Contract: EDCO CONTRACTORS, INC.
Primary Recipient
EDCO CONTRACTORS, INC.
Amount
$241,076.00
Award Date
9/02/2009
Administering Agency
CDFA Number
CDFA Program Title
Description
Replace boilers in building 1064. Work to include demo of one steam sectional boiler, including all piping, piping insulation, and piper supports. Provide and install two seam Cleaver Brooks boilers. A modification was entered given to remove 2 existin
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
M & M WELDING & FABRICATORS, INC. | Sub-recipient | $186,180.00 |
EDCO CONTRACTORS, INC. | Primary recipient | $35,861.00 |
JOHNSON CONTROLS INTERIORS L.L.C. | Sub-recipient | $12,400.00 |
OVERHEAD DOOR COMPANY OF BALTIMORE THE, INC | Sub-recipient | $4,335.00 |
MC QUITTY CONSTRUCTION, INC. | Sub-recipient | $2,300.00 |