Contract: PACE BUILDING CORPORATION
Primary Recipient
PACE BUILDING CORPORATION
Amount
$1,313,000.00
Award Date
3/29/2010
Administering Agency
Department of Veterans Affairs
CDFA Number
CDFA Program Title
Description
Project calls removal and replacement of ten (10) existing air handler units at the Kerrville, Texas VA Hospital. Work involves: selective demolition, mechanical (HVAC), fire protection and electrical work, etc.
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
R.E.C. INDUSTRIES, INC. | Sub-recipient | $934,029.00 |
PACE BUILDING CORPORATION | Primary recipient | $278,508.00 |
Eldridge Electric Company of Beaumont, Inc. | Sub-recipient | $90,500.00 |
American Automatic Sprinkler, Inc. | Sub-recipient | $9,963.00 |