Contract: EATON CORPORATION
Primary Recipient
EATON CORPORATION
Amount
$1,659,067.06
Award Date
6/30/2010
Administering Agency
U.S. Army Corps of Engineers / U.S. Army Corps of Engineers - civil program financing only
CDFA Number
CDFA Program Title
Description
TAS 96 3134, Construction, Recovery Act, P2# 105566, OSD# 6400, Purchase Order Number W9128F-10-P-0071 for Garrison Major Rehabilitation Station Service Switchgear and Dry Transformer, Garrison Power Plant, Riverdale, North Dakota
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
EATON CORPORATION | Primary recipient | $1,422,187.06 |
ABB Inc. | Sub-recipient | $236,880.00 |