Recovery Tracker

How Much Stimulus Funding is Going to Your County?

Salt Lake County, Utah, funds by Department of Veterans Affairs

Listing $6,012,987.18 in stimulus funds from Department of Veterans Affairs for Salt Lake

Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.

Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.

Recipient Amount Description Federal Dept./Agency Date
IXL/WORLD CLASS BUILDERS $920,507 Building 3 new electrical towers for electrical upgrade on Bldg. 14 Department of Veterans Affairs 1/22/2010
GRAND ENTERPRISES LLC $745,708 install solar light poles, remove old light poles, repair landscape Department of Veterans Affairs 9/17/2010
RWT L.L.C. $655,469 replace oudated/obsolete control panel devices in bldgs across from the VA medical center campus Department of Veterans Affairs 9/30/2010
GRAND ENTERPRISES LLC $569,951 install new 12 water line loop, install 2-15,000gal fuel tanks for emergency generators Department of Veterans Affairs 12/31/2009
Tasco Engineering, Inc. $407,790 New wire was installed and terminated at the switch gear, all testing is complete and project is accepted
This spending item is part of a $823,207 allocation. See details
Department of Veterans Affairs 9/15/2010
MSC DESIGN BUILD LLC $377,266 MS Construction has been contracted to complete all earthwork including installing new ductbanks, manholes, backfill and landscape repairs. R&L has been contracted to supply and install new fiber systems and test new systems
This spending item is part of a $810,016 allocation. See details
Department of Veterans Affairs 2/02/2010
MSC DESIGN BUILD LLC $370,322 New wire was installed and terminated at the switch gear, all testing is complete and project is accepted
This spending item is part of a $823,207 allocation. See details
Department of Veterans Affairs 9/15/2010
Tasco Engineering, Inc. $356,471 Tasco has been contracted to complete all earthwork including installing new ductbanks, manholes, backfill and landscape repairs. They are also responsible for installing conductors, switch gear and equipment pads
This spending item is part of a $781,088 allocation. See details
Department of Veterans Affairs 2/02/2010
RWT L.L.C. $284,954 bldg 8 locker room Department of Veterans Affairs 9/22/2010
MSC DESIGN BUILD LLC $244,298 Tasco has been contracted to complete all earthwork including installing new ductbanks, manholes, backfill and landscape repairs. They are also responsible for installing conductors, switch gear and equipment pads
This spending item is part of a $781,088 allocation. See details
Department of Veterans Affairs 2/02/2010
Ms Construction Inc $234,802 MS Construction has been contracted to complete all earthwork including installing new ductbanks, manholes, backfill and landscape repairs. R&L has been contracted to supply and install new fiber systems and test new systems
This spending item is part of a $810,016 allocation. See details
Department of Veterans Affairs 2/02/2010
R&L Network Solutions $197,948 MS Construction has been contracted to complete all earthwork including installing new ductbanks, manholes, backfill and landscape repairs. R&L has been contracted to supply and install new fiber systems and test new systems
This spending item is part of a $810,016 allocation. See details
Department of Veterans Affairs 2/02/2010
Ms Construction Inc $167,100 MS Construction has been contracted to complete all earthwork including installing new chilled water lines, backfill and landscape repairs.
This spending item is part of a $350,798 allocation. See details
Department of Veterans Affairs 2/02/2010
WHEELER MACHINERY CO. $122,319 Tasco has been contracted to complete all earthwork including installing new ductbanks, manholes, backfill and landscape repairs. They are also responsible for installing conductors, switch gear and equipment pads
This spending item is part of a $781,088 allocation. See details
Department of Veterans Affairs 2/02/2010
MSC DESIGN BUILD LLC $112,650 MS Construction has been contracted to complete all earthwork including installing new chilled water lines, backfill and landscape repairs.
This spending item is part of a $350,798 allocation. See details
Department of Veterans Affairs 2/02/2010
V.O. Brothers Mechanical, LLC $71,048 MS Construction has been contracted to complete all earthwork including installing new chilled water lines, backfill and landscape repairs.
This spending item is part of a $350,798 allocation. See details
Department of Veterans Affairs 2/02/2010
Coda Construction Inc $66,600 Upgrade/Replace Dlectrical Systems and Generators
This spending item is part of a $1,614,703 allocation. See details
Department of Veterans Affairs 3/23/2010
SPECTRUM ENGINEERS, INC. $58,000 Tasco has been contracted to complete all earthwork including installing new ductbanks, manholes, backfill and landscape repairs. They are also responsible for installing conductors, switch gear and equipment pads
This spending item is part of a $781,088 allocation. See details
Department of Veterans Affairs 2/02/2010
Ms Construction Inc $45,095 New wire was installed and terminated at the switch gear, all testing is complete and project is accepted
This spending item is part of a $823,207 allocation. See details
Department of Veterans Affairs 9/15/2010
A-CORE CONCRETE CUTTING, INC. $4,690 Project #644-09-103 Correct GEMs Deficiencies
This spending item is part of a $280,980 allocation. See details
Department of Veterans Affairs 3/31/2010