Recovery Tracker

How Much Stimulus Funding is Going to Your County?

Monterey County, Calif., funds by Army, Department of

Listing $10,095,776.55 in stimulus funds from Army, Department of for Monterey

Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.

Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.

Recipient Amount Description Federal Dept./Agency Date
ENVIRONMENTAL ASSESSMENT AND REMEDIATION MANAGEMENT, INC. $2,858,798 Construction of two new Visitor Centers and two new Search offices at the Bolio Gate, Franklin Gate,High Street and Taylor Street respectively U.S. Army Corps of Engineers, except civil program financing 9/27/2009
Fresno Plumbing & Heating Inc. $675,754 Replace Barracks Toilets - various Army, Department of 7/13/2010
J & J MAINTENANCE, INC. $592,760 The purpose of this task order is to provide a Type III Work Plan, the construction of a 600 sq ft expansion to, and repairs to modernize the utilities and medical functions of building 4390 at Ft Ord, CA.
This spending item is part of a $2,101,613 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 11/30/2009
ONSITE CONSTRUCTION & ENGINEERING, INC. $516,028 Replace Windows in Barracks @ Bldg #622 in Presidio of Monterey, CA. U.S. Army Corps of Engineers, except civil program financing 8/23/2009
Grant Construction, Inc. $376,251 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
COLLINS ELECTRICAL COMPANY, INC. $341,114 The purpose of this task order is to provide a Type III Work Plan, the construction of a 600 sq ft expansion to, and repairs to modernize the utilities and medical functions of building 4390 at Ft Ord, CA.
This spending item is part of a $2,101,613 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 11/30/2009
RED MOUNTAIN LLC $281,712 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
WILSON, GEO H INC $281,623 Replace Failing HVAC Systems, Barracks Buildings 647, 650, 651.
This spending item is part of a $315,256 allocation. See details
Army, Department of 8/20/2009
GOSTANIAN GENERAL BUILDING CORP $260,396 Remove asbestos containing material and replace floor covering in Building 652 barracks at Presidio of Monterey, CA Army, Department of 9/03/2009
GOSTANIAN GENERAL BUILDING CORP $260,396 Remove asbestos containing material and replace floor covering in Building 651 barracks at Presidio of Monterey, CA Army, Department of 9/03/2009
GOSTANIAN GENERAL BUILDING CORP $260,396 Replace Carpet, Barracks 652 U.S. Army Corps of Engineers, except civil program financing 9/03/2009
GOSTANIAN GENERAL BUILDING CORP $260,396 Replace Floor Covering, Building 651 U.S. Army Corps of Engineers, except civil program financing 9/03/2009
GRANITE CONSTRUCTION COMPANY $223,223 Repair Unsafe/Failed Access Roads and Paved Areas, C Company, 9th Signal Command.
This spending item is part of a $311,107 allocation. See details
Army, Department of 8/21/2009
BLACK BULL CONSTRUCTION INC. $221,126 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
BRANNON INC $216,070 Remove Inactive Communication Lines Base Wide.
This spending item is part of a $333,382 allocation. See details
Army, Department of 7/15/2009
STOLLMEYER ENGINEERING, INC. $200,867 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
MONTEREY, CITY OF $147,738 Replace Deterriorating and Leaking Water Lines Servicing DLI Classrooms. Army, Department of 8/21/2009
Estrella Associates, Inc. $126,133 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
WEBCO $124,423 AS A PART OF OPERATION AND MAINTENANCE, ARMY, RECOVERY ACT, THIS CONTRACT PROVIDES FOR ASBESTOS MITIGATION AND ABATEMENT AT THE PRESIDIO OF MONTEREY. PROJECT #38508; LOCATION: MONTEREY, CA. ASBESTOS MITIGATE AND ABATEMENT, PRESIDIO OF MONTEREY CALIFORNI
This spending item is part of a $281,234 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/24/2009
MONTEREY, CITY OF $117,312 Remove Inactive Communication Lines Base Wide.
