.9 inch d.b.h trees Pull Slash Hand Fire Line Road Reconstruction/Construction Chip and Remove Landing Slash Road Decommissioning Long Term Road Closu | Agriculture, Department of / Forest Service | 4/07/2010 |
KERRY FULLER ENTERPRISES, INC. | $47,767 | Contract | : striping roads | Agriculture, Department of / Forest Service | 3/18/2010 |
LAYMON, ROBERT D | $18,620 | Contract | : DEEPEN AND DECOMMISSION WELL AT META LAKE | Agriculture, Department of / Forest Service | 5/11/2010 |
CRUME, REX R | $19,850 | Contract | : Firm fixed price delivery order. Danger Tree removal on Federal lands. | Agriculture, Department of / Forest Service | 3/23/2010 |
GEOTECH ENVIRONMENTAL SERVICES, INC. | $33,768 | Contract | : Abandon Several Wells | Agriculture, Department of / Forest Service | 3/25/2010 |
CGO CONSTRUCTION COMPANY INC | $93,455 | Contract | : Recreation Sites Pavement Rehabilitation | Agriculture, Department of / Forest Service | 7/02/2010 |
SPRUCE VALLEY CORPORATION | $165,050 | Contract | : REMOVAL AND INSTALLATION OF CULVERTS, EXCAVATION,PLACEMENT OF EMBANKMENT,SEEDING AND MULCHING | Agriculture, Department of / Forest Service | 5/27/2010 |
THOMPSON CONTRACTING, INC. | $57,638 | Contract | : AGGRIGATE PLACEMENT | Agriculture, Department of / Forest Service | 2/28/2010 |
DAVID ACTON BUILDING CORPORATION | $238,630 | Contract | : LOWER NORTH FORK BRIDGE REPAIRS This contract will consists of bridge repairs on three bridges Flume Creek, Lolo Creek, and Skull Creek Bridges. Flume Bridge Repairs: This work will consists of removing and replacing timber abutment post, repairing stream | Agriculture, Department of / Forest Service | 8/03/2010 |
HUMAN INTERACTIVE PRODUCTS, INC. | $410,072 | Contract | : Removal of invasive non-native species along State Highway Evacuation Route | Agriculture, Department of / Forest Service | 7/20/2010 |
BUILDINGS & GROUNDS SERVICE CORPORATION | $264,998 | Contract | : Green Roof Project for Forest Service Depatment in Puerto Rico | Agriculture, Department of / Forest Service | 8/31/2010 |
PONDEROSA REFORESTATION, INC. | $263,825 | Contract | : Recovery SAFR - thinning and handpiling and burning piles in Deschutes National Forest | Agriculture, Department of / Forest Service | 7/01/2010 |
JALENE ENTERPRISES LTD | $76,674 | Contract | : Trail Brushing Wayne National Forest Athens Ranger District | Agriculture, Department of / Forest Service | 12/23/2009 |
CONSERVATION CORPS, CALIFORNIA | $75,000 | Grant | Recovery Act of 2009: Capital Improvement and Maintenance: As part of a on-going, long term maintenance strategy for the Pacific Coast Trail (PCT) that leverages work of partner organizations, including the Backcountry Horsemen, Pacific Coast Trail Association (PCTA) and Sierra Buttes Trails Stewardsdship with Plum... Show more | Agriculture, Department of / Forest Service | 7/20/2010 |
JL AVIATION INC | $8,000 | Contract | : Helicopter flight services to support movement of cargo | Agriculture, Department of / Forest Service | 4/20/2010 |
L R COSTANZO COMPANY INC | $235,046 | Contract | : Stair Reconstruction | Agriculture, Department of / Forest Service | 6/09/2010 |
WASTE MANAGEMENT OF NEW MEXICO, INC. | $28,910 | Contract | : DUMPSTER RENTAL FOR CONSTRUCTION IN PENASCO, NEW MEXICO FOR 16 MONTHS. | Agriculture, Department of / Forest Service | 3/22/2010 |
MOBILE MINI, INC. | $9,845 | Contract | : Mobile office Rental | Agriculture, Department of / Forest Service | 3/05/2010 |
FOREST ENERGY GROUP LLC | $622,696 | Contract | : Prime Contract | Agriculture, Department of / Forest Service | 7/15/2010 |
CENTRAL OR AGGREGATE | $28,400 | Contract | : UMATILLA Forest-Wide Toilet Site Development | Agriculture, Department of / Forest Service | 5/28/2010 |
KLP INC | $52,550 | Contract | : INSTALLATION OF LIGHTNING PROTECTION SYSTEMS | Agriculture, Department of / Forest Service | 5/11/2010 |
TYLER CONSTRUCTION GROUP, INC. | $290,900 | Contract | : We are to replace a old bathhouse with a new pre manufactured bath house at the Cherry Hill campground. Also to add 1000 tons of stone over the existing road. Also demolish the old bath house once the new one is accepted. | Agriculture, Department of / Forest Service | 5/13/2010 |
