Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
MASSACHUSETTS, COMMONWEALTH OF | $5,150,691 | Highway Planning and Construction BELCHERTOWN - WARE, RESURFACING AND RELATED WORK ON 2 SECTIONS OF ROUTE 9 The purpose of this project is to resurface portions of Route 9. Work will also include repairs/upgrades to guardrail end treatments as needed and new pavement markings. Belche | Federal Highway Administration | 4/02/2009 |
MASSACHUSETTS, COMMONWEALTH OF | $4,211,726 | Highway Planning and Construction EASTHAMPTON/NORTHAMPTON- MANHAN BIKE TRAIL CONSTRUCTION, FROM EASTHAMPTON LINK TO EARLE STREET This multi-use recreational rail trail project starts at Ferry Street in Easthampton and ends at Earle Street in Northampton, for a total length of 4,400 Me | Federal Highway Administration | 6/25/2009 |
MASSACHUSETTS, COMMONWEALTH OF | $3,891,211 | Highway Planning and Construction EASTHAMPTON - GREENFIELD - NORTHAMPTON- SOUTHAMPTON - WESTFIELD RESURFACING AND RELATED WORK ON ROUTES 10 AND 5 Project will consist of milling the existing paved surface of Route 5 and 10 and repaving with 2 of HMA modified top course material. Work | Federal Highway Administration | 4/02/2009 |
MASSACHUSETTS, COMMONWEALTH OF | $2,435,594 | Highway Planning and Construction Chesterfield - This project begins at the Westhampton Town Line and proceeds north-westerly for 3.08 miles to the intersection of South Street. The roadway currently exhibits potholes, alligator and block cracking, delaminating, raveling and rutting. Pro | Federal Highway Administration | 12/01/2009 |
MASSACHUSETTS, COMMONWEALTH OF | $1,846,293 | Highway Planning and Construction Amherst - Work under this project will consist of micromilling 1.5 from the existing paved surface and repaving with a 1.5 asphalt standard top course and a 0.75 paver placed friction course. Work will also include partial and full depth pavement repairs | Federal Highway Administration | 12/01/2009 |
MASSACHUSETTS, COMMONWEALTH OF | $1,210,451 | Highway Planning and Construction South Hadley - The project will resurface Route 47 (Hadley Street) in South Hadley from Ferry Street northerly to the Hadley Town Line. Work will include new pavement markings and the reconstruction of approximately 3,000 feet of asphalt sidewalk. | Federal Highway Administration | 12/01/2009 |
MASSACHUSETTS, COMMONWEALTH OF | $975,700 | Highway Planning and Construction HATFIELD- ELM STREET RECLAMATION AND RELATED WORK The project involves roadway and sidewalk rehabilitation on town-owned Elm Street in the Town of Hatfield, and includes cold planing, roadway reclamation, hot mix asphalt paving, replacement of sidewal | Federal Highway Administration | 6/01/2009 |
MASSACHUSETTS, COMMONWEALTH OF | $613,114 | Highway Planning and Construction NORTHAMPTON - JACKSON STREET SCHOOL SAFE ROUTES TO SCHOOL IMPROVEMENTS The purpose of this project is to improve access to the Jackson Street School by constructing new sidewalks, constructing a new access ramp to the nearby bike path, installing 4' c | Federal Highway Administration | 8/04/2009 |