Contract: MK ENGINEERS, LTD.

Primary Recipient

MK ENGINEERS, LTD.

Amount

$118,724.00

Award Date

8/25/2009

Administering Agency

Army, Department of / U.S. Army Corps of Engineers, except civil program financing

CDFA Number

CDFA Program Title

Description

As a part of design on project FY09 Install Generator Set Schofield Barracks Pump House 4 and FY09 Install Generator Set Schofield Barracks Pump House 3, Wheeler Army Airfield, East Range and Wahiawa, Oahu, Hawaii, MK Engineers, Ltd. prepared the design b

Recipients Connected to Award

Recipient Role Amount
MK ENGINEERS, LTD. Primary recipient $27,824.00
THERMAL ENGINEERING CORPORATION Sub-recipient $22,069.00
FUKUNAGA & ASSOCIATES, INC. Sub-recipient $12,816.00
ARCHITECTS PACIFIC, INC. Sub-recipient $12,714.00
MASA FUJIOKA & ASSOCIATES Sub-recipient $12,418.00
COST ENGINEERING OF HAWAII INC Sub-recipient $10,762.00
CONTROLPOINT SURVEYING, INC. Sub-recipient $7,592.00
SSFM INTERNATIONAL, INC Sub-recipient $5,784.00
Ebisu & Associates Sub-recipient $4,383.00
HIRATA & ASSOCIATES INC Sub-recipient $2,362.00