King County, Wash., funds by Transportation, Department of
Listing $305,451,781.73 in stimulus funds from Transportation, Department of for King
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $79,970,426 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 3/26/2009 |
KING, COUNTY OF | $70,940,537 | Federal Transit_Formula Grants Invest in public transportation by paying for the purchase of 66 40ft low floor hybrid electric replacement buses, and conduct preventive maintenance and provide operating assistance on all existing buses operated in the King County Region. The initial s | Federal Transit Administration | 5/21/2009 |
CENTRAL PUGET SOUND REGIONAL TRANSIT AUTHORITY | $44,000,000 | Federal Transit_Capital Investment Grants Design, right-of-way acquisition, light rail vehicle procurement and construction of the University Link Light Rail project. The University Link project is a 3.15 mile extension of the Initial Segment from the Pine Street Stub Tunnel (PSST) to the Univers | Federal Transit Administration | 6/25/2009 |
SEATTLE, CITY OF | $30,000,000 | Highway Planning and Construction TIGER | Federal Highway Administration | 5/27/2010 |
CENTRAL PUGET SOUND REGIONAL TRANSIT AUTHORITY | $23,061,105 | Federal Transit_Formula Grants Construct Univeristy Link light rail segment, Mountlake Terrace Freeway Station, M Street (Tacoma) to Lakewood Commuter Rail track and signal work, and design and construct a permanent Tukwila Commuter Rail Station and purchase approx five clean fuel buse | Federal Transit Administration | 5/20/2009 |
SEATTLE, CITY OF | $15,443,000 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 5/14/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $7,456,270 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 10/26/2009 |
REDMOND, CITY OF | $4,594,075 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 3/23/2009 |
NORMANDY PARK, CITY OF | $3,834,000 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 5/26/2009 |
SAMMAMISH, CITY OF | $3,500,000 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 6/30/2009 |
PORT OF SEATTLE | $2,875,171 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 7/20/2009 |
FARE LOGISTICS CORP | $2,089,174 |
Federal Transit_Formula Grants Invest in public transportation by purchasing two 40' compressed natural gas (CNG) buses, two 30' CNG buses, a regional fare collection system, fleet-wide automated passenger counters, an additional CNG compressor, and six nonrevenue support vehicles; by
This spending item is part of a $12,062,685 allocation.
See details
|
Federal Transit Administration | 8/14/2009 |
KENT, CITY OF | $2,000,000 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 4/22/2009 |
RENTON, CITY OF | $1,948,674 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 6/17/2009 |
TODD PACIFIC SHIPYARDS CORPORATION | $1,945,981 | Assistance to Small Shipyards Apprenticeship Program | Maritime Administration | 8/17/2009 |
KING, COUNTY OF | $1,314,011 | Federal Transit_Formula Grants Invest in public transportation by purchasing a maintenance barge to support passenger-only ferry operations. The barge will be used for daily and light maintenance on the County's ferry fleet as-well-as overnight moorage for up to 4 vessels. The barge wi | Federal Transit Administration | 8/20/2009 |
SEATTLE, CITY OF | $1,314,011 | Federal Transit_Formula Grants Invest in public transportation by renovating the Seattle Center Monorail guideways and supports, including replacement of the electric power conductor rails and providing operating assistance for South Lake Union Streetcar. | Federal Transit Administration | 5/20/2009 |
County of King | $1,270,557 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 4/24/2009 |
KVICHAK MARINE INDUSTRIES, INC. | $1,138,602 | Assistance to Small Shipyards Installation of a fixed boom crane with wireless controller, vertical integration of aluminum plate processing equipment, and training enhancements. | Maritime Administration | 8/17/2009 |
KING, COUNTY OF | $1,047,041 | Federal Transit_Formula Grants Invest in public transportation by paying for the purchase of 2 40ft low floor hybrid electric replacement buses. The initial stage of the manufacturing of the 40ft low floor hybrid buses takes place in Mississauga, Ontario, Canada. The bus shells are the | Federal Transit Administration | 8/05/2010 |
MARINE FLUID SYSTEMS, INC. | $744,244 | Assistance to Small Shipyards Small shipyard upgrades- Project#1) Upgrade railway and sidetrack. Project #2) Equipment procurement. Crane, forklift, iron worker, and welding machines. | Maritime Administration | 8/17/2009 |
EXPRESS CONSTRUCTION COMPANY, INC. | $664,364 |
Air Route Traffic Control Center (ARTCC) Curtain Wall Replacement Design/Build Projects. The project provide for the Design, Pre-Construction, Procurement and Construction Services for the Administration Wing Curtain Wall Replacement Design/Build Projects
This spending item is part of a $11,082,801 allocation.
See details
|
Federal Aviation Administration | 3/13/2009 |
FOSS MARITIME COMPANY | $621,761 | Assistance to Small Shipyards Purchase of various equipment | Maritime Administration | 8/17/2009 |
BOTHELL, CITY OF | $548,237 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 8/11/2009 |
BURIEN, CITY OF | $536,293 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 6/04/2009 |
SCHNEIDER ELECTRIC USA, INC. | $505,207 | SQUARE D SWITCHGEAR REQUIRED FOR THE SEATTLE TRACON POWER SYSTEM HARDENING PROJECT ACCORDING TO SQUARE D # 28300994 | Federal Aviation Administration | 6/01/2010 |
BOTHELL, CITY OF | $500,000 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 8/03/2009 |
BOTHELL, CITY OF | $457,355 | Highway Planning and Construction Highway Infrastructure Investment Grants | Federal Highway Administration | 6/04/2010 |
ARCADIA, INC. | $370,520 |
Air Route Traffic Control Center (ARTCC) Curtain Wall Replacement Design/Build Projects. The project provide for the Design, Pre-Construction, Procurement and Construction Services for the Administration Wing Curtain Wall Replacement Design/Build Projects
This spending item is part of a $11,082,801 allocation.
