Recovery Tracker

How Much Stimulus Funding is Going to Your County?

Grant County, Ore., funds by Agriculture, Department of

Listing $15,834,773.20 in stimulus funds from Agriculture, Department of for Grant

Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.

Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.

Recipient Amount Description Federal Dept./Agency Date
OCHOCO LUMBER COMPANY $4,890,000 Recovery Act of 2009: Wildland Fire Management Award Title: ARRA - Wood Fuel Pellet Facility in Grant and Harney Counties, Oregon Development of a compressed wood fuel facility within the boundaries of Grant and Harney Counties, Oregon, including design, permitting and installation of equipment. The... Show more
This spending item is part of a $5,000,000 allocation. See details
Forest Service 9/18/2009
MULTIPLE RECIPIENTS $686,128 Very Low to Moderate Income Housing Loans - Direct SECTION 502 SINGLE FAMILY HSNG DIRECT LN - 2009 ARRA Rural Housing Service 3/31/2009
O'RORKE LOGGING INC $663,996 This job is a biomass project. We fell smaller trees to be skidded and loaded onto log trucks and hauled to mills in Elgin and Pilot Rock. We hand cut some smaller biomass and piled it. Also hired a sub contractor to cut along 2 roads and chip small brush Forest Service 12/22/2009
HIGH DESERT AGGREGATE & PAVING, INC. $521,968 FSR 3618 & 3620 subgrade stabilization and paving of 2.1 miles of road. Project begins at the North end near Magone Lake campground. Work will consist of excavating material and constructing embankments. Project consists of pulverizing the Bituminous Surf Forest Service 6/21/2010
MULTIPLE RECIPIENTS $488,772 Very Low to Moderate Income Housing Loans - Guaranteed Single Family Housing Guaranteed Loans - ARRA Rural Housing Service 8/31/2009
A A A THUNDERDERBOLT FIRE SERVICE INC $426,614 Canyon Fuels Reduction treatment by tree thinning & hand piling, Blue Mt. Ranger District, Projects 3, 4 & 5 Forest Service 5/07/2010
PROFESSIONAL HEATING & COOLING INC $420,750 Installation of Energy Efficient heating, ventialtion, and air conditioning systems in 28 locations for Malhuer National Forest. All labor, materials, supplies, and equiptment required to perform this award is included. Forest Service 7/13/2010
WHITE SHIELD, INC. $420,012 Lead based paint abatement and painting project at Mahleur National Forest Building Sites Forest Service 7/02/2010
WATTERSON LOGGING $381,346 County Road 18 Biomass removal. Malheur National Forest.To improve forest health and to lower fuel levels to reduce risk of catastrophic fire's. Forest Service 6/30/2010
IRON TRIANGLE LLC $373,971 The end result of this contract is that trees are thinned to the desired spacing or basal area and less than 5 tons per acre of fuel loading remains on the treatment unit. All useable fuel material shall be cut, processed/bunched or bucked, and removed on Forest Service 6/30/2010
ENGLE CONTRACTING, LLC $369,228 Biomass Removal Forest Service 12/22/2009
KRIEGE LOGGING LLC $369,109 MALHEUR STEWARTSHIP COLABERATED TASK ORDER 7, RD 1. LOGGING UNIT PER CONTRACT. CUTTING TREES, SKIDDING TREES TO LANDING, DELIMBING TREES, LOADING LOGS ONTO TRUCKS AND HAULING LOGS TO MILL. Forest Service 6/30/2010
WINEGAR EXCAVATING INC $307,844 Minor constructed features and accessibility upgrades on the Malheur National Forest Campgrounds are being upgraded to include american disabilities act accessable picnic tables, firerings,fencing,gravel and blading of campgrounds Forest Service 5/27/2010
MOUNT SAINT HELENS REFORESTATION INC $299,584 Eagle Roost Thin/Hand Pile/Burn--tree branch pickup by hand Forest Service 2/10/2010
Oak Hill Roofing & Sheet Metal Services LLC $294,548 Roof Replacements Forest Wide, Malheur National Forest
This spending item is part of a $340,942 allocation. See details
Forest Service 6/02/2010
GRAYBACK FORESTRY, INC. $258,091 Idaho Cr. Plantation thinning and hand piling of trees that need to be cut to improve growth Forest Service 6/02/2010
HARNEY ROCK & PAVING CO. $247,976 This project consists of applying a chip seal to Forest Road 17 which is 11.13 miles long and is a double lane road with an existing asphalt paved surface 28' wide. Forest Service 6/03/2010
GAHLSDORF LOGGING, INC $211,288 Knox Biomass Removal Stewardship Contract Forest Service 12/22/2009
LANE CONTRACTORS, INC. $175,635 Installation of Energy-Efficient windows Forest Service 6/24/2010
HIGH DESERT AGGREGATE & PAVING, INC. $173,243 Project 2 consists of applying a single layer asphalt surface treatment (chip seal)to a 6.40 mile long segment of Forest Road 15, which is a double lane road with an existing asphalt paved surface 24 feet wide. Project 3 consists of applying a single laye Forest Service 6/03/2010
GAHLSDORF LOGGING INC. $168,677 Thinning and removal of BioMass Materials.
