Listing all stimulus spending by amount, in descending order. Return to U.S. Coast Guard page
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Type | Description | Federal Dept./Agency | Date |
---|---|---|---|---|---|
TECHNICAL MARINE SERVICE, INC. | $114,319 | Contract | : Boiler Controls Installation and Testing, Installation Report, and Crew Training | Homeland Security, Department of / U.S. Coast Guard | 9/29/2009 |
TECHNICAL MARINE SERVICE, INC. | $104,227 | Contract | : Boiler Controls Installation and Testing, Installation Report, and Crew Training | Homeland Security, Department of / U.S. Coast Guard | 9/29/2009 |
BERGERSON CONSTRUCTION INC | $2,850,320 | Contract | : Construction New Dual Covered Moorings USCG Station Neah Bay, Washington | Homeland Security, Department of / U.S. Coast Guard | 9/30/2009 |
MCCLURE AND SONS INC. | $2,527,382 | Contract | : Award of design build construction of new covered moorings. | Homeland Security, Department of / U.S. Coast Guard | 9/30/2009 |
BNSF RAILWAY COMPANY | $36,445,756 | Contract | : Note that this is not a federal award contract, grant, or loan; thus the above reporting information section is not applicable to this report. The recovery funds reported herein are reimbursement of the federal share of the expenses accrued by Burlington | Homeland Security, Department of / U.S. Coast Guard | 7/23/2009 |
TECHNICAL MARINE SERVICE, INC. | $100,866 | Contract | : Boiler Controls Installation and Testing, Installation Report, and Crew Training | Homeland Security, Department of / U.S. Coast Guard | 9/29/2009 |
BAILEY REFRIGERATION CO., INC. | $459,088 | Contract | : Type I Refrigeration Plant, Unit Cooler, Box | Homeland Security, Department of / U.S. Coast Guard | 4/08/2009 |
CLARK, NEXSEN, OWEN, BARBIERI & GIBSON, P. C. | $69,994 | Contract | : Phase I archaeological survey plus additional suvey and testing of the right-of-way for an underground waterline that will be installed on Colonial National Historical Park (CNHP) property and the Coast Guard Training Center (TRACEN) in Yorktown, VA. | Homeland Security, Department of / U.S. Coast Guard | 8/18/2009 |
TECHNICAL MARINE SERVICE, INC. | $114,319 | Contract | : Boiler Controls Installation and Testing, Installation Report, and Crew Training | Homeland Security, Department of / U.S. Coast Guard | 9/29/2009 |
TECHNICAL MARINE SERVICE, INC. | $98,657 | Contract | : Boiler Controls Installation and Testing, Installation Report, and Crew Training | Homeland Security, Department of / U.S. Coast Guard | 9/29/2009 |
CSX TRANSPORTATION, INC. | $14,614,808 | Contract | : Reporting represents 100% of all project labor and cost. 100% reporting is at the direction of the Mortimer Shea, Chief, General Law USGC. CSX will continue to report 100% regardless of $$ allocation until the General Counsel's office directs us not to r | Homeland Security, Department of / U.S. Coast Guard | 8/20/2009 |
BETHEL SERVICES, INCORPORATED | $7,076,578 | Contract | : Provide playground structure, including all associated utilities, playground equipment, and composite play structures; Arbor, including access walkway, pavers, and benches; and Relocated Swing Set, including concrete curb and accessible resilient surfacin | Homeland Security, Department of / U.S. Coast Guard | 5/22/2009 |
DOVER FLUID MANAGEMENT, INC. | $170,218 | Contract | : 500 GPM Auxiliary Seawater Pump Assembly | Homeland Security, Department of / U.S. Coast Guard | 12/04/2009 |
ALFA LAVAL INC. | $130,164 | Contract | : Lube Oil Purification System for 378' WHEC class Coast Guard Cutters | Homeland Security, Department of / U.S. Coast Guard | 10/30/2009 |
ECH ARCHITECTURE PS | $156,402 | Contract | : Provide LEED Analysis and Mechanical Engineering Services for Design Build RFP preparation for North Bend ENG/ASM Building | Homeland Security, Department of / U.S. Coast Guard | 10/08/2009 |
CANADIAN NATIONAL RAILWAY COMPANY | $30,037,955 | Contract | : Note that this is not a federally awarded contract, grant, or loan; thus the above reporting information section is not applicable to this report. The recovery funds reported herein are reimbursement of the federal share of the expenses accrued by Canadia | Homeland Security, Department of / U.S. Coast Guard | 9/21/2009 |