CGO CONSTRUCTION COMPANY INC | $225,120 | Contract | : Recreation Sites Reconstruction | Agriculture, Department of / Forest Service | 7/02/2010 |
NATHAN G LARGE | $31,891 | Contract | : Silverspot Butterfly Habitat Restoration | Agriculture, Department of / Forest Service | 5/13/2010 |
WESTERN PRE-CAST LLC | $1,850 | Contract | : Precast concrete septic tank with a precast base for rustic outhouse construction. | Agriculture, Department of / Forest Service | 8/27/2010 |
MCALLISTER, MICHAEL L | $11,894 | Contract | : Mapping Individual Tree positions and recording them into Excel Database. These trees were established as the future seed source for district wide reforestation. After the mapping is completed trees are permantly monument tagged. | Agriculture, Department of / Forest Service | 5/25/2010 |
TEMPLE & TEMPLE EXCAVATING & PAVING INC | $92,881 | Contract | : Jeffery Cemetery Road Reconstruction | Agriculture, Department of / Forest Service | 9/10/2010 |
MARSHFIELD FOREST SERVICE, INC | $124,624 | Contract | : This award is for the treatment of non-native invasivve spieces within Francis Marion National Forest. | Agriculture, Department of / Forest Service | 8/27/2010 |
CHANNEL CONSTRUCTION INC | $540,440 | Contract | : Hoonah Bridge Replacement | Agriculture, Department of / Forest Service | 3/12/2010 |
JACK BROWN & SON, INC | $36,260 | Contract | : Cutting and mulching some of the brush and trees within 300 feet of Lakeshore Drive in Lakehead CA to create a fire break. | Agriculture, Department of / Forest Service | 6/28/2010 |
E.C. THINNING LLC | $16,750 | Contract | : Thinning & Pruning | Agriculture, Department of / Forest Service | 8/10/2010 |
ACEVEDO, JORGE E | $495,542 | Contract | : ARRA Road Maintenance Roadside Brushing | Agriculture, Department of / Forest Service | 6/28/2010 |
PONDEROSA REFORESTATION, INC. | $187,550 | Contract | : Gold Beach Meadow Restoration and tree planting in the Rogue River Siskiyou National Forest | Agriculture, Department of / Forest Service | 7/13/2010 |
PENDLETON GRAIN GROWERS, INC. | $7,245 | Contract | : To provide materials for the Wallowa-Whitman National Forest. | Agriculture, Department of / Forest Service | 3/29/2010 |
SHAVER, PAULA JANE | $8,457 | Contract | : Cattle Guard | Agriculture, Department of / Forest Service | 7/30/2010 |
ACCURATE OUTFITTERS | $12,346 | Contract | : Recovery packing service contract for trail hitches accomplished by MCC crew. Responsible for packing MCC crews, tools and gear to designated sites and then returning to assist in packing them back out. Mules are used to pack the gear for the crews. Awa | Agriculture, Department of / Forest Service | 5/27/2010 |
INTERFACE AMERICAS, INC. | $9,651 | Contract | : purchase of carpet tile and adhesive | Agriculture, Department of / Forest Service | 4/28/2010 |
HAYDON BUILDING CORP. | $15,000 | Contract | : Stipend payment fo completion of Phase II submittals to the proposal | Agriculture, Department of / Forest Service | 9/22/2009 |
CHAMBERLIN ARCHITECTS PC | $385,541 | Contract | : Provide preliminary and final design engineering services for the replacement or rehabilitation of three bridges on NFSR 150 on the Gila NF. In addition, prepare NWP 404 and 401 permit documents for the three bridge projects. | Agriculture, Department of / Forest Service | 9/08/2010 |
TIMBERLINE LAND & INVESTMENTS | $799,662 | Contract | : Dullknife Stewardship is a thinning of timber and service contract for areas in the Big Horn national Forest | Agriculture, Department of / Forest Service | 5/06/2010 |
BOULANDGER, SCOTT D | $35,111 | Contract | : NORTHWEST MONTANA COUNTIES TRAIL MAINTENANCE AND RECONSTRUCTION | Agriculture, Department of / Forest Service | 5/24/2010 |
ACME AUTO LEASING LLC | $26,140 | Contract | : Vehicle Lease | Agriculture, Department of / Forest Service | 5/14/2010 |
ASPEN ENVIRONMENTAL GROUP | $75,064 | Contract | : ARRA Road Decommissioning - This work shall consist of implementation monitoring, documentation of finds and reporting in support of the SBNF ARRA Road Dcommissioning Project. | Agriculture, Department of / Forest Service | 4/13/2010 |