This spending item is part of a $224,253 allocation. See details
Forest Service 12/22/2009
CUTTING EDGE FORESTRY, INC. $164,710 CANYON FUELS REDUCTION PROJECT 2; BLUE MOUNTAIN RANGER DISTRICT-PRECOMMERCIAL THINNING, HAND PILING SLASH, AND BURNING OF SLASH PILES ON THE MALHUER N.F. Forest Service 5/07/2010
GRAYBACK FORESTRY, INC. $164,165 Thin and treat slash on Malheur NF by cutting trees and piling the cut trees into piles Forest Service 2/16/2010
GRAYBACK FORESTRY, INC. $159,848 Canyon Fuels Reduction, Poject #1 cutting down trees and brush no one wants, piling it into piles and burning it with diesel, gas and matches. Forest Service 5/07/2010
IRON TRIANGLE LLC $158,228 All fuel material shall be cut, processed/bunched or bucked, and removed on all treatment units so that remainging non-usable fuel loads are less than 5-10 tons per acre, excluding material left as wildlife logs. Fuel material shall be transported with a Forest Service 12/09/2009
GRAYBACK FORESTRY, INC. $157,340 thinning and hand pile Malheur NF Forest Service 12/18/2009
BACKLUND LOGGING CO $150,100 Hand slash piling on the Knox timber sale and FR16 of the Prairie City Ranger District of the Malheur National Forest Forest Service 8/23/2010
IRON TRIANGLE LLC $149,255 Project includes, but is not limited to reconstructing an existing parking lot and boat ramp, removing an existing vault toilet, installing a new vault toilet, constructing a simulated face concrete retaining wall, constructing a new AOA trail from the pa Forest Service 7/29/2010
BACKLUND LOGGING CO $145,950 Delivery order for 417 acres of handpiling over 12 miles along Grant County Road #18 Forest Service 9/09/2010
MILLER TIMBER SERVICES INC $144,658 Cutting down trees and hauling to milling facilities as well as roadside brushing
This spending item is part of a $288,585 allocation. See details
Forest Service 12/22/2009
GRAYBACK FORESTRY, INC. $138,395 Thinning and hand piling on the Malheur NF of trees and brush by cutting down with chainsaws to improve tree growth and reduce fire hazard Forest Service 9/10/2010
EASTERN OREGON ENVIRONMENTAL RECOVERY LLC $134,722 Install new potable water systems in three forest Service Guard Station in Eastern Oregon. Forest Service 6/20/2010
MOORE & HUECKMAN $128,868 thinning and grapple piling and burning of 2 units Forest Service 2/16/2010
HANSEN, MARK $108,018 1059 ACRES OF GRAPPLE PILLING CUT THINNING SLASH Forest Service 9/29/2009
3B'S FORESTRY, INCORPORATED $100,614 Precommercial Thinning: Pre-commercial thinning is performed before trees reach merchantable size, which is typically around 4.5 to 8 inches dbh (diameter at breast height, measured at 4.5 ft. above the ground). The objective of a pre-commercial thinning Forest Service 12/04/2009
Oak Hill Roofing & Sheet Metal Services LLC $97,340 Fire Lookout Catwalk Replacement, Roof Replacement, Floor Replacement - Malheur National Forest
This spending item is part of a $104,592 allocation. See details
Forest Service 8/31/2010
POWER PRO INC $97,174 Communications Project to install new upgraded phone lines. Forest Service 6/23/2010
A A A THUNDERDERBOLT FIRE SERVICE INC $96,494 Prairie City Ranger District Thin and Treat - Project #1 Forest Service 2/05/2010
WINSTON CORPORATION $87,000 Painting of Historical Builings in Mahleur National Forest Forest Service 6/14/2010
POWER PRO INC $84,650 SUPPLY AND INSTALL AN ABOVE GROUND FUEL TANKS AT CROW FLAR GUARD STATION AND BLUE MOUNTAIN WORK CENTER. INSTALLATION INCLUDES, BUT IS NOT LIMITED TO, POURING A CONCRETE SLAB, INSTALL BOLLARDS, CONNECTING TO A POWER SOURCE. Forest Service 3/25/2010
L D PERRY INC $84,208 Recovery-Solar water system upgrades at Big Creek and Yellow Jacket campgrounds, John Day, OR. Forest Service 6/07/2010