GALVESTON, COUNTY OF | $60,901,481 | Contract | : Note that this is not a federal award contract, grant, or loan; thus the above reporting information section is not applicable to this report. The recovery funds reported herein are reimbursement of the federal share of the expenses accrued by the County | Homeland Security, Department of / U.S. Coast Guard | 5/05/2010 |
GALVESTON, COUNTY OF | $60,901,481 | Contract | : Note that this is not a federally awarded contract, grant, or loan; thus the above reporting information section is not applicable to this report. The recovery funds reported herein are a reimbursement of the federal share of the expenses accrued by Galv | Homeland Security, Department of / U.S. Coast Guard | 9/17/2009 |
NAUTICAL ENGINEERING, INC. | $362,428 | Contract | : TYPE III REEFER CONDENSING UNIT INSTALLATION - USCGC MORGENTHAU | Homeland Security, Department of / U.S. Coast Guard | 2/23/2010 |
NAUTICAL ENGINEERING, INC. | $415,255 | Contract | : TYPE III REEFER CONDENSING UNIT INSTALLATION - USCGC MELLON | Homeland Security, Department of / U.S. Coast Guard | 2/23/2010 |
HILLER SYSTEMS INCORPORATED | $1,275,158 | Contract | : Installation of Fire Alarm Systems aboard six (6) 378' Class Cutter | Homeland Security, Department of / U.S. Coast Guard | 3/02/2010 |
FEDERAL MARINE AND DEFENSE SERVICES, LLC | $425,990 | Contract | : 378' Auxilary Sea Pump Replacement | Homeland Security, Department of / U.S. Coast Guard | 2/25/2010 |
NAUTICAL ENGINEERING, INC. | $315,632 | Contract | : TYPE III REEFER CONDENSING UNIT INSTALLATION - USCGC BOUTWELL | Homeland Security, Department of / U.S. Coast Guard | 2/23/2010 |
FEDERAL MARINE AND DEFENSE SERVICES, LLC | $153,229 | Contract | : Installation of Lube Oil Purifiers | Homeland Security, Department of / U.S. Coast Guard | 2/24/2010 |
NAUTICAL ENGINEERING, INC. | $341,645 | Contract | : TYPE III REEFER CONDENSING UNIT INSTALLATION - USCGC MIDGETT | Homeland Security, Department of / U.S. Coast Guard | 2/23/2010 |
NDI ENGINEERING COMPANY | $237,441 | Contract | : Direct Project Management and Engineering Technical Support Services to the HEC/MEC Branch, SFLC-011. | Homeland Security, Department of / U.S. Coast Guard | 2/24/2010 |
OREGON INTERNATIONAL PORT OF COOS BAY | $14,538 | Contract | : Temporary mooring and upgrade to dock being used with fencing and electrical of Coast Guard Vessels during the demolition and construction of the covered mooring project at Coast Guard Station Coos Bay, Oregon. Slip will relocate two 47' MBLs immediately | Homeland Security, Department of / U.S. Coast Guard | 10/01/2009 |
TAB CONSTRUCTION COMPANY, INC. | $4,096,973 | Contract | : Bulkhead sheet piling and concrete placement | Homeland Security, Department of / U.S. Coast Guard | 5/28/2010 |
BRATSLAVSKY CONSULTING ENGINEERS, INC. | $225,000 | Contract | : Inspection services at CGC Sycamore Cordova housing phase II | Homeland Security, Department of / U.S. Coast Guard | 4/23/2010 |
TETRA TECH TESORO, INC. | $5,658,131 | Contract | : Design and Construct New and Modified Existing Infrastructure for Homeporting New Fast Response Cutters (FRC) at U.S. Coast Guard Base Support Unit (BSU) Miami, Miami Beach, Florida. The scope of work includes, but is not limited to, modifications to exis | Homeland Security, Department of / U.S. Coast Guard | 5/28/2010 |
BRATSLAVSKY CONSULTING ENGINEERS, INC. | $140,000 | Contract | : Inspection services for Neah Bay covered mooring construction | Homeland Security, Department of / U.S. Coast Guard | 4/22/2010 |
VETERAN CONSTRUCTORS, INC. | $17,875,799 | Contract | : The scope of work includes, but is not limited to the design and construction of a three story barracks building and a separate galley building. | Homeland Security, Department of / U.S. Coast Guard | 8/30/2010 |
CRAWFORD CONSULTING SERVICES, INC | $326,114 | Contract | : The scope of work includes full time construction inspection services for the Design/Build to replace Thrun Hall Barracks & Galley | Homeland Security, Department of / U.S. Coast Guard | 8/26/2010 |
CRAWFORD CONSULTING SERVICES, INC | $324,658 | Contract | : The scope of work includes Construction Inspection Services for the Upgrade of the Water Distribution System at USCG TRACEN in Yorktown, VA | Homeland Security, Department of / U.S. Coast Guard | 7/26/2010 |
TECHNICAL MARINE SERVICE, INC. | $158,107 | Contract | : Boiler Controls Installation and testing, Installation Report, Crew Training | Homeland Security, Department of / U.S. Coast Guard | 4/22/2010 |
