Contract: GRANITE CONSTRUCTION COMPANY

Primary Recipient

GRANITE CONSTRUCTION COMPANY

Amount

$6,526,000.00

Award Date

2/03/2010

Administering Agency

Transportation, Department of / Federal Highway Administration

CDFA Number

CDFA Program Title

Description

The Wawona Road project consists of pulverizing and overlaying 24.4 miles of Wawona Road (Highway 41) through Yosemite National Park. The scope of work includes pulverizing 8 of existing road and overlaying the pulverized materials with 4.5 of asphalt co

Recipients Connected to Award

Recipient Role Amount
GRANITE CONSTRUCTION COMPANY Primary recipient $2,305,354.00
John R. Lawson Rock & Oil, Inc. Sub-recipient $1,264,100.00
FORCE TRAFFIC CONTROL INC Sub-recipient $1,030,028.00
Gary Brown Electric, Inc. Sub-recipient $906,777.00
DRAGON MATERIAL TRANSPORT INC Sub-recipient $332,500.00
HYDROTECH, INC. Sub-recipient $290,630.00
Fonseca McElroy Grinding Co Inc Sub-recipient $213,468.00
STERNDAHL ENTERPRISES, INC. Sub-recipient $60,721.00
Performance Energy, Inc. Sub-recipient $45,750.00
DON BERRY CONSTRUCTION, INC. Sub-recipient $32,608.00
N P C CONSTRUCTION INC Sub-recipient $21,000.00
PAVEMENT RECYCLING SYSTEMS, INC. Sub-recipient $14,460.00
CASH & LINCOLN FENCE CO Sub-recipient $8,604.00