Contract: GRANITE CONSTRUCTION COMPANY
Primary Recipient
GRANITE CONSTRUCTION COMPANY
Amount
$6,526,000.00
Award Date
2/03/2010
Administering Agency
Transportation, Department of / Federal Highway Administration
CDFA Number
CDFA Program Title
Description
The Wawona Road project consists of pulverizing and overlaying 24.4 miles of Wawona Road (Highway 41) through Yosemite National Park. The scope of work includes pulverizing 8 of existing road and overlaying the pulverized materials with 4.5 of asphalt co
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
GRANITE CONSTRUCTION COMPANY | Primary recipient | $2,305,354.00 |
John R. Lawson Rock & Oil, Inc. | Sub-recipient | $1,264,100.00 |
FORCE TRAFFIC CONTROL INC | Sub-recipient | $1,030,028.00 |
Gary Brown Electric, Inc. | Sub-recipient | $906,777.00 |
DRAGON MATERIAL TRANSPORT INC | Sub-recipient | $332,500.00 |
HYDROTECH, INC. | Sub-recipient | $290,630.00 |
Fonseca McElroy Grinding Co Inc | Sub-recipient | $213,468.00 |
STERNDAHL ENTERPRISES, INC. | Sub-recipient | $60,721.00 |
Performance Energy, Inc. | Sub-recipient | $45,750.00 |
DON BERRY CONSTRUCTION, INC. | Sub-recipient | $32,608.00 |
N P C CONSTRUCTION INC | Sub-recipient | $21,000.00 |
PAVEMENT RECYCLING SYSTEMS, INC. | Sub-recipient | $14,460.00 |
CASH & LINCOLN FENCE CO | Sub-recipient | $8,604.00 |