Kings County, N.Y., funds by General Services Administration
Listing $84,899,646.52 in stimulus funds from General Services Administration for Kings
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
NICHOLSON & GALLOWAY, INC | $45,424,178 |
Fa+?ade Repair and Slate Roof Replacement at the U.S. Post Office and Courthouse located at 271 Cadman Plaza East, Brooklyn, NY 11201
This spending item is part of a $61,746,842 allocation.
See details
|
Public Buildings Service | 7/27/2009 |
TURTLE ASSOCIATES LLC | $6,710,726 | This energy conservation and renewable energy conservation project is located in Brooklyn, NY. Along with the base contract, which includes a mechanical upgrade of removing old chillers and boilers and replacing with new, there will be work completed on | Public Buildings Service | 3/31/2010 |
LEND LEASE (US) CONSTRUCTION LMB INC | $5,597,985 |
The U.S. Post Office & Conrad B. Duberstein Bankruptcy Court. Brooklyn, NY. Exterior Restoration including Granite Restoration, Terra Cotta Replacement, Slate Roof Replacemenr and Window Refurbishment.
This spending item is part of a $8,047,237 allocation.
See details
|
Public Buildings Service | 7/15/2009 |
VOLMAR CONSTRUCTION INC. | $5,584,325 | Building renovation of half of the building at the Emanuel Celler US Courthouse. | Public Buildings Service | 5/28/2009 |
FEMENELLA & ASSOCIATES, INC. | $3,939,467 |
Fa+?ade Repair and Slate Roof Replacement at the U.S. Post Office and Courthouse located at 271 Cadman Plaza East, Brooklyn, NY 11201
This spending item is part of a $61,746,842 allocation.
See details
|
Public Buildings Service | 7/27/2009 |
Pace Plumbing Corp. | $3,518,297 |
The Thurgood Marshall Courthouse infrastructure upgrade.
This spending item is part of a $64,000,000 allocation.
See details
|
Public Buildings Service | 4/15/2009 |
AMERICON, INC. | $2,607,474 |
ARRA - Design-Build Tune Up (Mechanical & Electrical System Revisions). Provide Design-Build services to implement energy conservation measures at the Theodore Roosevelt U.S. Courthouse, Brooklyn, NY that were identified in the retro-commissioning report
This spending item is part of a $3,626,636 allocation.
See details
|
Public Buildings Service | 5/27/2010 |
GOODY, CLANCY & ASSOCIATES, INC. | $2,110,795 |
Architecture and engineering professional services for the Facade Repair & Slate Roof Replacement of the US Post Office and Courthouse at 271 Cadman Plaza, East, Brooklyn, New York. Specific services include the design services for upgrades to exiting si
This spending item is part of a $2,480,116 allocation.
See details
|
Public Buildings Service | 6/08/2009 |
Superstructures Engineering + Architecture, Pllc | $1,864,575 |
The U.S. Post Office & Conrad B. Duberstein Bankruptcy Court. Brooklyn, NY. Exterior Restoration including Granite Restoration, Terra Cotta Replacement, Slate Roof Replacemenr and Window Refurbishment.
This spending item is part of a $8,047,237 allocation.
See details
|
Public Buildings Service | 7/15/2009 |
BOVIS LEND LEASE LMB, INC. | $1,804,010 | Provide program management activities including professional, technical, administrative and clerical support to the General Services Administration (GSA) Project Team's management of and the successful completion of the Modernization of the Emanuel Celler | Public Buildings Service | 5/19/2009 |
IRON EAGLE ENVIRONMENTAL SERVICES | $1,125,000 |
Fa+?ade Repair and Slate Roof Replacement at the U.S. Post Office and Courthouse located at 271 Cadman Plaza East, Brooklyn, NY 11201
This spending item is part of a $61,746,842 allocation.
See details
|
Public Buildings Service | 7/27/2009 |
MCDONOUGH BOLYARD PECK, INC. | $532,972 | The Conrad B. Duberstein U.S. Bankruptcy Courthouse is a historic structure located in the Civic Center of the Borough of Brooklyn, New York. It is a good example of Romanesque Revival architecture, it is a local historical Landmark in the City of New Yor | Public Buildings Service | 12/31/2009 |
Relogistics Inc | $377,010 |
Fa+?ade Repair and Slate Roof Replacement at the U.S. Post Office and Courthouse located at 271 Cadman Plaza East, Brooklyn, NY 11201
This spending item is part of a $61,746,842 allocation.
See details
|
Public Buildings Service | 7/27/2009 |
Cole Consulting Corp. | $363,670 |
The U.S. Post Office & Conrad B. Duberstein Bankruptcy Court. Brooklyn, NY. Exterior Restoration including Granite Restoration, Terra Cotta Replacement, Slate Roof Replacemenr and Window Refurbishment.
This spending item is part of a $8,047,237 allocation.
