Contract: M. A. MORTENSON COMPANY
Primary Recipient
M. A. MORTENSON COMPANY
Amount
$3,074,743.00
Award Date
3/23/2010
Administering Agency
General Services Administration / Public Buildings Service
CDFA Number
CDFA Program Title
Description
The work covered by this contract was awarded to our company on March 23, 2010. The first phase work scope included only Construction Manager as Constructor Preconstruction services for the Tenant Improvement in the existing Federal Office Building locat
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
M. A. MORTENSON COMPANY | Primary recipient | $1,250,399.00 |
ALBERS MECHANICAL CONTRACTORS, INC | Sub-recipient | $459,800.00 |
Elliott Contracting Corporation | Sub-recipient | $447,830.00 |
Stern Drywall Inc | Sub-recipient | $292,838.00 |
Nasseff Mechanical Contractors | Sub-recipient | $172,000.00 |
Walmarc Partners Corporation | Sub-recipient | $79,818.00 |
Paul's Architectural Woodcraft Co. | Sub-recipient | $77,850.00 |
ABSOLUTE COMMERCIAL FLOORING INC | Sub-recipient | $63,584.00 |
KENDELL DOORS & HARDWARE, INC. | Sub-recipient | $50,960.00 |
Kirk Acoustics, Inc | Sub-recipient | $49,905.00 |
SWANSON & YOUNGDALE, INC | Sub-recipient | $37,956.00 |
CD Tile & Stone Inc | Sub-recipient | $34,850.00 |
U.S. Framers & Finishers, Inc. | Sub-recipient | $24,496.00 |
Brin Glass Company | Sub-recipient | $13,719.00 |
OFFISOURCE, INC. | Sub-recipient | $11,200.00 |
Bartley Sales Company, Inc. | Sub-recipient | $7,538.00 |