Contract: JIM COOLEY CONSTRUCTION, INC.
Primary Recipient
JIM COOLEY CONSTRUCTION, INC.
Amount
$5,632,481.03
Award Date
1/28/2010
Administering Agency
General Services Administration / Public Buildings Service
CDFA Number
CDFA Program Title
Description
HURRICANE IKE DAMAGE - REPAIR AND ALTERATIONS TO USPO/COURTHOUSE IN GALVESTON TX
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
Lakewood Mechanical Inc | Sub-recipient | $2,178,983.00 |
JIM COOLEY CONSTRUCTION, INC. | Primary recipient | $1,616,296.03 |
HOWELL ELECTRIC INC | Sub-recipient | $890,000.00 |
Millennium Glass and Mirrors Inc | Sub-recipient | $460,979.00 |
A & H Masonry | Sub-recipient | $113,230.00 |
CFI MECHANICAL, INC. | Sub-recipient | $100,000.00 |
HAZARD ASSESSMENT LEADERS INC | Sub-recipient | $47,300.00 |
Leslie Plumbing & Sales Inc | Sub-recipient | $43,891.00 |
Stucco All Purpose Plastering | Sub-recipient | $43,861.00 |
Empire Steel Erectors, L.P. | Sub-recipient | $33,464.00 |
Cross Plan, Inc. | Sub-recipient | $32,850.00 |
Mayco Building Systems Inc | Sub-recipient | $32,236.00 |
Brinkmann Investments, Inc. | Sub-recipient | $27,100.00 |
Ceilings, Inc | Sub-recipient | $8,791.00 |
T.A.S. Commercial Concrete Construction, LLC | Sub-recipient | $3,500.00 |