Contract: GARLAND COMPANY INC, THE
Primary Recipient
GARLAND COMPANY INC, THE
Amount
$518,253.00
Award Date
11/30/2009
Administering Agency
General Services Administration / Public Buildings Service
CDFA Number
CDFA Program Title
Description
A. Contractor shall implement a tear off of the existing built-up roof system and all associated components down to the top surface of existing polyurethane roof insulation. The insulation system shall be set into solid mopping of Type III hot asphalt ove
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
Berwald Roofing | Sub-recipient | $344,200.00 |
GARLAND COMPANY INC, THE | Primary recipient | $174,053.00 |