Contract: EDCO CONTRACTORS, INC.
Primary Recipient
EDCO CONTRACTORS, INC.
Amount
$333,514.16
Award Date
12/16/2009
Administering Agency
CDFA Number
CDFA Program Title
Description
Replace exterior steam lines in several building. A modification was awarded to change steam piping for entire project from schedule 40 to schedule 80 and to provide temporary heat fro E1572 while shutdown. A second modification was awarded to provide n
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
T & M CONSTRUCTION, INC. | Sub-recipient | $312,357.95 |
EDCO CONTRACTORS, INC. | Primary recipient | $21,156.21 |