TX8022NW WORLD TRADE BRIDGE COVID-19 DECONTAMINATION PROJECT FOR AN ESTIMATED SQUAREFOOTAGE OF 49,922 SF
Total Committed
$209K
Product or Service Description
Facilities Operations Support Services
Contracting Agency
Effective Date
Sept. 30, 2020
Funding Department
PBS R7
Type
Firm fixed price
Solicitation Procedure
Only one source
Extent Competed
Not available for competition
Reason
Authorized By Statute (Far 6.302 5(A)(2)(I))
Recent Contract Actions
Contracts can have multiple “contract actions”: This is how agencies spend money for a specific purpose, adjust the amount committed or change the contract in a way that doesn’t affect the amount. That last scenario is usually indicated by a $0 action. If there is a contract action for a negative amount, it generally means the contract was adjusted or canceled.
Vendor | Description | Signed | Reason for Change | Amount Committed |
---|---|---|---|---|
KING & GEORGE, LLC | COVID 19 DETAILED CLEANING & DISINFECTION WORLD TRADE LPOE LAREDO TX0733NW 5,696SF | April 22, 2021 | $4,757 | |
KING & GEORGE, LLC | COVID 19 DETAILED CLEANING & DISINFECTION LAREDO COURTHOUSE TX0311ZZ 18,300SF | April 21, 2021 | $9,150 | |
KING & GEORGE, LLC | LINE 973 VERBAL NTE COVID 19 DETAILED CLEANING & DISINFECTION J&L LPOE LAREDO TX0325JL 4,531SF | March 23, 2021 | $3,081 | |
KING & GEORGE, LLC | COVID-19 DETAILED CLEANING WORLD TRADE BRIDGE LAREDO, TEXAS | March 17, 2021 | $2,652 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE COLOMBIA SOLIDARITY BRIDGE LAND PORT OF ENTRY (LPOE), LAREDO, TX | March 8, 2021 | $4,526 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE COLOMBIA SOLIDARITY BRIDGE LPOE LAREDO TEXAS. | March 8, 2021 | $2,685 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING COVID 9 AT JUAREZ & LINCOLN BRIDGE LAREDO, TEXAS | Feb. 10, 2021 | $3,222 | |
KING & GEORGE, LLC | EMERGENCY COVID-19 CLEANING AT JUAREZ LINCOLN BRIDGE LPOE LAREDO TEXAS | Feb. 5, 2021 | $11,770 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE JUAREZ LINCOLN BRIDGE LAND PORT OF ENTRY (LPOE) (TX0282JL) TERMINATION I35, LAREDO, TX | Feb. 3, 2021 | $4,680 | |
KING & GEORGE, LLC | DETAILED COVID 19 CLEANING AND DISINFECTING CONVENT BRIDGE LPOE LAREDO TX BUILDING NUMBER TX0325CV - LAREDO, TX | Feb. 2, 2021 | $3,606 | |
KING & GEORGE, LLC | COVID 19 CLEANING DISINFECTION J&L ADMIN BUILDINGTERMINATION I35 LAREDO TX | Jan. 26, 2021 | $3,778 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTION COVID19 GEORGE P KAZEN LAREDO FEDERAL COURTHOUSE TX0311ZZ LAREDO TEXAS | Jan. 26, 2021 | $2,685 | |
KING & GEORGE, LLC | COVID-19 CLEANING AND DISINFECTION - GPK BLDG TX0311ZZ 111420 USMS NOV 16, 2020 | Jan. 26, 2021 | $4,588 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING COVID 19 COLOMBIA BRIDGE TX0596CB LAREDO TEXAS - COMBINED INCIDENT | Jan. 26, 2021 | $6,138 | |
KING & GEORGE, LLC | COVID19 DETAILED CLEANING AND DISINFECTING AT THE JUAREZ LINCOLN BRIDGE TX0283JL TERMINATION I-35 LAREDO TX | Jan. 22, 2021 | $6,655 | |
KING & GEORGE, LLC | COVID 19 DETAILED CLEANING AND DISINFECTING AT THE JUAREZ&LINCOLN BUS PROCESSING BUILDING, LAREDO, TX 070284 | Jan. 22, 2021 | $3,368 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE COLOMBIA SOLIDARITY BRIDGE LAND PORT OF ENTRY, LAREDO, TX | Jan. 22, 2021 | $7,749 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE COLOMBIA SOLIDARITY BRIDGE LAND PORT OF ENTRY (LPOE), LAREDO, TX | Jan. 21, 2021 | $3,299 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE COLOMBIA SOLITARY BRIDGE LPOE (TX0596CB) | Jan. 21, 2021 | $4,757 | |
KING & GEORGE, LLC | DISINFECTION OF 5200SF REQUIRED TO STOP THE SPREAD OF THE NOVEL CORONAVIRUS AT GEORGE P. KAZAN FEDERAL COURTHOUSE 1300 VICTORIA ST LAREDO TX0311ZZ | Jan. 20, 2021 | $3,989 | |
KING & GEORGE, LLC | DISINFECTION OF 4500SF REQUIRED TO STOP THE SPREAD OF THE NOVEL CORONAVIRUS AT COLOMBIA BRIDGE LPOE TERMINATION SH-255 LAREDO TX 78045 | Jan. 20, 2021 | $3,452 | |