This spending item is part of a $333,382 allocation. See details
Army, Department of 7/15/2009
COLLINS ELECTRICAL COMPANY, INC. $115,124 Install/Modernize Exterior Lighting for Barracks Areas, 800 and 600 Series.
This spending item is part of a $157,879 allocation. See details
Army, Department of 8/21/2009
Walter G Beck III $114,471 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
MONTEREY, CITY OF $96,909 Replace Failing Water Laterals Supporting Classroom Buildings 209-218. Army, Department of 8/21/2009
Homer T. Hayward Lumber Co. $96,733 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
MONTEREY, CITY OF $91,141 Repair Natural Gas Systems. Army, Department of 8/21/2009
Central Valley Exteriors $90,330 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
MONTEREY, CITY OF $87,884 Repair Unsafe/Failed Access Roads and Paved Areas, C Company, 9th Signal Command.
This spending item is part of a $311,107 allocation. See details
Army, Department of 8/21/2009
C B C Roofing Inc $86,450 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
RMP SAFETY SERVICES $76,324 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Trombley Painting Co $75,710 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
SC Dunn Drywall $68,364 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
TROFHOLZ TECHNOLOGIES, INC. $61,480 Install Turnstile at Taylor Gate, Presidio of Monterey U.S. Army Corps of Engineers, except civil program financing 9/15/2009
Henry Schmitz Plumbing $59,301 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
MONTEREY, CITY OF $58,937 Replace Failing HVAC System CPAC Building 277. Army, Department of 8/20/2009
MONTEREY, CITY OF $55,802 Install Fire Sprinkler Heads, DLI Classrooms, Building 611. Army, Department of 8/20/2009
James Sommerville Inc $52,836 Construct Sidewalk to Access DLI Cloassrooms, Health and Safety.
This spending item is part of a $85,448 allocation. See details
Army, Department of 8/20/2009
MONTEREY, CITY OF $42,755 Install/Modernize Exterior Lighting for Barracks Areas, 800 and 600 Series.
This spending item is part of a $157,879 allocation. See details
Army, Department of 8/21/2009
Templeton Floor Company, Inc. $38,850 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
MONTEREY, CITY OF $33,633 Replace Failing HVAC Systems, Barracks Buildings 647, 650, 651.
This spending item is part of a $315,256 allocation. See details
Army, Department of 8/20/2009
MONTEREY, CITY OF $32,613 Construct Sidewalk to Access DLI Cloassrooms, Health and Safety.
This spending item is part of a $85,448 allocation. See details
Army, Department of 8/20/2009
MTM ENGINEERING & CONTRACTING SERVICES, INC. $31,041 AS A PART OF OPERATION AND MAINTENANCE, ARMY, RECOVERY ACT, THIS CONTRACT PROVIDES FOR ASBESTOS MITIGATION AND ABATEMENT AT THE PRESIDIO OF MONTEREY. PROJECT #38508; LOCATION: MONTEREY, CA. ASBESTOS MITIGATE AND ABATEMENT, PRESIDIO OF MONTEREY CALIFORNI
This spending item is part of a $281,234 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/24/2009
FENCE FACTORY $28,292 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
GOSTANIAN GENERAL BUILDING CORP $27,555 Repair Deteriorated Floor, Cuilding 630 U.S. Army Corps of Engineers, except civil program financing 8/31/2009
A Plus Fire Protection $25,250 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
M3 ENVIRONMENTAL CONSULTING $24,145 AS A PART OF OPERATION AND MAINTENANCE, ARMY, RECOVERY ACT, THIS CONTRACT PROVIDES FOR ASBESTOS MITIGATION AND ABATEMENT AT THE PRESIDIO OF MONTEREY. PROJECT #38508; LOCATION: MONTEREY, CA. ASBESTOS MITIGATE AND ABATEMENT, PRESIDIO OF MONTEREY CALIFORNI
This spending item is part of a $281,234 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/24/2009
