Contract: BETTER BUILT CONSTRUCTION SERVICES INC
Primary Recipient
BETTER BUILT CONSTRUCTION SERVICES INC
Amount
$446,984.12
Award Date
6/03/2009
Administering Agency
CDFA Number
CDFA Program Title
Description
The project consists of furnishing all plant, labor, material and equipment and performing all work necessary to disconnect and dispose off one badly damaged transformer, disconnect and deliver to Building 2453 the second transformer (less damaged) at Sub
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
AREA UTILITIES INC | Sub-recipient | $385,000.00 |
BETTER BUILT CONSTRUCTION SERVICES INC | Primary recipient | $61,984.12 |