Recovery Tracker

How Much Stimulus Funding is Going to Your County?

Prince George's County, Md., funds by Army, Department of

Listing $18,183,823.98 in stimulus funds from Army, Department of for Prince George's

Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.

Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.

Recipient Amount Description Federal Dept./Agency Date
AB CONSTRUCTION INC $2,580,000 replace Bridge Army, Department of 9/15/2009
WELCH AND RUSHE, INC. $1,802,000 Replace old, inefficient 12th Street steam line by adding new energy efficient boilers in several buildings now being served by the old line.
This spending item is part of a $3,161,540 allocation. See details
Army, Department of 8/27/2009
CORINTHIAN CONTRACTORS INC. $1,629,687 RECOVERYPROJECT#::AJF69112::RP# The project consists of the site work and preparation, landscaping, asphalting and construction of the 100 space S. Parking Lot and Stormwater Management Pond on the Air National Guard Readiness Center Headquarters campus a Army, Department of 5/28/2010
CLARK CONSTRUCTION GROUP, LLC $1,176,455 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
LIMBACH COMPANY LLC $1,144,000 Renovation and Rehabilitation of Historical Building 257(JAG Headquarters).
This spending item is part of a $2,847,724 allocation. See details
Army, Department of 1/21/2010
Mona Electric Group, Inc. $974,520 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
MCCLONE CONSTRUCTION COMPANY $912,497 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
JCM ASSOCIATES, INC. $864,297 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
ISEC, INCORPORATED $853,186 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
AIR IDEAL, INC. $540,593 Repair and Replace the HTHW System at the Adelphi Lab. Army, Department of 12/30/2009
ICON EXTERIOR BUILDING SOLUTIONS, LP $481,413 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
A. C. Dellovade, Inc. $457,249 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
CH2M HILL, INC. $449,952 Construction Mangement and Administrative Services Army, Department of 7/30/2009
AB CONSTRUCTION INC $398,052 Bridge Repairs Army, Department of 9/17/2009
CLEVELAND CONSTRUCTION, INC $338,536 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
BERKEL & COMPANY CONTRACTORS, INC. $306,700 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
MCA CONSTRUCTION, INC. $280,964 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009
CONTRACTING SPECIALISTS INCORPORATED-DC $268,000 Replace concrete decking and other repairs at the Floral Drive Bridge, Adelphi, MD Army, Department of 3/26/2010
AIW, INC. $263,368 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
CAPITAL ROOFING INC $235,800 Remove and dispose of existing modified bitumen roof, roof insulation, light weight concrete taper. Remove all vented or non vented base sheets from the structural deck. Remove all existing parapet coping metal and flashing. M.B. roof from penthouse, alo
This spending item is part of a $272,916 allocation. See details
Army, Department of 8/03/2009
DESBUILD INCORPORATED $215,958 Demo of floor, painting, flooring, mill work,plumbing, remove & install new copper gutters and downspouts, remove & install copper flat-seam roof, reapir slate roof and remove additional VCT and install the new VCT.
This spending item is part of a $870,000 allocation. See details
Army, Department of 1/07/2010
UNIVERSITY OF MARYLAND $200,000 A Hot Water and Gas-Fired Membrane-Based Absorption Chiller. The contractor shall develop and demonstrate a membrane-based integrated absorber / evaporator for lithium bromide absorption chiller applications.
This spending item is part of a $1,500,000 allocation. See details
Army, Department of 1/21/2010
DJB CONTRACTING, INCORPORATED $152,000 Demo of floor, painting, flooring, mill work,plumbing, remove & install new copper gutters and downspouts, remove & install copper flat-seam roof, reapir slate roof and remove additional VCT and install the new VCT.
This spending item is part of a $870,000 allocation. See details
Army, Department of 1/07/2010
PROSPECT WATERPROOFING COMPANY $151,018 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
PHOENIX FIRE PROTECTION, INC. $150,000 Renovation and Rehabilitation of Historical Building 257(JAG Headquarters).
This spending item is part of a $2,847,724 allocation. See details
Army, Department of 1/21/2010
UNIVERSITY OF MARYLAND $146,070 SBIR II: Light Weight ARU
This spending item is part of a $746,213 allocation. See details
Army, Department of 8/03/2010
DAVID ALLEN COMPANY, INCORPORATED $133,157 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
DELAWARE ELEVATOR, INC. $129,000 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009
AVITECTURE, INC. $95,880 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