See details
|
Public Buildings Service | 7/15/2009 |
GOSHOW ARCHITECTS, L.L.P. | $335,196 |
Analyze and confirm specific energy conservation and renewable energy generation features to be included in the Conrad B. Duberstein U.S. Bankruptcy Courthouse, Brooklyn, New York
This spending item is part of a $917,352 allocation.
See details
|
Public Buildings Service | 11/17/2009 |
MDC ELECTRICAL CONTRACTOR LLC | $325,600 |
ARRA - Design-Build Tune Up (Mechanical & Electrical System Revisions). Provide Design-Build services to implement energy conservation measures at the Theodore Roosevelt U.S. Courthouse, Brooklyn, NY that were identified in the retro-commissioning report
This spending item is part of a $3,626,636 allocation.
See details
|
Public Buildings Service | 5/27/2010 |
GRUZEN SAMTON ARCHITECTS PLANNERS & INTERIOR DESIGNERS LLP | $311,556 |
Continuing construction administration services for the renovation of Emanuel Celler Courthouse. **Although the stimulus money received did not provide full time employment for the job descriptions listed under Description of Jobs Created, it did provide
This spending item is part of a $765,756 allocation.
See details
|
Public Buildings Service | 5/20/2009 |
BANC 3, INC. | $311,553 | Construction Management support services for the Electrical and Mechanical Upgrade to the Alfonso M. D'Amato US Court House and Federal Building | Public Buildings Service | 3/31/2010 |
HATCH MOTT MACDONALD NY INC. | $261,102 |
ARRA - Design-Build Tune Up (Mechanical & Electrical System Revisions). Provide Design-Build services to implement energy conservation measures at the Theodore Roosevelt U.S. Courthouse, Brooklyn, NY that were identified in the retro-commissioning report
This spending item is part of a $3,626,636 allocation.
See details
|
Public Buildings Service | 5/27/2010 |
MIDCITY ELECTRICAL CORP | $221,600 |
Fa+?ade Repair and Slate Roof Replacement at the U.S. Post Office and Courthouse located at 271 Cadman Plaza East, Brooklyn, NY 11201
This spending item is part of a $61,746,842 allocation.
See details
|
Public Buildings Service | 7/27/2009 |
ROBERT SILMAN ASSOCIATES, P.C. | $206,873 |
Architecture and engineering professional services for the Facade Repair & Slate Roof Replacement of the US Post Office and Courthouse at 271 Cadman Plaza, East, Brooklyn, New York. Specific services include the design services for upgrades to exiting si
This spending item is part of a $2,480,116 allocation.
See details
|
Public Buildings Service | 6/08/2009 |
BROOKS RANGE CONTRACT SERVICES, INC. | $199,950 | Brooks Range will provide GSA with not to exceed 900 hours of overtime engineers hours at the Dubertstein Courthouse, Brooklyn NY in support of energy project. Engineers shall escort and monitor construction contractors, expidite shut downs for tie-ins, | Public Buildings Service | 9/14/2010 |
KATCHADOURIAN, NINA | $145,000 | Development of a public art work for the Van Buren, ME border station. Have spent total of $850 total related to site to Van Buren, ME. | Public Buildings Service | 6/04/2010 |
Able Rigging Contractors, Inc | $138,140 |
ARRA - Design-Build Tune Up (Mechanical & Electrical System Revisions). Provide Design-Build services to implement energy conservation measures at the Theodore Roosevelt U.S. Courthouse, Brooklyn, NY that were identified in the retro-commissioning report
This spending item is part of a $3,626,636 allocation.
See details
|
Public Buildings Service | 5/27/2010 |
ARCHITECTURAL TESTING, INC. | $120,500 |
The U.S. Post Office & Conrad B. Duberstein Bankruptcy Court. Brooklyn, NY. Exterior Restoration including Granite Restoration, Terra Cotta Replacement, Slate Roof Replacemenr and Window Refurbishment.
This spending item is part of a $8,047,237 allocation.
See details
|
Public Buildings Service | 7/15/2009 |
BURLEW MECHANICAL LLC | $96,900 |
ARRA - Design-Build Tune Up (Mechanical & Electrical System Revisions). Provide Design-Build services to implement energy conservation measures at the Theodore Roosevelt U.S. Courthouse, Brooklyn, NY that were identified in the retro-commissioning report
This spending item is part of a $3,626,636 allocation.
See details
|
Public Buildings Service | 5/27/2010 |
ADT Security Services, Inc. | $95,587 |
Fa+?ade Repair and Slate Roof Replacement at the U.S. Post Office and Courthouse located at 271 Cadman Plaza East, Brooklyn, NY 11201
This spending item is part of a $61,746,842 allocation.