KING & GEORGE, LLC | DISINFECTION OF 3461SF REQUIRED TO STOP THE SPREAD OF THE NOVEL CORONAVIRUS AT WORLD TRADE BRIDGE LPOE TERMINATION I-69W LAREDO TX0733NW | Jan. 20, 2021 | $2,621 | |
KING & GEORGE, LLC | DISINFECTION OF 4600SF REQUIRED TO STOP THE SPREAD OF THE NOVEL CORONAVIRUS AT JUAREZ LINCOLN BRIDGE LPOE TERMINATION I-35 LAREDO TX0283JL | Jan. 15, 2021 | $3,529 | |
KING & GEORGE, LLC | DISINFECTION OF 6000SF REQUIRED TO STOP THE SPREAD OF THE NOVEL CORONAVIRUS AT GEORGE P KAZAN FB 1300 VICTORIA ST LAREDO TX0311ZZ | Jan. 15, 2021 | $4,603 | |
KING & GEORGE, LLC | COVID 19 DETAILED CLEANING & DISINFECTION COLUMBIA LPOE LAREDO TX8016CB | Jan. 14, 2021 | $22,384 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE COLOMBIA SOLIDARITY BRIDGE LAND PORT OF ENTRY (LPOE) (TX0306CB) TERMINATION SH-255., LAREDO, TX | Jan. 13, 2021 | $3,069 | |
KING & GEORGE, LLC | DEOBLIGATION OF FUNDS DUE TO TASK ORDER BEING AWARDED TO THE WRONG CONTRACTOR FOR COVID-19 CLEANING DISINFECTING TORNILLO LAND PORT OF ENTRY ADMIN BUILDING TX0711TG & KENNELS TX0712TG, TORNILLO, TX | Jan. 13, 2021 | Funding Only Action | -$26,267 |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE CONVENT BORDER LAND PORT OF ENTRY (TX0116CV), LAREDO, TX | Jan. 11, 2021 | $3,409 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE CONVENT BRIDGE TX0116CV, 100 CONVENT ST LAREDO TX | Jan. 6, 2021 | $3,238 | |
KING & GEORGE, LLC | COVID 19 DETAILED CLEANING & DISINFECTION WORLD TRADE BRIDGE LPOE EL PASO TX0733NW | Dec. 29, 2020 | $2,847 | |
KING & GEORGE, LLC | THE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE FUNDS FROM THE ORIGINAL AWARD TO REFLECT THE FINAL PROPOSAL AMOUNT OF $2,329.00. | Dec. 29, 2020 | Funding Only Action | -$1,176 |
KING & GEORGE, LLC | THE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE FUNDS TO REFLECT THE PROPOSED AMOUNT. GEORGE P KAZEN FEDERAL BUILDING, TX0311ZZ, LAREDO, TX | Oct. 8, 2020 | Funding Only Action | -$6,227 |
KING & GEORGE, LLC | COVID-19 CLEANING DISINFECTING LOCATED GEORGE P KAZEN FEDERAL BUILDING, TX0311ZZ, LAREDO, TX | Sept. 30, 2020 | $13,072 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE GEORGE P KAZEN FEDERAL BUILDING TX0311ZZ, 1300 VICTORIA ST., LAREDO, TEXAS 78040-5016 | Sept. 25, 2020 | $3,505 | |
KING & GEORGE, LLC | COVID 19 DETAILED CLEANING&DISINFECTION AT GEORGE P KAZEN FEDERAL BUILDING TX0311ZZ | Sept. 25, 2020 | $3,505 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTING AT THE CONVENT BORDER STATION BUILDING TX0116CV,100 CONVENT AVE, LAREDO TEXAS | Sept. 25, 2020 | $2,715 | |
KING & GEORGE, LLC | COVID-19 CLEANING DISINFECTING TORNILLO LAND PORT OF ENTRY ADMIN BUILDING TX0711TG&KENNELS TX0712TG - TORNILLO, TX | Sept. 24, 2020 | $26,267 | |
KING & GEORGE, LLC | COVID-19 CLEANING DISINFECTING LOCATED COLOMBIA BORDER STATION BUILDING TX0596CB - TERMINATION SH-255 LAREDO TX | Sept. 24, 2020 | $4,230 | |
KING & GEORGE, LLC | DETAILED CLEANING AND DISINFECTION COVID-19 JUAREZ&LINCOLN LAREDO | Sept. 22, 2020 | $6,556 | |
KING & GEORGE, LLC | COVID CLEANING | Sept. 22, 2020 | $2,889 | |
KING & GEORGE, LLC | DEFINITIZED COVID CLEANING | Sept. 2, 2020 | Funding Only Action | -$15,164 |
KING & GEORGE, LLC | COVID CLEANING BLDG TX0596CB | Aug. 14, 2020 | $23,722 | |
KING & GEORGE, LLC | ACTUAL AMOUNT CHARGED FOR DETAILED CLEANING IS $24,713.92 | Aug. 3, 2020 | Funding Only Action | -$31,199 |
KING & GEORGE, LLC | TX8022NW WORLD TRADE BRIDGE COVID-19 DECONTAMINATION PROJECT FOR AN ESTIMATED SQUAREFOOTAGE OF 49,922 SF | July 9, 2020 | $55,913 |
About this data
This data comes from the Federal Procurement Data System, which includes all contracts worth $10,000 or more. We look at all contracts that are tagged with the procurement code for COVID-19 or otherwise started in 2020 and contain “COVID-19” in the description. Department of Defense contracting data is subject to a 90-day delay before it appears in the data.