NFP GROUP, INC. $89,500 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
LAKOTA CONTRACTING, INC $87,725 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
Calvert Masonry, Inc. $81,600 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
AMERICAN AMPLIFIER & TELEVISION INC $52,236 Providing all plant, labor, material, equipment and transportation necessary to perform facility maintenance, alterations, repair and minor construction work in the Aberdeen and Edgewood areas of Aberdeen Proving Ground as well as various satellite off-po
This spending item is part of a $1,696,088 allocation. See details
Army, Department of 3/03/2010
Independent Fire Protection Inc $50,420 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009
SPARKLE PAINTING CO., INC. $50,000 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
Deming Enterprises, Inc. $47,200 Contractor shall provide all management, labor, materials, and equipment to repair the failing BURS roofing system IAW the attached specifications and contractors proposal. Contractor shall provide a written progress schedule with milestones for each cat
This spending item is part of a $1,715,257 allocation. See details
Army, Department of 8/06/2009
POWER SOLUTIONS, LLC $42,144 The objective of this project is to remove Sissal wall covering in building 1425 at US Army Medical Research Institute of Infectious Diseases, Ft Detrick, MD. Building 1425 has over 100,000 square feet and height of over 30 feet. Work includes providing
This spending item is part of a $1,536,099 allocation. See details
U.S. Army Corps of Engineers, except civil program financing 9/28/2009
HILLIS CARNES ENGINEERING ASSOCIATES, INC $39,924 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
EAST COAST BUILDING SERVICES, INC $39,420 Contractor shall provide all management, labor, materials, and equipment to repair the failing BURS roofing system IAW the attached specifications and contractors proposal. Contractor shall provide a written progress schedule with milestones for each cat
This spending item is part of a $1,715,257 allocation. See details
Army, Department of 8/06/2009
RUGO STONE, L.L.C. $30,462 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
Quality Erectors, Inc. $26,490 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009
CFS SERVICE CORPORATION $25,600 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009
ANDERSON COMPANY, L.L.C., THE $25,000 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
CFS SERVICE CORPORATION $23,700 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009
B R T Masonry LLC $22,000 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009
GOVERNMENT SERVICES INTEGRATED PROCESS TEAM LLC $21,037 Modification 04 Revisions and clarifications to RTA documents for the Warriors in Transition Unit, Ft. Campbell, KY U.S. Army Corps of Engineers, except civil program financing 10/26/2009
CFS SERVICE CORPORATION $20,100 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009
BERGER/EA JV $19,966 Furnish all labor, material and delievery in accordance with the attached Statement of Work for Cemetery Investigation, Chapel 2, Building 3715, Andrews Air Force Base, Maryland. This investigation is being conducted in order to satisfy theresponsibilitie Army, Department of 5/14/2010
E A ENGINEERING $19,966 The purpose of this Delivery Order is to conduct archeological investigations at an approximately .5-acre parcel at the location of Building 3715 (Chapel 2) at Andrews Air Force Base, in Washington, D.C. This delievery order also required the preparation U.S. Army Corps of Engineers, except civil program financing 5/14/2010
PARTITION PLUS, INC. $9,780 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009
JAMES R. WALLS CONTRACTING COMPANY $8,046 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009
COLOR-AD INC $7,995 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
MARATHON CLEANING, INC. $5,500 RECOVERY-AJXF 069112-ANGRC OPERATIONS CENTER Firm fixed price for construction of the second component (MILCON) of the HQ complex which is a 2 story wing of about 20,000sf housing a conference center and support facilities. These components will flank a
This spending item is part of a $7,425,982 allocation. See details
Army, Department of 7/30/2009
American Synthetic Surfaces, Inc. $4,060 Repair Bldg 2116, Physical Fitness Center to include bathrooms, showers & lockers; heating ventilation and a/c; athletic court flooring; and interior finishes.
This spending item is part of a $418,570 allocation. See details
Army, Department of 1/01/2010
WOODBRIDGE GLASS COMPANY, INCORPORATED $3,600 Construct New Elev for Bldg 103; renovate Fitness Facility; Deluge Fire Protection System Upgrades Bldg107
This spending item is part of a $599,700 allocation. See details
Army, Department of 12/29/2009