Grant: CLEMSON UNIVERSITY
Primary Recipient
CLEMSON UNIVERSITY
Amount
$43,165,502.00
Award Date
12/30/2009
Administering Agency
CDFA Number
81.087
CDFA Program Title
Renewable Energy Research and Development
Description
Clemson University proposes to engineer, construct and operate a Wind Turbine Drivetrain Test Facility (CU WTDTF) for highly accelerated testing of drivetrains for wind turbines up to 15MW with a 30% overload capacity. The primary team on the project incl
Vendors Connected to Award
Vendor | Role | Amount |
---|---|---|
RENK Labeco Test Systems Corp. | Primary vendor | $2,730,980.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $5,071,820.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $1,300,000.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $700,000.00 |
Fluor Enterprises, Inc | Primary vendor | $70,568.84 |
Fluor Enterprises, Inc | Primary vendor | $124,340.32 |
Fluor Enterprises, Inc | Primary vendor | $154,794.78 |
Fluor Enterprises, Inc | Primary vendor | $153,379.30 |
RENK Labeco Test Systems Corp. | Primary vendor | $204,823.50 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $380,386.50 |
Fluor Enterprises, Inc | Primary vendor | $155,260.54 |
Fluor Enterprises, Inc | Primary vendor | $61,641.66 |
RENK Labeco Test Systems Corp. | Primary vendor | $8,533,780.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $285,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $591,295.00 |
AEC Engineering, Inc. | Primary vendor | $101,050.48 |
AEC Engineering, Inc. | Primary vendor | $124,974.00 |
AEC Engineering, Inc. | Primary vendor | $277,496.73 |
AEC Engineering, Inc. | Primary vendor | $287,597.99 |
National Instruments | Primary vendor | $35,384.18 |
National Instruments | Primary vendor | $121,746.73 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $500,000.00 |
AEC Engineering, Inc. | Primary vendor | $318,568.73 |
AEC Engineering, Inc. | Primary vendor | $319,507.22 |
Choate Construction Company | Primary vendor | $1,273,089.66 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
AEC Engineering, Inc. | Primary vendor | $269,016.76 |
National Instruments | Primary vendor | $27,930.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
AEC Engineering, Inc. | Primary vendor | $198,811.55 |
AEC Engineering, Inc. | Primary vendor | $163,912.30 |
AEC Engineering, Inc. | Primary vendor | $133,226.22 |
Choate Construction Company | Primary vendor | $362,200.05 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
RENK Labeco Test Systems Corp. | Primary vendor | $585,210.00 |
Choate Construction Company | Primary vendor | $1,085,950.75 |
Choate Construction Company | Primary vendor | $838,763.48 |
AEC Engineering, Inc. | Primary vendor | $97,504.55 |
AEC Engineering, Inc. | Primary vendor | $295,673.70 |
Orbis, Inc. | Primary vendor | $132,880.00 |