Contract: MAPCO, INC.
Primary Recipient
MAPCO, INC.
Amount
$29,305.27
Award Date
4/30/2009
Administering Agency
CDFA Number
CDFA Program Title
Description
Remove and replace stack cap on boiler # 2 with larger diameter. Replace tie down cables and hardware on 4 boiler stacks above the roof. Remove 2 each existing motor driven and 2 each non motor driven exhaust fans on the roof and replace with new motor dr
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
SKE INTERNATIONAL INC | Sub-recipient | $24,185.00 |
MAPCO, INC. | Primary recipient | $5,120.27 |