SPUR CONSTRUCTION | $34,426 | Contract | : door and jam replacement | Agriculture, Department of / Forest Service | 8/16/2010 |
ADVERTISING CONCEPTS, INCORPORATED | $342,951 | Contract | : Signage System in Inyo National Forest, Mammoth Lakes, CA. to construct cohesive signage system including interpretive messaging and wayfinding along Lake Mary Bike path. Fabricate and install approximately 150 custom directional signs with structural st | Agriculture, Department of / Forest Service | 7/02/2010 |
LKE CORP. | $86,346 | Contract | : Repair of Ballpark Road. Erosion Control, Removal of individual trees, disposal of tops and limps, logs and stumps. Removal of existing culverts. Repair drainage by use of excavation. Remediation of Earth Berms. Roadway reconditioning and aggregate resurf | Agriculture, Department of / Forest Service | 12/29/2009 |
L R COSTANZO COMPANY INC | $1,064,225 | Contract | : Black Locust Allee Restoration Project at Grey Towers | Agriculture, Department of / Forest Service | 6/02/2010 |
STERTZ, MICHAEL | $29,999 | Contract | : Pour concrete foundation and construct ADA ramp | Agriculture, Department of / Forest Service | 5/07/2010 |
SISKIYOU BIOSURVEY LLC | $10,350 | Contract | : Manual collection of wild seed of native grass, shrub and forb species in support of habitat restoration activities | Agriculture, Department of / Forest Service | 8/02/2010 |
ENDLESS GUTTER & SHEET METAL CO INC | $42,500 | Contract | : install storm windows and doors | Agriculture, Department of / Forest Service | 12/07/2009 |
GREEN SEAL ENVIRONMENTAL, INC. | $197,659 | Contract | : Remove and dispose of sewage sludge. Replace sewage lagoon liner | Agriculture, Department of / Forest Service | 12/31/2009 |
OLGUIN'S, INC. | $19,813 | Contract | : Logs and rough cut lumber. | Agriculture, Department of / Forest Service | 12/18/2008 |
LIGHTHOUSE FOR THE BLIND, THE | $6,555 | Contract | : Provide tree marking paint to the Forest Service in support of their activities. This includes procuring raw material, packaging the paint and preparting for shipment. This activity takes only a few hours to complete. | Agriculture, Department of / Forest Service | 11/02/2009 |
ACME AUTO LEASING LLC | $70,886 | Contract | : Vehicle lease | Agriculture, Department of / Forest Service | 5/12/2010 |
HCE, INC. | $347,985 | Contract | : Reconstruction of campground, creation of parking areas and repair and improvement to road access to campground and lake for public recreational use. | Agriculture, Department of / Forest Service | 7/21/2010 |
TORRESOLA, ELIO | $41,115 | Contract | : For the cleanup of the intakes in 10 dams at El Yunque National Forest. | Agriculture, Department of / Forest Service | 3/19/2010 |
HAMMITT, MERNE | $99,990 | Contract | : Upgrade Water System, buffalo Gap National Recreation Area, Medora, ND | Agriculture, Department of / Forest Service | 10/01/2010 |
JACK BROWN & SON, INC | $118,440 | Contract | : Cutting and mulching the smaller weaker trees to give the bigger and healthier trees a boost. We also mow the brush to help reduce the fire hazard. | Agriculture, Department of / Forest Service | 7/08/2010 |
FITZPATRICK PAINTING, INCORPORATED | $130,151 | Contract | : Exterior painting of the historic Timberline Lodge. This included removing multiple layers of old paint, preparing the surface which includes washing, re-caulking and priming surfaces. Areas of rotted wood were replaced, windows resealed. A historic carv | Agriculture, Department of / Forest Service | 12/18/2009 |
DALE A BARGER | $31,467 | Contract | : Log Landing | Agriculture, Department of / Forest Service | 3/25/2010 |
ERIC'S TREE SERVICE | $64,200 | Contract | : This a fuel reduction project for the US Forest Service. Fuel reduction is grinding brush and trees to create standing tree spacing so wild fires do not have a heavy fuel load. This is to decrease the possibility of forest fires. | Agriculture, Department of / Forest Service | 12/17/2009 |
HENDERSON CONTRACTORS CORP | $203,701 | Contract | : Secure forest openings maintenance on the Wayne National Forest,Ironton,Athens Ranger Districs, Marietta units. Cut the grass, trees, and shrubs in the open areas where indicated on contract. | Agriculture, Department of / Forest Service | 1/20/2010 |
