Browse All Approved Stimulus Highway Projects
Road and bridge projects are expected to make up one of the biggest chunks of the jobs created in the stimulus package. Below, you’ll find a chart of more than 5,800 projects that have been approved by the U.S. Department of Transportation. Once given the green light, states can put the projects out to bid, contract them and begin construction work. So far, about 2,300 projects are under way.
Help us find out how much progress has been made on these projects by participating in our Stimulus Spot Check.
For more on the stimulus, check out our blog and resource page.
State | County | Project Number | Project Description | Improvement Type | ARRA Funds Obligated |
---|---|---|---|---|---|
ARIZONA | MARICOPA | GRI0200 | Pre-Engineer/Design and Construct Pavement Rehab projects | Other | $11,227 |
ARIZONA | PIMA | IT00200 | SAN XAVIER ROAD BETWEEN MISSION AND LOS REALES ROADS ON TOHONO O'ODHAM NATION | Other | $10,000 |
ARIZONA | MOHAVE | KNG0201 | Mill and repave intersection | Other | $2,000 |
ARIZONA | MOHAVE | KNG0202 | Street overlay / pavement preservation | Other | $10,000 |
ARIZONA | LA PAZ | LLA0201 | 2" Overlay | Other | $6,000 |
ARIZONA | MARICOPA | LPK0201 | Pre-Engineer/Design and mill and replace pavement resurfacing/ reconstruction | Other | $12,279 |
ARIZONA | PINAL | MAR0200 | Intersection signalization | Other | $20,000 |
ARIZONA | MOHAVE | MM00001 | ALONG MOHAVE CHANNEL BETWEEN GORDON DRIVE AND BANK STREET IN THE CITY OF KINGMAN, ARIZONA | Transportation Enhancements | $698,368 |
ARIZONA | MOHAVE | MM00200 | ALONG MOHAVE CHANNEL BETWEEN BANK STREET AND NORTHERN AVENUE IN THE CITY OF KINGMAN, AZ; SHARED USE PATHWAY---ARRA | Transportation Enhancements | $440,000 |
ARIZONA | MOHAVE | MM00203 | MILL & REPLACE; NORTHERN AVE; STOCKTON HILL RD TO BANK STREET IN KINGMAN, AZ | Other | $20,000 |
ARIZONA | MARICOPA | MMA0201 | Pave existing shoulders and add bike lane | New Construction | $750,000 |
ARIZONA | MARICOPA | MMA0210 | Pre-Engineer/Design and construct AR Overlay | Other | $59,508 |
ARIZONA | PIMA | MRN0202 | Pavement Preservation | Other | $10,000 |
ARIZONA | NAVAJO | NNA0200 | Pavement Preservation | Other | $40,000 |
ARIZONA | MARICOPA | PE00205 | Beardley Road; Lake Pleasant road to 83rd Ave in Peoria; Preliminary Engineering; | Other | $11,301 |
ARIZONA | MARICOPA | PE00206 | BEARDSLEY ROAD CONNECTION; Loop 101 to Beardsley Road at 83rd ave.Lake Pleasant Pkwy in Peoria. Preliminary Engineering | Other | $28,504 |
ARIZONA | MARICOPA | PHX0209 | Design & Construction of Intersection Improvements | Other | $27,693 |
ARIZONA | MARICOPA | PHX0229 | Design & Construction of Removal/Replacement of Existing ADA Ramps or Construction of New ADA Ramps | Other | $82,550 |
ARIZONA | MARICOPA | PHX0230 | Design & Construction of Removal/Replacement of Existing ADA Ramps or Construction of New ADA Ramps | Other | $82,550 |
ARIZONA | MARICOPA | PHX0231 | Design & Costruct Bridge Deck Rehabilitations | Other | $187,106 |
