Jackson County, Ore., funds by Transportation, Department of
Listing $18,772,440.58 in stimulus funds from Transportation, Department of for Jackson
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
TRANSPORTATION, OREGON DEPARTMENT OF | $9,011,293 | Highway Planning and Construction OR62 & OR140 PAVING | Federal Highway Administration | 3/24/2009 |
ROGUE VALLEY TRANSPORTATION DISTRICT | $2,429,712 | Federal Transit_Formula Grants This grant will improve Rogue Valley Transportation District's (RVTD)facilities and purchase equipment and buses. | Federal Transit Administration | 6/19/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $1,937,085 | Highway Planning and Construction GRIND AND PAVE 11 MILES OF INTERSTATE 5 ARRA FUNDS TO COMPLETE PAVING PROJECT | Federal Highway Administration | 3/24/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $1,390,796 | Highway Planning and Construction JACKSON COUNTY ROADS: PAVEMENT RESURFACING | Federal Highway Administration | 7/24/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $1,058,176 | Highway Planning and Construction BARNETT ROAD - BLUE HERON PARK UNIT 2C | Federal Highway Administration | 8/21/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $546,191 | Highway Planning and Construction REPLACE CULVERT | Federal Highway Administration | 5/19/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $389,776 | Highway Planning and Construction 2 IN PAVEMENT OVERLAY IN ACCORDANCE WITH 1R GUIDELINES | Federal Highway Administration | 6/08/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $381,549 | Highway Planning and Construction REPAVE ROADWAY & OVERLAY, INSTALL SIGNAGE AND SIGNALS | Federal Highway Administration | 6/11/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $339,446 | Highway Planning and Construction I-5 WELCOME SIGN | Federal Highway Administration | 1/07/2010 |
TRANSPORTATION, OREGON DEPARTMENT OF | $337,276 | Highway Planning and Construction PINE STREET PAVEMENT RESURFACING (CENTRAL POINT) | Federal Highway Administration | 12/10/2009 |
ROGUE VALLEY TRANSPORTATION DISTRICT | $316,000 | Federal Transit_Formula Grants This grant is funded from ARRA STP funds 100% Federal Share and was included in the STIP KN 16572. The project will complete an approximate 1 acre size gravel area by paving it for bus vehicle parking. | Federal Transit Administration | 6/19/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $192,069 | Highway Planning and Construction SIDEWALK RECONSTRUCTION | Federal Highway Administration | 5/07/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $180,500 | Highway Planning and Construction C ST: BIKE/PED IMPROVEMENTS (JACKSONVILLE) | Federal Highway Administration | 12/10/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $84,999 | Highway Planning and Construction 2 IN PAVEMENT OVERLAY IN ACCORDANCE WITH 1R GUIDELINES | Federal Highway Administration | 4/29/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $58,000 | Highway Planning and Construction CONSTRUCT BIKE LANES AND SIDEWALKS | Federal Highway Administration | 5/14/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $43,161 | Highway Planning and Construction REPAVE ROADWAY & OVERLAY, INSTALL SIGNAGE AND SIGNALS | Federal Highway Administration | 4/16/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $27,450 | Highway Planning and Construction INSTALL WELCOME SIGN | Federal Highway Administration | 11/09/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $24,877 | Highway Planning and Construction REPAVE ROADWAY & OVERLAY, INSTALL SIGNAGE ANDSIGNALS | Federal Highway Administration | 6/11/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $20,096 | Highway Planning and Construction 2 IN PAVEMENT OVERLAY IN ACCORDANCE WITH 1R GUIDELINES | Federal Highway Administration | 4/15/2009 |
TRANSPORTATION, OREGON DEPARTMENT OF | $3,987 | Highway Planning and Construction SIDEWALK RECONSTRUCTION | Federal Highway Administration | 4/15/2009 |