Browse All Approved Stimulus Highway Projects
Road and bridge projects are expected to make up one of the biggest chunks of the jobs created in the stimulus package. Below, you’ll find a chart of more than 5,800 projects that have been approved by the U.S. Department of Transportation. Once given the green light, states can put the projects out to bid, contract them and begin construction work. So far, about 2,300 projects are under way.
Help us find out how much progress has been made on these projects by participating in our Stimulus Spot Check.
For more on the stimulus, check out our blog and resource page.
| State | County | Project Number | Project Description | Improvement Type | ARRA Funds Obligated |
|---|---|---|---|---|---|
| OHIO | MONTGOMERY | E090585 | STREET RESURFACING. | Pavement Improvement | $205,282 |
| OHIO | ASHTABULA | E090658 | Resurfacing and reconstruction. | Other | $50,000 |
| OHIO | STARK | E090664 | Track Rehabilitation | Other | $1,200,000 |
| OHIO | SUMMIT | E090665 | Deck overlay and fence installation. | Bridge Improvement | $7,500,000 |
| OHIO | PORTAGE | E090680 | REPLACE OR REHAB BRIDGE OVER CUYAHOGA RIVER AND CSX. IMPROVE CRAIN AVE. INTERSECTION IMPROVEMENT OF THREE INTERSECTIONS. | Bridge Replacement | $3,000,000 |
| OHIO | ROSS | E090681 | It is proposed to widen SR104 from US35 to the new relocated SR207 by adding additional thru traffic lanes and a center turn lane. PE Only-100% LPA Funds. | Pavement Improvement | $6,500,000 |
| OHIO | HOCKING | E090683 | Part 2 of 3, the Nelsonville By-Pass (CO Phase). Includes PE and RW phase activities. Some environmental under old PID 14040. Part 1 CO Phase under PID 80949. Part 3 CO Phase under PID 79577. ARR | New Construction | $55,880,000 |
| OHIO | CUYAHOGA | E090686 | Construct a grade separation at Columbia Road (SR-252) and the CSX RailroadCompany tracks in the City of Olmsted Falls.SAFETEA-LU Earmark(NEW BRIDGE, SFN 1810391) | New Bridge Construction | $7,693,000 |
| OHIO | HOCKING | E090688 | Part 3 of 3, the Nelsonville By-Pass (CO phase). Part 1 CO Phase under PID 80949. PE, RW and CO Phase Part 2 under PID 23846. Some environmental under old PID 14040. ARRA ID 7217 | New Construction | $120,210,000 |
| OHIO | MAHONING | E090692 | Mill and Fill. | Pavement Improvement | $236,500 |
| OHIO | PREBLE | E090709 | Replace small culvert PRE-40-0740. The existing culvert is an 84"x40" cast-in-place concrete culvert. | Pavement Improvement | $135,640 |
| OHIO | BUTLER | E090710 | Resurfacing sections of Tylersville & River Roads and replacing the striping and RPMs in the same sections. | Pavement Improvement | $2,294,165 |
| OHIO | CLERMONT | E090711 | Resurfacing, full depth pavement repair, berm repair, pavement striping, and RPMs on various County roads (approx. 28 miles). Curb and ADA curb ramps on Buckwheat Road. | Pavement Improvement | $2,464,300 |
| OHIO | GREENE | E090713 | Simple overlay of pavement, striping and berm repair. | Pavement Improvement | $185,881 |
| OHIO | HAMILTON | E090715 | Cornell Road to be microsurfaced. New pavement marking and curb ramps as well. | Pavement Improvement | $130,725 |
| OHIO | HAMILTON | E090716 | Resurface a portion of the Reed Hartman Hwy. Also, perform pavement repair, curb & gutter repair, replace signal loops with video detection, replacing pavement striping, place new RPMs, and where ap | Pavement Improvement | $840,000 |
| OHIO | HAMILTON | E090718 | Resurfacing, curb replacement, base repairs, and inlet reconstruction to restore roadway integrity. | Pavement Improvement | $635,000 |
| OHIO | CUYAHOGA | E090751 | Widen existing bridge to standard shoulder widths. Ramp to be used as a detour for the Innerbelt Bridge. Project includes work necessary to create an additional temporary lane on I77 between I90 and | Bridge Improvement | $2,804,765 |
| OHIO | WOOD | E090752 | Hydrodemo the existing wearing course and overlay with micro-silica. (See PID 25492 for pavement major rehab) of 4 bridges. Perform necessary related work. Original project scope of the Disalle bridge | Bridge Improvement | $5,585,106 |
| OHIO | HARRISON | E090753 | 11 - Bridge Replacement, No Added Capacity | Bridge Replacement | $910,619 |
| OHIO | FRANKLIN | E090754 | FY09 Urban Paving Project - City Of Columbus.FRA-US40-8.59-10.55: Columbus. W Broad Street From Hague Ave To Central Ave.Added Federal/State Paving Of West Broad St Ramps (Broad St To I-70 WB And I-70 | Pavement Improvement | $654,980 |
| OHIO | TUSCARAWAS | E090755 | general system - poor performing pavements | Pavement Improvement | $1,093,310 |