See details
|
Federal Aviation Administration | 3/13/2009 |
NORTH BEND, CITY OF | $227,443 | Formula Grants for Other Than Urbanized Areas This project will improve two existing gravel parking lots for park and ride facilities for use by transit riders and carpoolers on the I-90 corridor. The improvements include paving, drainage, lighting, signage, and landscaping. | Federal Transit Administration | 2/25/2010 |
LAKE UNION DRYDOCK COMPANY | $184,217 | Assistance to Small Shipyards Drydock Upgrade and Technology Upgrade | Maritime Administration | 8/17/2009 |
Porter & Associates Inc | $75,015 |
To conduct ARRA related work on FMO full-scope reviews, follow-ups, cost allocation plans, financial capacity and capability assessments, agreed-upon procedures, and special assignments
This spending item is part of a $1,350,000 allocation.
See details
|
Federal Transit Administration | 4/11/2011 |
Holmberg Company | $69,250 |
Replacement of the HVAC units on the roof of the Annex Builidng at the Seattle Air RouteTraffic Control Center located in Auburn Washington
This spending item is part of a $87,798 allocation.
See details
|
Federal Aviation Administration | 9/07/2010 |
PACIFIC RIM ENVIRONMENTAL INC | $65,850 |
This project involves environmental services to support air quality monitoring during asbestos abatement activities at air traffic facilities nationwide. This project has been awarded under Contract DTFA0102C0016, Modification 791. The initial Modificatio
This spending item is part of a $849,074 allocation.
See details
|
Federal Aviation Administration | 12/08/2009 |
E-CORP. | $48,138 | Refurbish the restrooms in the annex building in Seattle. | Federal Aviation Administration | 9/14/2010 |
CONSULTING ASSOCIATES OF NY, INC. | $46,200 |
Air Route Traffic Control Center (ARTCC) Curtain Wall Replacement Design/Build Projects. The project provide for the Design, Pre-Construction, Procurement and Construction Services for the Administration Wing Curtain Wall Replacement Design/Build Projects
This spending item is part of a $11,082,801 allocation.
See details
|
Federal Aviation Administration | 3/13/2009 |
E-CORP. | $18,548 |
Replacement of the HVAC units on the roof of the Annex Builidng at the Seattle Air RouteTraffic Control Center located in Auburn Washington
This spending item is part of a $87,798 allocation.
See details
|
Federal Aviation Administration | 9/07/2010 |
APPLY-A-LINE INC | $17,888 |
This 5 mile long road reconstruction and rehabilitation project is located on Forest Road 22, approximately 29 miles north of Montesano, WA in Grays Harbor County. It includes earth grading, aggregate base placement, paving and culvert installation and r
This spending item is part of a $4,446,476 allocation.
See details
|
Federal Highway Administration | 6/18/2009 |
TERRA DYNAMICS, INC. | $6,917 | Bonding Assistance Program DBE AMERICAN REINVESTMENT AND RECOVERY ACT OF 2009 BONDING ASSISTANCE REIMBURSABLE FEE PROGRAM | Office of the Secretary of Transportation | 8/19/2010 |
RALPH'S CONCRETE PUMPING, INC. | $1,700 |
This 5 mile long road reconstruction and rehabilitation project is located on Forest Road 22, approximately 29 miles north of Montesano, WA in Grays Harbor County. It includes earth grading, aggregate base placement, paving and culvert installation and r
This spending item is part of a $4,446,476 allocation.
See details
|
Federal Highway Administration | 6/18/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $548,237 allocation.
See details
|
Federal Highway Administration | 8/11/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $1,948,674 allocation.
See details
|
Federal Highway Administration | 6/17/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $2,875,171 allocation.
See details
|
Federal Highway Administration | 7/20/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $3,834,000 allocation.
See details
|
Federal Highway Administration | 5/26/2009 |
BOTHELL, CITY OF | $0 | Highway Planning and Construction Highway Infrastructure Investment Grant: Urbanized Areas over 200K Population | Federal Highway Administration | 12/09/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $4,594,075 allocation.
See details
|
Federal Highway Administration | 3/23/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $536,293 allocation.
See details
|
Federal Highway Administration | 6/04/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $2,000,000 allocation.
See details
|
Federal Highway Administration | 4/22/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $15,443,000 allocation.
See details
|
Federal Highway Administration | 5/14/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $3,500,000 allocation.
See details
|
Federal Highway Administration | 6/30/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $1,270,557 allocation.
See details
|
Federal Highway Administration | 4/24/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Formula Grants for Other Than Urbanized Areas This project will improve two existing gravel parking lots for park and ride facilities for use by transit riders and carpoolers on the I-90 corridor. The improvements include paving, drainage, lighting, signage, and landscaping.
This spending item is part of a $227,443 allocation.
See details
|
Federal Transit Administration | 2/25/2010 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 | Highway Planning and Construction Highway Infrastructure Investment Grant: Urbanized Areas over 200K Population | Federal Highway Administration | 12/09/2009 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $457,355 allocation.
See details
|
Federal Highway Administration | 6/04/2010 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction TIGER
This spending item is part of a $30,000,000 allocation.
See details
|
Federal Highway Administration | 5/27/2010 |
TRANSPORTATION, WASHINGTON STATE DEPARTMENT OF | $0 |
Highway Planning and Construction Highway Infrastructure Investment Grants
This spending item is part of a $500,000 allocation.
See details
|
Federal Highway Administration | 8/03/2009 |