See details
|
Public Buildings Service | 7/27/2009 |
Taylor Family Trust | $79,000 |
Provide temporary chiller (chiller on a truck) to be parked on Tillary Street and piped into the Duberstein Courthouse Brooklyn NY. Modification 01 entended Chiller requirement to 5/24/2011 for an additional $34,100.00
This spending item is part of a $132,193 allocation.
See details
|
Public Buildings Service | 4/06/2011 |
ENVIRONMENTAL PLANNING & MANAGEMENT, INC. | $76,507 |
The U.S. Post Office & Conrad B. Duberstein Bankruptcy Court. Brooklyn, NY. Exterior Restoration including Granite Restoration, Terra Cotta Replacement, Slate Roof Replacemenr and Window Refurbishment.
This spending item is part of a $8,047,237 allocation.
See details
|
Public Buildings Service | 7/15/2009 |
VERTICAL ACCESS, LLC | $63,298 |
Architecture and engineering professional services for the Facade Repair & Slate Roof Replacement of the US Post Office and Courthouse at 271 Cadman Plaza, East, Brooklyn, New York. Specific services include the design services for upgrades to exiting si
This spending item is part of a $2,480,116 allocation.
See details
|
Public Buildings Service | 6/08/2009 |
JACOBS TECHNOLOGY INC. | $59,463 | The scope of this project is to design and implement opportunities to provide cost efficient solutions, or Energy Conservation Measures (ECMs), to reduce energy consumption at the Roosevelt US Courthouse. Jacobs responsibilities in support of these effort | Public Buildings Service | 9/30/2010 |
BROOKS RANGE CONTRACT SERVICES, INC. | $53,193 |
Provide temporary chiller (chiller on a truck) to be parked on Tillary Street and piped into the Duberstein Courthouse Brooklyn NY. Modification 01 entended Chiller requirement to 5/24/2011 for an additional $34,100.00
This spending item is part of a $132,193 allocation.
See details
|
Public Buildings Service | 4/06/2011 |
Beasley, Chin & Hunderman PC | $38,750 |
Architecture and engineering professional services for the Facade Repair & Slate Roof Replacement of the US Post Office and Courthouse at 271 Cadman Plaza, East, Brooklyn, New York. Specific services include the design services for upgrades to exiting si
This spending item is part of a $2,480,116 allocation.
See details
|
Public Buildings Service | 6/08/2009 |
Viridian Energy & Environmental, LLC | $31,062 |
Architecture and engineering professional services for the Facade Repair & Slate Roof Replacement of the US Post Office and Courthouse at 271 Cadman Plaza, East, Brooklyn, New York. Specific services include the design services for upgrades to exiting si
This spending item is part of a $2,480,116 allocation.
See details
|
Public Buildings Service | 6/08/2009 |
BANC 3, INC. | $29,600 | Provide Construction Management services for the Re-Commissioning of the Theodore Roosevelt US Courthouse and Federal Building One Year after Implementation | Public Buildings Service | 9/23/2010 |
JABLONSKI BUILDING CONSERVATION, INC. | $29,338 |
Architecture and engineering professional services for the Facade Repair & Slate Roof Replacement of the US Post Office and Courthouse at 271 Cadman Plaza, East, Brooklyn, New York. Specific services include the design services for upgrades to exiting si
This spending item is part of a $2,480,116 allocation.
See details
|
Public Buildings Service | 6/08/2009 |
Nasco Heating & Air Conditoning Inc | $29,000 |
ARRA - Design-Build Tune Up (Mechanical & Electrical System Revisions). Provide Design-Build services to implement energy conservation measures at the Theodore Roosevelt U.S. Courthouse, Brooklyn, NY that were identified in the retro-commissioning report
This spending item is part of a $3,626,636 allocation.
See details
|
Public Buildings Service | 5/27/2010 |
WISS, JANNEY, ELSTNER ASSOCIATES, INC. | $24,000 |
The U.S. Post Office & Conrad B. Duberstein Bankruptcy Court. Brooklyn, NY. Exterior Restoration including Granite Restoration, Terra Cotta Replacement, Slate Roof Replacemenr and Window Refurbishment.
This spending item is part of a $8,047,237 allocation.
See details
|
Public Buildings Service | 7/15/2009 |
Riehm Corporation | $20,000 |
Fa+?ade Repair and Slate Roof Replacement at the U.S. Post Office and Courthouse located at 271 Cadman Plaza East, Brooklyn, NY 11201
This spending item is part of a $61,746,842 allocation.
See details
|
Public Buildings Service | 7/27/2009 |
BROOKS RANGE CONTRACT SERVICES, INC. | $19,984 | Provide project support services (escort, equipment shutdowns, tie in of mechanical, fire alarm equipment) to 225 Cadman Plaza,Brooklyn, NY | Public Buildings Service | 2/28/2011 |
BROOKS RANGE CONTRACT SERVICES, INC. | $16,409 | Commisioning work at both Duberstien & Roosevelt Couthouses | Public Buildings Service | 12/09/2009 |