CAMPBELL CONSTRUCTION GROUP, LLC | $2,531,617 | Contract | : Housing Repairs @ SFO Southwest Harbor (various units) Southwest Harbor, ME (USCG). Award includes 4 change orders approved. Increased award amount by $66,822.00 | Homeland Security, Department of / U.S. Coast Guard | 8/26/2010 |
CRAWFORD CONSULTING SERVICES, INC | $241,555 | Contract | : The scope of work includes full time construction inspection services during construction of the USCG Station Eaton's Neck Rebuild Boathouse Project | Homeland Security, Department of / U.S. Coast Guard | 8/31/2010 |
CRAWFORD CONSULTING SERVICES, INC | $203,910 | Contract | : The scope of work includes Inspection Services for Homeporting New Fast Response Cutters (FRC) at the USCG BSU, Miami, FL | Homeland Security, Department of / U.S. Coast Guard | 7/26/2010 |
WARD'S MARINE ELECTRIC, INC. | $3,353,885 | Contract | : Replace Automatic Bus Transfer switches on 10 U.S. Coast Guard 378' LRE Cutters | Homeland Security, Department of / U.S. Coast Guard | 4/20/2010 |
ADIRA CONSTRUCTION, INC. | $4,333,821 | Contract | : Design and construction upgrade water distribution system, On Base Phase 1, U.S. Coast Guard Training Center, Yorktown, Va. | Homeland Security, Department of / U.S. Coast Guard | 7/20/2010 |
TTEC-TESORO JOINT VENTURE | $1,175,052 | Contract | : Design and construction for the upgrade of the water distribution system Off Base at the USCG Training Center, Yorktown, VA. The scope of work includes, but is not limited to, installation of two new 12' potable waterlines. | Homeland Security, Department of / U.S. Coast Guard | 8/05/2010 |
HASKELL COMPANY, THE | $8,008,529 | Contract | : The scope of work includes, but is not limited to, design and construction of a new boat maintenance facility and optional item for the construction of a new boat ramp as shown on the RFP drawings and specifications. | Homeland Security, Department of / U.S. Coast Guard | 9/07/2010 |
TTEC-TESORO JOINT VENTURE | $7,700,210 | Contract | : Renovate/relocate Paint Complex (including Electrical Power Upgrades) at USCG Yard, Baltimore, MD. The scope of work includes providing all labor, material, equipment, transportation and supervision necessary to complete the renovation and relocation of t | Homeland Security, Department of / U.S. Coast Guard | 9/14/2010 |
CARDNO TEC, INC. | $8,371,206 | Contract | : Installation/Reading of Meters throughout United States Coast Guard Units | Homeland Security, Department of / U.S. Coast Guard | 9/24/2010 |
JKT/PCL, A TRIBAL JOINT VENTURE | $6,890,669 | Contract | : Award of design build construction of new Engineering?AST building | Homeland Security, Department of / U.S. Coast Guard | 8/30/2010 |
BRATSLAVSKY CONSULTING ENGINEERS, INC. | $67,860 | Contract | : Inspection services during construction of the new covered moorings in Coos Bay | Homeland Security, Department of / U.S. Coast Guard | 8/13/2010 |
JKT/PCL, A TRIBAL JOINT VENTURE | $7,137,850 | Contract | : Design-Build contract for new ENG-AST Building | Homeland Security, Department of / U.S. Coast Guard | 8/30/2010 |
CONTECH ENGINEERING, INC. | $3,663,183 | Contract | : Award of Construction of New PAR Complex and Paint Booth | Homeland Security, Department of / U.S. Coast Guard | 9/15/2010 |
BRATSLAVSKY CONSULTING ENGINEERS, INC. | $262,964 | Contract | : Inspection services during construction of new engineering building in North Bend, Oregon. | Homeland Security, Department of / U.S. Coast Guard | 8/25/2010 |
WARD'S MARINE ELECTRIC, INC. | $3,327,056 | Contract | : Replace Automatic Bus Transfer switches on 10 U.S. Coast Guard 378' LRE Cutters | Homeland Security, Department of / U.S. Coast Guard | 4/20/2010 |
ANIXTER, INC | $1,510 | Contract | : PURCHASE OF SUPPLIES - COMMERCIAL OFF THE SHELF (COTS) | Homeland Security, Department of / U.S. Coast Guard | 9/14/2010 |
BETHEL SERVICES, INCORPORATED | $3,636,923 | Contract | : Paving Roads, laying utilities (water & sewer) and environmental testing of soil. | Homeland Security, Department of / U.S. Coast Guard | 8/30/2010 |
CMS COMMUNICATIONS INC. | $32,550 | Contract | : TELEPHONES AND TELEPHONE EQUIPMENT FOR THEIR PHONE SYSTEM | Homeland Security, Department of / U.S. Coast Guard | 1/05/2011 |
TECHNICAL MARINE SERVICE, INC. | $109,092 | Contract | : Boiler Controls Installation and testing, Installation Report, and Crew Training | Homeland Security, Department of / U.S. Coast Guard | 9/29/2009 |