Guaynabo, P.R., funds by General Services Administration
Listing $1,903,151.33 in stimulus funds from General Services Administration for Guaynabo
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
DDG INC | $1,255,934 | This project was to provide a variety of sustainable features that will modernize the 35 year old complex into a high performing energy efficient facility. These features include a rooftop array of photovoltaic panesl to reduce electrical demand; roof mo | General Services Administration | 10/06/2010 |
INTEGRA PROJECT SERVICES CORP. | $391,773 |
Heery International is providing Construction Manager as Agent services for the Federal Bureau of Investigations (FBI) Office Consolidation Project for Construction Management Services for the Master Plan & Garage Design for a new Federal Employee Parking
This spending item is part of a $1,059,077 allocation.
See details
|
Public Buildings Service | 10/23/2009 |
DDG INC | $156,362 | This project was to provide a variety of sustainable features that will modernize the 35 year old complex into a high performing energy efficient facility. These features include a rooftop array of photovoltaic panesl to reduce electrical demand; roof mo | General Services Administration | 6/07/2011 |
SMITHS DETECTION, INC | $60,593 | Manufacturer/Contractor to provide security equipment (i.e., Multizone Walk-Through Metal Detector, Hand-held Metal Detector, Hi-SCAN 5030si X-ray System, and related software and roller tables) to the Veterans Benefit Administration located in Guaynabo, | General Services Administration | 7/12/2010 |
CONTINENTAL MARBLE & STONE WORKS, CORP. | $33,614 |
During this quarter we continued as the Prime Contractor reconstruction of the 2nd & 3rd Floor swing space(completing and moving into their swing space the Library, FCU and BRACS tenants) and the west mechanical boiler room at the Federal Office Building
This spending item is part of a $73,504,501 allocation.
See details
|
Public Buildings Service | 5/06/2010 |
DEYA ELEVATOR SERVICE INC | $4,875 |
During this quarter we continued as the Prime Contractor reconstruction of the 2nd & 3rd Floor swing space(completing and moving into their swing space the Library, FCU and BRACS tenants) and the west mechanical boiler room at the Federal Office Building
This spending item is part of a $73,504,501 allocation.
See details
|
Public Buildings Service | 5/06/2010 |