HomeAll ContractsContract
REPLACE 480V SWITCHGEAR IN SUBSTATION 1100. MODIFICATION EXTENDS COMPLETION DATE ESTABLISHED AT NOTICE TO PROCEED BY 60 DAYS TO AUGUST 11, 2020 TO RESUME ON SITE ACTIVITY AND EVALUATE DENIED ACCESS TO KSC IMPACTS PENDING SUBMISSION.
Total Committed
$0
Product or Service Description
Repair or Alteration of Electronic and Communications Facilities
Total Potential Value
$789K
Effective Date
July 12, 2019
Funding Department
NASA KENNEDY SPACE CENTER
Type
Firm fixed price
Solicitation Procedure
Negotiated proposal/quote
Extent Competed
Full and open competition after exclusion of sources

Recent Contract Actions

Contracts can have multiple “contract actions”: This is how agencies spend money for a specific purpose, adjust the amount committed or change the contract in a way that doesn’t affect the amount. That last scenario is usually indicated by a $0 action. If there is a contract action for a negative amount, it generally means the contract was adjusted or canceled.

Vendor Description Signed Reason for Change Amount Committed
MILITARY CONSTRUCTION CORPORATION REPLACE 480V SWITCHGEAR IN SUBSTATION 1100. MODIFICATION EXTENDS COMPLETION DATE ESTABLISHED AT NOTICE TO PROCEED BY 60 DAYS TO AUGUST 11, 2020 TO RESUME ON SITE ACTIVITY AND EVALUATE DENIED ACCESS TO KSC IMPACTS PENDING SUBMISSION. June 8, 2020 Supplemental Agreement For Work Within Scope $0
About this data
This data comes from the Federal Procurement Data System, which includes all contracts worth $10,000 or more. We look at all contracts that are tagged with the procurement code for COVID-19 or otherwise started in 2020 and contain “COVID-19” in the description. Department of Defense contracting data is subject to a 90-day delay before it appears in the data.
Close Comment Creative Commons Donate Email Facebook Mobile Phone Podcast Print RSS Search Search Twitter WhatsApp
Current site Current page