Contract: JOHN J. KIRLIN SPECIAL PROJECTS, LLC
Primary Recipient
JOHN J. KIRLIN SPECIAL PROJECTS, LLC
Amount
$7,418,936.93
Award Date
7/30/2010
Administering Agency
Army, Department of / U.S. Army Corps of Engineers, except civil program financing
CDFA Number
CDFA Program Title
Description
ARRA Funds for Work Plan & Construction/Repair for revision in preparation for the Redesign location for Temporary Transition Space for Orthopedics and Podiatry Clinic, Dwight D. Eisenhower Army Medical Clinic, Ft. Gordon, GA.
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
JOHN J. KIRLIN SPECIAL PROJECTS, LLC | Primary recipient | $2,080,045.93 |
TYLER CONSTRUCTION GROUP, INC. | Sub-recipient | $1,614,060.00 |
ICON CONSTRUCTION, INC. | Sub-recipient | $1,179,790.00 |
GOLD MECH, INC. | Sub-recipient | $896,160.00 |
MILLER ELECTRIC COMPANY | Sub-recipient | $870,385.00 |
AMI GROUP, INC. | Sub-recipient | $516,221.00 |
CENTURY FIRE PROTECTION, LLC | Sub-recipient | $180,710.00 |
ROSS & BARUZZINI, INC. | Sub-recipient | $63,445.00 |
Bmh Engineering LLC | Sub-recipient | $18,120.00 |