Providence County, R.I., funds by Department of Veterans Affairs
Listing $12,850,501.66 in stimulus funds from Department of Veterans Affairs for Providence
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
M. DISANDRO & SONS MASONRY, INC. | $4,200,000 | TAS::36 0158::TAS FCA Repair and Replace Exterior Fa+?ade Phase II, Project 650-08130, At VA Medical Center, Providence, RI. | Department of Veterans Affairs | 9/16/2010 |
BRICAN, INC. | $2,293,747 | Provide all Labor and Materials to install new steam traps, steam line and steam monitoring system. Contract also calls for 4 new sub-basement entrances as well as sub-basement floor slab. | Department of Veterans Affairs | 4/28/2010 |
BRICAN, INC. | $1,820,088 | FCA Convert High Pressure Steam Boilers to Low Pressure Steam Boilers. | Department of Veterans Affairs | 3/22/2010 |
BRICAN, INC. | $1,533,000 | Provide all Materials and Labor to update/renovate HVAC System for Wards 6A and 6B, VAMC Providence, RI. | Department of Veterans Affairs | 4/06/2010 |
BRICAN, INC. | $1,216,228 | Boiler plant modifications including Construction, Alterations, Mechanical/Electrical work as well as necessary removal of portions of existing structures and construction. | Department of Veterans Affairs | 9/27/2010 |
BRICAN, INC. | $415,918 | Perform repairs to the existing Medical Gas System. | Department of Veterans Affairs | 8/27/2010 |
IRONCLAD SERVICES, INC. | $405,418 |
Phase 1 - Project #650-07-107 - Replace Electrical Wiring, Modification #0002, dated 09/23/10 to decrease the estimate quantity of conduit required for new branch circuits per conduit tracking sheet and contrator's draft final invoice.
This spending item is part of a $875,266 allocation.
See details
|
Department of Veterans Affairs | 7/31/2009 |
TECTA AMERICA CORP. | $325,500 |
Remove & replace the existing roof systems of the following: Building 1, 8th Floor, Building 1, 9th Floor, including small roof over equipement room, Building 1, C-Wing, large roof, Building 1, C-Wing, 5th & 6th Floor small roofs (3), Building T-18, Build
This spending item is part of a $457,974 allocation.
See details
|
Department of Veterans Affairs | 8/19/2010 |
TRANE U.S. INC. | $312,000 |
FURNISH LABOR, MATERIAL, TRANSPORTATION, EQUIPMENT, DISPOSAL AND SUPERVISION TO REPLACE AIR HANDLING UNIT EQUIPMENT (PHASE 2) AT BUILDING 1 MECHANICAL TOWER, WEST ROXBURY VAMC
This spending item is part of a $1,284,779 allocation.
See details
|
Department of Veterans Affairs | 3/29/2010 |
LEGION CONSTRUCTION, INC. | $132,474 |
Remove & replace the existing roof systems of the following: Building 1, 8th Floor, Building 1, 9th Floor, including small roof over equipement room, Building 1, C-Wing, large roof, Building 1, C-Wing, 5th & 6th Floor small roofs (3), Building T-18, Build
This spending item is part of a $457,974 allocation.
See details
|
Department of Veterans Affairs | 8/19/2010 |
American Pride Insulation Co | $56,000 |
Provide all necessary supervision, labor, materials & equipment to modify the boiler Jamaica Plain VAMC, MA.
This spending item is part of a $4,258,000 allocation.
See details
|
Department of Veterans Affairs | 6/17/2010 |
American Pride Insulation Co | $48,304 |
Furnish all labor, materials, transportation, equipment, disposal and supervision to renovate the Specialty Clinic at the Brockton VAMC Facility
This spending item is part of a $3,468,000 allocation.
See details
|
Department of Veterans Affairs | 9/20/2010 |
Atlantic Insulation Corp. Of New England Inc. | $36,225 |
FURNISH LABOR, MATERIAL, TRANSPORTATION, EQUIPMENT, DISPOSAL AND SUPERVISION TO REPLACE AIR HANDLING UNIT EQUIPMENT (PHASE 2) AT BUILDING 1 MECHANICAL TOWER, WEST ROXBURY VAMC
This spending item is part of a $1,284,779 allocation.
See details
|
Department of Veterans Affairs | 3/29/2010 |
American Pride Insulation Co | $35,200 |
Provide all necessary supervision, labor, materials, transportation, disposal to replace the steam piping (Phase II) at the Jamaica Plain VAMC, MA.
This spending item is part of a $1,299,450 allocation.
See details
|
Department of Veterans Affairs | 6/17/2010 |
American Pride Insulation Co | $20,400 |
Provide all labor, materials, equipment, transportation, supervision and disposal necessary for the Chiller Upgrade at Jamaica Plain VAMC, MA.
This spending item is part of a $889,500 allocation.
See details
|
Department of Veterans Affairs | 6/30/2010 |
LEGION CONSTRUCTION, INC. | $0 |
TAS::36 0158::TAS FCA Repair and Replace Exterior Fa+?ade Phase II, Project 650-08130, At VA Medical Center, Providence, RI.
This spending item is part of a $2,409,505 allocation.
See details
|
Department of Veterans Affairs | 9/16/2010 |