| OHIO | LOGAN | E090756 | Pavement planing and resurfacing of the existing roadway with asphalt concrete.(Urban Paving Program) | Pavement Improvement | $227,525 |
| OHIO | CUYAHOGA | E090757 | Replace concrete ramps at IR-480 and W. 130th. | Pavement Improvement | $757,580 |
| OHIO | ASHLAND | E090767 | Replace 3 Span Slab Bridge Over Jerome Forkstimulus Estimate 430,310 (Cbrown 02/03/09)** Selected Stimulus Project ** | Bridge Replacement | $393,060 |
| OHIO | PORTAGE | E090927 | Replacement of existing 2 span steel truss and steel beam structure, also includes approach reconstruction | Bridge Replacement | $1,124,000 |
| OHIO | ASHLAND | E090785 | Replace 3 Span Steel Beam Bridge Over Muddy Forkstimulus Estimate 508,333 (Cbrown 02/13/09)** Selected Stimulus Project ** | Bridge Replacement | $439,070 |
| OHIO | WAYNE | E090786 | Rehabilitate Deficient 302' Structure Over IR71Stimulus Estimate 1,769,290 (Cbrown 01/20/09)** Selected Stimulus Project ** | Bridge Improvement | $1,643,250 |
| OHIO | LUCAS | E090789 | A partially ARRA funded and partially Urban Paving Program funded resurfacing of Telegraph Rd (US-24) from Alexis Rd (SR-184) to just south of the Michigan State Line in the City of Toledo. Perform n | Pavement Improvement | $315,000 |
| OHIO | LUCAS | E090790 | The Partially (TMACOG) ARRA funded and partially Urban Paving Program funded resurfacing of Detroit Ave (US-24) in the City of Toledo from I-75 near Monroe St to Central Ave (SR-120). Perform necessa | Pavement Improvement | $570,000 |
| OHIO | CUYAHOGA | E090792 | Track rehabilitation work to reduce derailment expenses and help railroad provide reliable service to two rail-dependent businesses that employ a total of 50 people. | Other | $67,000 |
| OHIO | KNOX | E090793 | Districtwide approach slab leveling | Bridge Improvement | $1,100,000 |
| OHIO | WAYNE | E090800 | City of Orrville; Upgrade to Railroad lights and gates | Safety/Traffic Management | $850,000 |
| OHIO | CLARK | E090801 | West County Port Authority; Track Rehabilitation | Other | $1,000,000 |
| OHIO | COLUMBIANA | E090802 | Modernize Warning Devices And Reconstruct Ohi-Rail Grade Crossing AAR 503 455W. Arra Odot Tracking Id Is 12995. | Safety/Traffic Management | $250,000 |
| OHIO | MEDINA | E090803 | Replacement of rail, ballast, crossing surfaces, and other system improvements along the city's 3.6-mile long rail line. | Other | $949,795 |
| OHIO | PORTAGE | E090807 | Adding lanes in each direction plus additional turn lanes where necessary. | Pavement Improvement | $1,000,000 |
| OHIO | CUYAHOGA, SUMMIT | E090808 | District 12 ITS - Freeway Management System (MOT). TRAC Project.Moved from 2008 to 2009 due to Director request to redesign withoutfiber optic in the project. To be sold with D4 ITS project, PID77482 | Safety/Traffic Management | $26,662,500 |
| OHIO | STARK | E090846 | Widen Existing Road To 4 Lanes With Curb & Gutters, 5 Lanes To Be Provided At All Major Intersections Includes Storm Sewer & Traffic Signals. | Pavement Widening | $4,800,000 |
| OHIO | STATEWIDE | E090854 | RJ Corman Western Ohio Lines Rehabilitation (Allen, Van Wert, Auglaize, & Mercer Counties) | Other | $1,300,000 |
| OHIO | TRUMBULL | E090859 | Transportation issue to be corrected : Mill and resurface roadway including repair of curbs, sidewalks and install ADA curb ramps. Install / upgrade lighting. | Pavement Improvement | $711,060 |
| OHIO | VAN WERT | E090911 | Modernization of warning devices at the CFE grade crossings; AARs 532 743U, 532 744B, 532 745H, 532 747W, 532 749K, 532 750E & 532 748 D | Safety/Traffic Management | $778,600 |
| OHIO | SUMMIT | E090780 | Reconstruction. Adding turn lanes. | Other | $220,000 |
| OKLAHOMA | MUSKOGEE | STIM001 | I-40: FR MILE POST 281.67 TO 288.22 | Pavement Improvement | $26,884,000 |
| OKLAHOMA | LE FLORE | STIM008 | US-271: FR SH-112 WEST TO SH-9A (4 LN DIVIDED) REPLACE BR & REHB EXISTING LANES | Bridge Replacement | $5,968,238 |
| OKLAHOMA | ATOKA | STIM009 | SH-3: FROM 0.33 MI WEST OF THE PUSHMATAHA C/L EAST 1.82 MI | Pavement Widening | $3,818,000 |
| OKLAHOMA | GARVIN | STIM010 | I-35: FROM SH-29, NORTH 6.57 MI TO SH-19(MP 66.19 TO MP 72.76) | Pavement Improvement | $24,830,000 |
| OKLAHOMA | SEMINOLE | STIM011 | I-40: FROM 4.0 MI EAST OF SH 99, EAST 2.47 MI(MP 204.22 TO MP 206.69) | Pavement Improvement | $2,730,000 |
| OKLAHOMA | MCCLAIN | STIM013 | I-44: FROM US-62 (END OF HE BAILEY TP), NORTH 7.5 MI(MP 106.92 TO MP 114.42) | Pavement Improvement | $6,760,000 |
| OKLAHOMA | CANADIAN | STIM015 | I-40: FROM FROM MILE MARKER 132 TO MILE MARKER 136(PAVE & BR REHAB) | Pavement Improvement | $30,000,000 |