Gsi Soils Inc $22,866 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Landscape Development, Inc. $22,845 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Western Insulation, Inc. $18,977 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
3C ENGINEERING, INC. $16,090 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
WALLACE GROUP $13,956 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
WEBCO $12,730 INSTALL SAFETY COMPONENTS IN COMMUNICATIONS CLOSETS: EMERGENCY LIGHTING, EMERGENY SHUT OFF SWITCHES, FIRE SUPPRESSION AND TEMPERATURE CONTROLS AT PRESIDIO OF MONTEREY, CA
This spending item is part of a $67,085 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/15/2009
GRIFFIN CARPETS INC $8,473 AS A PART OF OPERATION AND MAINTENANCE, ARMY, RECOVERY ACT, THIS CONTRACT PROVIDES FOR ASBESTOS MITIGATION AND ABATEMENT AT THE PRESIDIO OF MONTEREY. PROJECT #38508; LOCATION: MONTEREY, CA. ASBESTOS MITIGATE AND ABATEMENT, PRESIDIO OF MONTEREY CALIFORNI
This spending item is part of a $281,234 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/24/2009
FERGUSON ENTERPRISES, INC. $8,098 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Hamon Overhead Door Company, Inc. $7,530 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Contemporary Home Services $6,950 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Pestmaster Svcs $5,994 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Mike Roach Electric Inc $5,165 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Design Genre International $5,050 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
CENTRAL COAST CCD LLC $4,921 AS A PART OF OPERATION AND MAINTENANCE, ARMY, RECOVERY ACT, THIS CONTRACT PROVIDES FOR ASBESTOS MITIGATION AND ABATEMENT AT THE PRESIDIO OF MONTEREY. PROJECT #38508; LOCATION: MONTEREY, CA. ASBESTOS MITIGATE AND ABATEMENT, PRESIDIO OF MONTEREY CALIFORNI
This spending item is part of a $281,234 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/24/2009
MTM ENGINEERING & CONTRACTING SERVICES, INC. $4,256 INSTALL SAFETY COMPONENTS IN COMMUNICATIONS CLOSETS: EMERGENCY LIGHTING, EMERGENY SHUT OFF SWITCHES, FIRE SUPPRESSION AND TEMPERATURE CONTROLS AT PRESIDIO OF MONTEREY, CA
This spending item is part of a $67,085 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/15/2009
ATLAS PERFORMANCE INDUSTRIES, INC. $4,164 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
WEBCO $3,630 REPAIR CORRODED EXTERNAL SURFACES BLDG 84 @ PRESIDIO OF MONTEREY
This spending item is part of a $24,666 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/15/2009
FERGUSON ENTERPRISES, INC. $2,902 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Fence Factory A California Corporation $2,293 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Pacific Coast Fireplaces, Inc $1,499 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
MTM ENGINEERING & CONTRACTING SERVICES, INC. $1,130 REPAIR CORRODED EXTERNAL SURFACES BLDG 84 @ PRESIDIO OF MONTEREY
This spending item is part of a $24,666 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/15/2009
Fence Factory A California Corporation $816 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
Fence Factory A California Corporation $484 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
FERGUSON ENTERPRISES, INC. $213 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
FERGUSON ENTERPRISES, INC. $195 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
FERGUSON ENTERPRISES, INC. $105 Design and construction of a single structure and all necessary work for a total of Four (4) 4 BR / 2B JNCO (Junior Non-Commissioned Officer) housing units and a single structure for a Garrison Commanders Residence on Governmentowned land at Ft Hunter Lig
This spending item is part of a $2,404,432 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/30/2009
MONTEREY, CITY OF $0 Replace Barracks Toilets - various
This spending item is part of a $545,656 allocation. See details
Army, Department of 7/13/2010