Contract: FERMI RESEARCH ALLIANCE, LLC
Primary Recipient
FERMI RESEARCH ALLIANCE, LLC
Amount
$25,000,000.00
Award Date
5/15/2009
Administering Agency
Energy, Department of / Office of Science
CDFA Number
CDFA Program Title
Description
WAS Number: KA/CH14/9/ARRA-1 Fermilab GPP Augmentation - This funding will be used to reduce the backlog of GPP projects at Fermi National Accelerator Laboratory (Fermilab). The funding would allow six highest priority projects to be done. The priority
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
FERMI RESEARCH ALLIANCE, LLC | Primary recipient | $4,585,323.67 |
BARTON MALOW COMPANY | Sub-recipient | $3,805,795.00 |
PANDECON, INC. | Sub-recipient | $3,613,419.01 |
R. C. WEGMAN CONSTRUCTION CO. | Sub-recipient | $3,527,657.00 |
A J Maggio Co | Sub-recipient | $3,238,273.00 |
ZONATHERM PRODUCTS, INC. | Sub-recipient | $762,689.00 |
PANDECON, INC. | Sub-recipient | $697,404.00 |
HORCHER CONSTRUCTION, INC. | Sub-recipient | $538,852.00 |
PANDECON, INC. | Sub-recipient | $526,913.00 |
PATTEN INDUSTRIES, INC. | Sub-recipient | $414,402.00 |
ZONATHERM PRODUCTS, INC. | Sub-recipient | $339,625.00 |
HANSON PROFESSIONAL SERVICES INC. | Sub-recipient | $205,970.00 |
CRAWFORD, MURPHY & TILLY, INC. | Sub-recipient | $190,000.00 |
STUDIO GC, INC. | Sub-recipient | $153,644.00 |
WARD COMMERCIAL CONSTRUCTION INC | Sub-recipient | $145,830.00 |
CRAWFORD, MURPHY & TILLY, INC. | Sub-recipient | $144,700.00 |
STEELCASE INC. | Sub-recipient | $142,627.78 |
PATTEN INDUSTRIES, INC. | Sub-recipient | $137,430.00 |
SUPERIOR CRANE CORP. | Sub-recipient | $137,243.00 |
EQUITY CONSTRUCTION SERVICE INC | Sub-recipient | $124,500.00 |
STUDIO GC, INC. | Sub-recipient | $119,700.00 |
CRAWFORD, MURPHY & TILLY, INC. | Sub-recipient | $109,100.00 |
CORDOGAN, CLARK & ASSOCIATES | Sub-recipient | $102,000.00 |
MGM TRANSFORMER CO. | Sub-recipient | $101,936.00 |
MGM TRANSFORMER CO. | Sub-recipient | $99,600.00 |
CORDOGAN, CLARK & ASSOCIATES | Sub-recipient | $94,000.00 |
STUDIO GC, INC. | Sub-recipient | $85,549.00 |
PANDECON, INC. | Sub-recipient | $66,181.00 |
HANSON PROFESSIONAL SERVICES INC. | Sub-recipient | $65,000.00 |
EQUITY CONSTRUCTION SERVICE INC | Sub-recipient | $63,398.00 |
STUDIO GC, INC. | Sub-recipient | $57,551.00 |
GRAYBAR ELECTRIC COMPANY, INC. | Sub-recipient | $54,222.00 |
PRIMERA ENGINEERS, LTD. | Sub-recipient | $50,789.96 |
CONSOLIDATED ELECTRICAL DISTRIBUTORS, INC. | Sub-recipient | $49,799.00 |
CRAWFORD, MURPHY & TILLY, INC. | Sub-recipient | $44,600.00 |
DEARBORN CRANE AND ENGINEERING COMPANY | Sub-recipient | $43,050.00 |
KEILHAUER | Sub-recipient | $42,925.22 |
UUSCO OF ILLINOIS, INC. | Sub-recipient | $42,452.25 |
GRAYBAR ELECTRIC COMPANY, INC | Sub-recipient | $38,256.92 |
BURNS & MCDONNELL ENGINEERING COMPANY, INC. | Sub-recipient | $36,432.00 |
UTILITY CONCRETE PRODUCTS, L.L.C. | Sub-recipient | $35,835.00 |
ARLINGTON ELECTRICAL CONSTRUCTION CO INC | Sub-recipient | $31,674.39 |
GRAYBAR ELECTRIC COMPANY, INC | Sub-recipient | $30,100.00 |
CORDOGAN, CLARK & ASSOCIATES | Sub-recipient | $26,950.80 |
CORDOGAN, CLARK & ASSOCIATES | Sub-recipient | $26,000.00 |
GIBSON ELECTRIC CO., INC. | Sub-recipient | $25,600.00 |
PRIMERA ENGINEERS, LTD. | Sub-recipient | $25,000.00 |