ARIZONA | MARICOPA | PHX0232 | Design & Costruct Bridge Joint Rehabilitations | Other | $184,883 |
ARIZONA | MARICOPA | PHX0233 | Design &Procure/Install CCTV | Other | $141,205 |
ARIZONA | MARICOPA | PHX0234 | Design & Procure/Install Fiber Optic Backbone System | Other | $91,334 |
ARIZONA | MARICOPA | PHX0235 | Design &Procure/Install Wireless Communications | Other | $106,654 |
ARIZONA | MARICOPA | PHX0236 | Inventory / Programming & Procure / Install Traffic Control Signs | Other | $226,668 |
ARIZONA | YAVAPAI | YYV0202 | Cold in place recycle; reconstruction | Other | $20,000 |
ARIZONA | MARICOPA | PHX0238 | Design & Construction of Pavement Preservation | Other | $91,786 |
ARIZONA | MARICOPA | PHX0239 | Design & Construction of Pavement Preservation | Other | $91,786 |
ARIZONA | PIMA | PPM0161 | Paved shoulders, shared use driveway improvements, access ramps | New Construction | $575,000 |
ARIZONA | PIMA | PPM0214 | Pavement Preservation | Other | $74,690 |
ARIZONA | PIMA | PPM0215 | Structural deck repairs performed from above & between parapet walls. | Other | $60,000 |
ARIZONA | YAVAPAI | PRV0203 | Overlay/ 3" AC | Other | $20,000 |
ARIZONA | PIMA | SAH0201 | La Villita in Rancho Sahuarita, and Duval Mine Road from La Canada to west town limits in SAHUARITA- Pavement Pres. and Pathway. | Other | $10,000 |
ARIZONA | NAVAJO | SLW0201 | Pavement Preservation | Other | $40,000 |
ARIZONA | PIMA | STC0200 | Pavement Preservation | Other | $10,000 |
ARIZONA | GILA | SUP0200 | Pavement Preservation | Other | $20,000 |
ARIZONA | MARICOPA | SUR0208 | Pre-Engineer/Design and construct pavement Reconstruction and ITS Conduit Installation | Other | $29,334 |
ARIZONA | PIMA | SVS0200 | Multi use path, landscaping, and irrigation | Other | $650,000 |
ARIZONA | COCHISE | SVS0204 | Widening, signal upgrades, drainage, improvements, curb, sidewalk, MUP on S side. | Other | $20,000 |
ARIZONA | GRAHAM | THR0200 | 2" AC Overlay | Other | $20,000 |
ARIZONA | PIMA | TUC0231 | Pavement Preservation | Other | $71,700 |
ARIZONA | MARICOPA | WBG0200 | Design and Complete Pavement Mill and Replace | Other | $12,883 |
ARIZONA | YUMA | YMP0200 | San Luis II Port of Entry, Avenue E and County 25th Street Preliminary Engineering | New Construction | $20,127 |
ARIZONA | MARICOPA | YTN0200 | Pre-Engineer/Design and construct mill and replace - pavement resurfacing | Other | $12,918 |
ARIZONA | YUMA | YUM0200 | Construction of an interpretative plaza, complete with retaining walls | New Construction | $750,000 |
ARIZONA | MARICOPA | PHX0237 | Design & Construction of Pavement Preservation | Other | $91,786 |
ARKANSAS | LAWRENCE | ARR1001 | PROVIDE GRADING AND STRUCTURES FOR 9.89 MILES OF A 4-LANE DIVIDED FACILITY ON NEW LOCATION | New Construction | $21,094,279 |
ARKANSAS | PULASKI | ARR1003 | CONTINUE MODIFICATION OF EXISTING INTERCHANGE | Bridge Improvement | $15,991,380 |
ARKANSAS | ST FRANCIS | ARR1004 | ACHM REHABILITATION OF 4.30 MILES | Pavement Improvement | $1,663,847 |
ARKANSAS | PHILLIPS | ARR1005 | ACHM REHABILITATION OF 1.36 MILES | Pavement Improvement | $438,262 |