GILA CUT-OUT CONSTRUCTION, LLC | $52,000 | Contract | : Tree removal and grubing along forest road 152 in Grant County,NM Gila National Forest | Agriculture, Department of / Forest Service | 2/23/2010 |
MOBILE MINI, INC. | $3,681 | Contract | : Storage COntainer 20' | Agriculture, Department of / Forest Service | 3/09/2010 |
VERJAS NUEVO MILENIO INC | $154,764 | Contract | : Installation of aprox.10,323LF of 4 strands of barbed wire fencew/4-?poles on the Estate Thomas Experimental Forest Bondary | Agriculture, Department of / Forest Service | 8/25/2010 |
SWECO PRODUCTS, INC. | $12,959 | Contract | : Performed various repairs and provided new and/or rebuilt parts for a SWECO 480 trail dozer, serial number SC480-7004 per quote listing provided on 9/20/10. | Agriculture, Department of / Forest Service | 9/29/2010 |
RON'S BACKHOE EXCAVATING | $272,809 | Contract | : TAS::12 1102::TAS REPLACE WATER SYSTEMS AT LITTLE OAKS RECREATION AREA. THIS DOCUMENT REPLACES AG-4419-C-10-0479. | Agriculture, Department of / Forest Service | 2/14/2011 |
LORING, SCOT | $1,900 | Contract | : Establishment of monitoring plots for the rare plants Rhamnus crocea and Horkelia tridentata. Re-measurement of plots after fuels treatment (controlled burn)has taken place. Objective: to observe effects of dense vegetation removal and subsequent fire o | Agriculture, Department of / Forest Service | 3/23/2010 |
SANCHEZ FORESTRY SERVICES | $47,200 | Contract | : wilderness trail bridge construction in the mt.hood national forest. | Agriculture, Department of / Forest Service | 5/04/2010 |
NAMBE PUEBLO HEALTHCARE SERVICES, LLC | $247,710 | Contract | : Little Tesuque Improvements, Santa Fe National Forest | Agriculture, Department of / Forest Service | 9/01/2010 |
D & H HAULING & EXCAVATION, LLC | $105,940 | Contract | : Hand slashing and Excavator piling. | Agriculture, Department of / Forest Service | 11/18/2009 |
SIERRA RESOURCE MANAGEMENT, INC. | $289,800 | Contract | : Granite Stewardship Project. Award provided funds for an additional 375 acres of forest thinning. | Agriculture, Department of / Forest Service | 3/09/2009 |
CARTER CONSTRUCTION | $145,905 | Contract | : Reconstruction of Pinnacle Fire Tower at Cherokee National Forest | Agriculture, Department of / Forest Service | 8/04/2010 |
GLADES ENVIRONMENT INC. | $166,460 | Contract | : Glen Falls Trail Northern Section: Maintain and/or reconstruct 0.7 miles of Glen Falls Trail (upper trail) and side trails to observation platforms #1 and #2. The upper trail section of Glen Falls Trail extends from the Highlands Trail head on NC106 (Sta | Agriculture, Department of / Forest Service | 8/26/2010 |
NORTHWEST MANAGEMENT INC | $135,796 | Contract | : Capital Improvement and Maintenance Thinning Services; cut trees, thin brush species for fire hazard reduction | Agriculture, Department of / Forest Service | 12/17/2009 |
TRINIDAD A. ESCARENO | $75,538 | Contract | : SHASTA LAKE LADDER FUELS REDUCTION | Agriculture, Department of / Forest Service | 2/04/2010 |
QMAX CO | $25,184 | Contract | : HULL CABIN SITE REHABILITATION | Agriculture, Department of / Forest Service | 6/24/2010 |
LIGHTHOUSE FOR THE BLIND, THE | $24,901 | Contract | : Provide tree marking paint to the Forest Service in support of their activities. This includes procuring raw material, packaging the paint and preparing for shipment. This activity takes only a few hours to complete. | Agriculture, Department of / Forest Service | 7/13/2010 |
EUREKA DEVELOPMENT, LLC | $70,379 | Contract | : Culvert replacement | Agriculture, Department of / Forest Service | 8/28/2009 |
NORTHWEST TRAILS, INC. | $121,738 | Contract | : Bull Prarie Lake Trail Improvement. Improve 1 mile trail around lake for sustainability and accessibility | Agriculture, Department of / Forest Service | 5/27/2010 |
IDAHO FOREST GROUP LLC | $1,051,310 | Contract | : To reduce hazardous fuels on 577 acres in the Payette National Forest; Reduce erosion through road decommissioning on 17.4 miles; contribute to woody biomass utilization by removing slash from National Forest lands. | Agriculture, Department of / Forest Service | 4/12/2010 |