Minnesota • Hennepin County
Top 10 Largest Contracts
LIGHTING REPLACEMENT - 494 TO 694 (Federal... | MN / Hennepin |
$5,350,000
|
REBUILD CABLE MEDIAN BARRIER, ASSIGN RESOU... | MN / Hennepin |
$3,210,000
|
INTERCHANGE MODIFICATION TO ALLOW WB 494 T... | MN / Hennepin |
$1,077,000
|
LANDSCAPING BETWEEN TH5 AND I394 (Federal ... | MN / Hennepin |
$535,000
|
Total # Projects: | 13 |
Total # Contracts: | 4 |
Total $ Projects: | $82,378,565 |
Total $ Contracts: | $10,172,000 |
Other Counties
Project $ | |
---|---|
Aitkin | $7,482,433 |
Anoka | $180,000 |
Becker | $304,089 |
Beltrami | $4,770,972 |
Benton | $0 |
Big Stone | $5,143,074 |
Blue Earth | $4,065,812 |
Brown | $0 |
Carlton | $77,971 |
Carver | $1,651,400 |
Cass | $0 |
Chippewa | $10,373,737 |
Chisago | $16,551,935 |
Clay | $2,361,659 |
Clearwater | $1,257,948 |
Cook | $491,197 |
Cottonwood | $0 |
Crow Wing | $0 |
Dakota | $8,453,866 |
Dodge | $0 |
Douglas | $1,041,808 |
Faribault | $0 |
Fillmore | $0 |
Freeborn | $17,178,008 |
Goodhue | $1,784,727 |
Grant | $0 |
Houston | $0 |
Hubbard | $417,899 |
Isanti | $1,780,480 |
Itasca | $5,529,722 |
Jackson | $702,273 |
Kanabec | $1,322,178 |
Kandiyohi | $1,202,117 |
Kittson | $798,863 |
Koochiching | $0 |
Lac qui Parle | $0 |
Lake | $78,722 |
Lake of the Woods | $0 |
Le Sueur | $0 |
Lincoln | $1,130,303 |
Lyon | $308,307 |
McLeod | $323,937 |
Mahnomen | $0 |
Marshall | $602,838 |
Martin | $0 |
Meeker | $0 |
Mille Lacs | $10,644,590 |
Morrison | $1,752,901 |
Mower | $5,171,891 |
Murray | $0 |
Nicollet | $14,983,026 |
Nobles | $1,521,461 |
Norman | $0 |
Olmsted | $2,787,019 |
Otter Tail | $2,370,896 |
Pennington | $0 |
Pine | $854,128 |
Pipestone | $0 |
Polk | $7,533,452 |
Pope | $0 |
Ramsey | $2,548,086 |
Red Lake | $0 |
Redwood | $2,219,889 |
Renville | $459,776 |
Rice | $4,769,068 |
Rock | $66,806 |
Roseau | $0 |
St. Louis | $41,000,744 |
Scott | $7,499,000 |
Sherburne | $469,472 |
Sibley | $437,312 |
Stearns | $5,853,534 |
Steele | $1,363,231 |
Stevens | $263,338 |
Swift | $244,040 |
Todd | $872,252 |
Traverse | $1,441,828 |
Wabasha | $0 |
Wadena | $0 |
Waseca | $938,822 |
Washington | $8,053,126 |
Watonwan | $0 |
Wilkin | $115,403 |
Winona | $7,528,310 |
Wright | $2,136,106 |
Yellow Medicine | $1,119,361 |
Show/hide all |
Collaborate
These news organizations have followed up and written stories using this database:
- PBS NewsHour/Patchwork Nation analyzed how transportation stimulus funds were distributed across communities.
Add yourself to this list: News organizations are welcome to use data here in their own stories. Please credit ProPublica for providing the data. If you have a good story to share or collaborate on, contact Senior Editor Tom Detzel
Questions? Tips?
About This Data
Note: To build this database, ProPublica obtained two sets of records from the U.S. Department of Transportation. We cleaned it to remove duplicates and other discrepancies, but it may have mistakes we didn't catch. If you find one, please let us know and include any information that may help us verify the correction. Also, the federal data is based on the states’ monthly reporting and may not be up-to-date.