WAGGONER, RONALD W. $79,875 Silvies Biomass/Gold Removal. The projected volume was more than the volume that was actually removed. Therefore the amount of award reflects the decrease. Forest Service 12/09/2009
BROWNING CONTRACTING, LLC $74,055 Prairie City Ranger District Thin & Treat Forest Service 2/16/2010
IRON TRIANGLE LLC $72,877 Biomass removal Forest Service 12/09/2009
3B'S FORESTRY, INCORPORATED $72,450 Precommercial Thinning Pre-commercial thinning is performed before trees reach merchantable size, which is typically around 4.5 to 8 inches dbh (diameter at breast height, measured at 4.5 ft. above the ground). The objective of a pre-commercial thinning Forest Service 12/11/2009
WINEGAR EXCAVATING INC $65,546 Water Distribution System at the Crane Prairie Guard Station Forest Service 6/21/2010
EASTERN OREGON ENVIRONMENTAL RECOVERY LLC $63,746 Install new potable water system at Forest Service Guard station. Forest Service 6/08/2010
MARCIEL WELL DRILLING & PUMPS $62,710 Malheur National Forest - Drill new domestic water wells at Crane Prairie and Crow Flat Guard Stations Forest Service 5/18/2010
GRAYBACK FORESTRY, INC. $57,717 Thin, pile, burn Malheur NF by cutting down trees and brush that no one wants, piling it into piles and then burning it with gas, diesel and matches Forest Service 12/04/2009
STONE ECOSURVEYS LLC $56,362 Expected outcome is a complete species list for several project areas in Malheur National Forest. Forest Service 8/10/2010
Tommy Reedy $55,576 Thinning and removal of BioMass Materials.
This spending item is part of a $224,253 allocation. See details
Forest Service 12/22/2009
HENDERSON LOGGING, INC $55,256 Roadside maintanence and brushing task orders 4 & 5 of several roads in the Malheur National Forest. Award includes clearing roadside brush to designated distances along several miles of Malheur National Forest roads. Forest Service 12/02/2009
GRAY BEAR CONSTRUCTION CO. $46,394 Roof Replacements Forest Wide, Malheur National Forest
This spending item is part of a $340,942 allocation. See details
Forest Service 6/02/2010
EASTERN OREGON STEWARDSHIP SERVICES CORP $35,898 Collection and mapping native seed for the Malheur National Forest Forest Service 7/29/2010
TRAINING EMPLOYMENT CONSORTIUM $33,283 Recovery Act of 2009: Capital Improvement and Maintenance The Oregon Youth Employment Initiative (OYEI) award has an overall purpose to: preserve and create jobs that promote economic recovery, assist those most impacted by the recession and to invest in environmental protection. The funds will prov... Show more
This spending item is part of a $9,627,090 allocation. See details
Forest Service 4/02/2009
TRAINING EMPLOYMENT CONSORTIUM $31,530 Recovery Act of 2009: Capital Improvement and Maintenance The Oregon Youth Employment Initiative (OYEI) award has an overall purpose to: preserve and create jobs that promote economic recovery, assist those most impacted by the recession and to invest in environmental protection. The funds will prov... Show more
This spending item is part of a $9,627,090 allocation. See details
Forest Service 4/02/2009
MONUMENT SCHOOL DISTRICT $31,323 Recovery Act of 2009: Capital Improvement and Maintenance The Oregon Youth Employment Initiative (OYEI) award has an overall purpose to: preserve and create jobs that promote economic recovery, assist those most impacted by the recession and to invest in environmental protection. The funds will prov... Show more
This spending item is part of a $9,627,090 allocation. See details
Forest Service 4/02/2009
