Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
MARTEL CONSTRUCTION, INC. | $4,239,120 |
Design and construction of a new 146,000 square-feet federalcourthouse by the General Services Administration (GSA) in Billings, MT. The five-story courthouse is expected to be completed in late 2012.
This spending item is part of a $67,511,499 allocation.
See details
|
Public Buildings Service | 12/23/2009 |
Martin and Associates, Inc. | $3,066,261 |
Design and construction of a new 146,000 square-feet federalcourthouse by the General Services Administration (GSA) in Billings, MT. The five-story courthouse is expected to be completed in late 2012.
This spending item is part of a $67,511,499 allocation.
See details
|
Public Buildings Service | 12/23/2009 |
CENTURY COMPANIES, INC. | $1,320,509 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
F H G CONSTRUCTION LLC | $1,124,039 |
Design and construction of a new 146,000 square-feet federalcourthouse by the General Services Administration (GSA) in Billings, MT. The five-story courthouse is expected to be completed in late 2012.
This spending item is part of a $67,511,499 allocation.
See details
|
Public Buildings Service | 12/23/2009 |
THYSSENKRUPP ELEVATOR CORPORATION | $1,014,900 |
Design and construction of a new 146,000 square-feet federalcourthouse by the General Services Administration (GSA) in Billings, MT. The five-story courthouse is expected to be completed in late 2012.
This spending item is part of a $67,511,499 allocation.
See details
|
Public Buildings Service | 12/23/2009 |
PCL CONSTRUCTION SERVICES, INC | $883,915 | This project involves the design & construction of operating efficiency upgrades to the Bozeman, Montana Federal Building / Post Office. The notice to proceed (NTP) was provided on September 10, 2010 and the project is substantially complete. | Public Buildings Service | 8/25/2010 |
LIBERTY ELECTRIC, INC. | $813,539 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Central Plumbing | $637,764 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
LANGLAS & ASSOCIATES - BOZEMAN, INC. | $470,326 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Easton Concrete Inc | $387,484 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Montana Helical Piers | $232,162 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
WILLIAMSON FENCING INC | $213,483 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
DOWL, LLC | $210,536 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Doll's Glass Co. | $152,967 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
S & H ALUMINUM PRODUCTS, INC. | $131,142 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
ATS INLAND NW, LLC | $120,440 |
Energy Improvement Design/Build at Federal Building in Bozeman, MT
This spending item is part of a $126,320 allocation.
See details
|
Public Buildings Service | 3/02/2010 |
AMAZING PAINTING INC | $104,453 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
The Foam Depot | $80,865 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Bacon Signs, Inc | $74,834 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Set It LLC | $71,237 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Pierce's Flooring | $65,527 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Sylvan Nursery Inc | $64,870 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Advanced Fire Systems Inc | $55,558 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
ALLIED ENGINEERING SERVICES, INC. | $54,720 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Sheridan Electric Co-Op Inc | $52,845 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
CTA INC. | $48,529 | Other Architects & Engin gen-The contractor shall provide engineering and commissioning exp0ertise to conduct recommissioning/retro-commissioning planning, scoping, testing, investigation, evaluation, analysis, calculations, recommendations and report wri | Public Buildings Service | 7/08/2009 |
Associated Construction Engineering, Inc. | $33,680 |
We will provide construction management/project management for the Bozeman, Montana Federal Building. In this quarter, the project was supported by American Recovery and Reinvestment Act funds.
This spending item is part of a $49,087 allocation.
See details
|
Public Buildings Service | 3/29/2010 |
Le Cabinet Shoppe, Inc. | $29,236 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Heydon Overhead Door, Inc | $28,110 |
This project is for the design and construction of a new U.S. Land Port of Entry at Scobey, MT. The contract includes a new main port building, construction of roadways and parking, and construction of water, sewer, security, electrical, and telecommunica
This spending item is part of a $8,030,481 allocation.
See details
|
Public Buildings Service | 8/14/2009 |
Kath Williams Associates | $24,180 |
Construction Manager as Agent Services for the Design and construction of the U.S. Federal Courthouse Billings, Montana
This spending item is part of a $4,703,183 allocation.
See details
|
Public Buildings Service | 12/17/2009 |
ULTEIG ENGINEERS, INC. | $15,407 |
We will provide construction management/project management for the Bozeman, Montana Federal Building. In this quarter, the project was supported by American Recovery and Reinvestment Act funds.
This spending item is part of a $49,087 allocation.
See details
|
Public Buildings Service | 3/29/2010 |
Project Sheetmetal & Welding LLC | $8,000 |
Energy Improvement Design/Build at Federal Building in Bozeman, MT
This spending item is part of a $126,320 allocation.
See details
|
Public Buildings Service | 3/02/2010 |
BIGHORN CORPORATION | $1,550 |
Energy Improvement Design/Build at Federal Building in Bozeman, MT
This spending item is part of a $126,320 allocation.
See details
|
Public Buildings Service | 3/02/2010 |
MIDLAND MECHANICAL, INC. | $0 |
Energy Improvement Design/Build at Federal Building in Bozeman, MT
This spending item is part of a $126,320 allocation.
See details
|
Public Buildings Service | 3/02/2010 |