First, we received an updated copy of the national database of stimulus road and bridge projects as of Sept. 25. Separately, we obtained data that states filed to the federal government as part of the stimulus legislation's reporting requirements. These data list which contractors had been awarded particular projects. We were able to trace more than 90 percent of the funds to individual counties. In a few other cases, projects are statewide and cannot be narrowed to county or serve multiple counties. We’ve indicated those cases in the data.
Wherever possible, we matched DOT projects to state recovery filings. They did not match in every instance. The DOT projects, which total $19 billion, include hundreds of projects not yet associated with a contractor. The contractors' data totals about $13 billion in obligated funds. In a few cases, state contractors did not match a DOT project. Some projects also have multiple contractors. When there is no matching contractor information for a project, searches and lists will return a blank.
We're trying to make this information as accurate as possible, so if you see something that needs to be corrected, please let us know.
Read more...
Here are our tips for running background checks on stimulus contractors.
All projects for Hennepin. Not all projects have been awarded contracts.
Project Name | Contractor | County | Improvement Type | Amount |
---|---|---|---|---|
REBUILD CABLE MEDIAN BARRIER, ASSIGN RESOURCES (Federal ID: 09ES130) | CROWLEY COMPANY INC | Hennepin | Safety/Traffic Management | $3,210,000 |
LANDSCAPING BETWEEN TH5 AND I394 (Federal ID: 09ES132) | A & G INVESTMENTS INC | Hennepin | Other | $535,000 |
INTERCHANGE MODIFICATION TO ALLOW WB 494 TO ENTER WB 212 AS AN ADD LANE, LAYOUT WORK NEEDS TO BEGIN SOON (Federal ID: 09ES138) | VALLEY PAVING INC | Hennepin | Pavement Improvement | $1,077,000 |
LIGHTING REPLACEMENT - 494 TO 694 (Federal ID: 09ES143) | COLLISYS | Hennepin | Safety/Traffic Management | $5,350,000 |
TH 169 TO FERNBROOK - CONSTRUCT NEW 4-LANE FREEWAY AND INTERCHANGES (Federal ID: 09ES136) | No Contractor | Hennepin | Pavement Widening | $56,215,303 |
I-94:I-494 IN MAPLE GROVE TO CSAH 152 (BROOKLYN BLVD) IN BROOKLYN PARK, LANDSCAPING (Federal ID: 09ES155) | No Contractor | Hennepin | Transportation Enhancements | $214,000 |
TH 212: IN EDEN PRAIRE, AT CSAH 4 & DELL RD, LANDSCAPING (Federal ID: 09ES158) | No Contractor | Hennepin | Transportation Enhancements | $214,000 |
TH 7: AT WOODDALE AVE - CONST A GRADE SEPARATED INTERCHANGE, ETC & NEW BRIDGE #27B65 FR CP RR CR #5199 TO TH 100 SB (Federal ID: 09ES171) | No Contractor | Hennepin | New Bridge Construction | $3,465,000 |
CSAH 10: REALINE & WIDEN CSAH 10 & CSAH 101 FR CSAH 101 TO WEST OF PEONY LN (Federal ID: 09ES176) | No Contractor | Hennepin | Pavement Widening | $3,064,000 |
CEDAR LAKE TRAIL: IN MPLS, THIRD AV N. CONNECTION, ALONG THIRD AVE N FROM 12TH ST N TO 7TH ST N. (Federal ID: 10ES002) | No Contractor | Hennepin | Transportation Enhancements | $484,572 |
CSAH 153 (LOWRY AV): IN MPLS, REPL BR #2723 W #27B60 OVER MISSISSIPPI RIVER INCL APPR & STORMWATER QUALTIY IMPROVEMENTS. (Federal ID: 10ES013) | No Contractor | Hennepin | Bridge Replacement | $10,000,000 |
MSAS 159 (CAMPUS DR/26TH AV): MILL & OVLY FROM CR61 TO TEAKWOOD LN, RECONST FROM TEAKWOOD LN TO SYCAMORE LN, REPL CULV (Federal ID: 10ES028) | No Contractor | Hennepin | Pavement Improvement | $346,560 |
MSAS 109 (WINNETKA AV N): IN NEW HOPE, CSAH 10 TO 62ND AV, RECONSTRUCT. (Federal ID: 10ES035) | No Contractor | Hennepin | Pavement Improvement | $834,000 |