TRAINING EMPLOYMENT CONSORTIUM $31,256 Recovery Act of 2009: Capital Improvement and Maintenance The Oregon Youth Employment Initiative (OYEI) award has an overall purpose to: preserve and create jobs that promote economic recovery, assist those most impacted by the recession and to invest in environmental protection. The funds will prov... Show more
This spending item is part of a $9,627,090 allocation. See details
Forest Service 4/02/2009
TRAINING EMPLOYMENT CONSORTIUM $29,935 Recovery Act of 2009: Capital Improvement and Maintenance The Oregon Youth Employment Initiative (OYEI) award has an overall purpose to: preserve and create jobs that promote economic recovery, assist those most impacted by the recession and to invest in environmental protection. The funds will prov... Show more
This spending item is part of a $9,627,090 allocation. See details
Forest Service 4/02/2009
BRIAN BROOKS $28,911 Stand Exams. Timber and ground vegetation data collection using GPS navigation to install random plots. Tree species, diameters, heights, and damages are recorded for each tree on plot. Trees per acre and volume can be calculated from this data. Forest Service 3/08/2010
TRAINING EMPLOYMENT CONSORTIUM $25,293 Recovery Act of 2009: Capital Improvement and Maintenance The Oregon Youth Employment Initiative (OYEI) award has an overall purpose to: preserve and create jobs that promote economic recovery, assist those most impacted by the recession and to invest in environmental protection. The funds will prov... Show more
This spending item is part of a $9,627,090 allocation. See details
Forest Service 4/02/2009
NRC ENVIRONMENTAL SERVICES INC. $23,520 Underground Heating Oil Tank Removals and remediation for nine locations.
This spending item is part of a $28,091 allocation. See details
Forest Service 2/11/2010
CAREX WORKING GROUP, L.L.C. $20,000 Recovery Act of 2009: Wildland Fire Management Willow and Cottonwood Inventory of the Malheur National Forest - conduct an inventory of willow and cottonwood species on the Malheur National Forest while retaining and creating employment opportunities that might not otherwise be available. This proje... Show more Forest Service 2/18/2010
MCALLISTER, MICHAEL L $17,335 TAS::12 1118::TAS RECOVERY - MALHEUR NATIONAL FOREST 2010 STAND EXAM 5 (DEARDORF-BIG COW), OREGON Forest Service 3/08/2010
A A A THUNDERDERBOLT FIRE SERVICE INC $11,130 Emigrant Creek District, Project 17, Stand management, thinning and pullback of conifers in the Malhuer National Forest Forest Service 8/11/2010
A A A THUNDERDERBOLT FIRE SERVICE INC $10,815 STAND DENSITY MANAGEMENT - PINE SPRINGS 207 & 209 THINNING AND PULLBACK OF CONIFERS Forest Service 8/11/2010
HUECKMAN, TODD $10,395 Thinning and Chipping of resulting slash in a Ponderosa Pine and Douglas Fir seed orchard. Forest Service 5/27/2010
SISKIYOU BIOSURVEY LLC $10,350 Manual collection of wild seed of native grass, shrub and forb species in support of habitat restoration activities Forest Service 8/02/2010
GRAY BEAR CONSTRUCTION CO. $7,252 Fire Lookout Catwalk Replacement, Roof Replacement, Floor Replacement - Malheur National Forest
This spending item is part of a $104,592 allocation. See details
Forest Service 8/31/2010
MULTIPLE RECIPIENTS $5,015 Supplemental Revenue Assistance Program Supplemental Revenue Assistance Payments (SURE) Farm Service Agency 11/30/2010
WHITE SHIELD, INC. $4,571 Underground Heating Oil Tank Removals and remediation for nine locations.
This spending item is part of a $28,091 allocation. See details
Forest Service 2/11/2010
A A A THUNDERDERBOLT FIRE SERVICE INC $3,880 Malheur National Forest, Blue Mountain Ranger District, Plantation Maintenance, Lower Middle Fork Thinning and Handpiling Forest Service 9/24/2010
MULTIPLE RECIPIENTS $0 Very Low to Moderate Income Housing Loans - Direct SECTION 502 SINGLE FAMILY HSNG DIRECT LN - 2009 ARRA Rural Housing Service 6/30/2010