BAILEY EDWARD DESIGN, INC. $32,447 Contract : Bailey Edward architecure was contracted to conduct a Pre-Design study related to the repair of the exterior brick and re-sealing of the windows at teh reasearch facility in Madison. Agriculture, Department of / Agricultural Research Service 9/09/2009
JOHNSON-MCADAMS FIRM, P.A., THE $28,838 Contract : A-E design, bid phase and construction phase services to repair/replace the 100-Ton Air Conditioner and Cooling Tower with Aircooled Chiller and associated piping for the Harned Building located at the ARS Research Facility located in Starkville, MS. Agriculture, Department of / Agricultural Research Service 8/18/2009
MERRICK & COMPANY $24,774 Contract : Akron USDA/ARS Bldg 1 HVAC Repairs - Design Services. Agriculture, Department of / Agricultural Research Service 8/11/2009
STV INCORPORATED $34,794 Contract : Replace Air Distribution system at the Appalachian Fruit Research Station, Kearneysville, WV Agriculture, Department of / Agricultural Research Service 7/16/2009
PRO-MARK SERVICES, INC. $1,511,585 Contract : RECOVERY PROJECT FOR REPLACEMENT OF LABORATORY FACILITIES? HVAC SYSTEMS AND COMPONENTS at the Red River Agricultural Research Center 1605 Albrecht Blvd. in Fargo, N.D. Agriculture, Department of / Agricultural Research Service 9/29/2009
DELTA ENGINEERS, ARCHITECTS, & LAND SURVEYORS, P.C. $256,636 Contract : Bid Phase and Construction Administration Services for the Replacement of a Chiller, Generator, and UST at the HNRCA in Boston, MA. Agriculture, Department of / Agricultural Research Service 9/30/2009
CLARO COMPANY INC $381,795 Contract : Contractor shall install a new HVAC system and exhaust for fume hood and all necessary controls. Installing insulation above the ceiling and underside of roof decking. Installing ceiling system and light fixtures. Agriculture, Department of / Agricultural Research Service 9/24/2009
KSA-KRANTZ SYSTEMS & ASSOCIATES, LLC $109,166 Contract : Repair fire alarm system Agriculture, Department of / Agricultural Research Service 7/29/2009
ZGA ARCHITECTS AND PLANNERS, CHARTERED $12,911 Contract : PREDESIGN SERVICES FOR REPLACMENT HVAC & ELECTRICAL/CONTROL SYSTEMS Agriculture, Department of / Agricultural Research Service 8/13/2009
TECTONICS $116,290 Contract : Provide Architect Engineer construction support services for WRRC, Recivery - Repair Exterior Finishes, West Annex Building and Service Building, Albany, CA. Agriculture, Department of / Agricultural Research Service 4/05/2010
BERNARD JOHNSON CORPORATION $1,914,635 Contract : Design Update for Phase 8 (Power Plant Upgrade) and Phase 9A & 9B (Renovation of Pilot Plant Laboratories) at the Eastern Regional Research Center (ERRC) - Major Renovation to ERRC to address deferred maintenance of critical mechanical, electrical and plu Agriculture, Department of / Agricultural Research Service 7/10/2009
ARCINI CONSTRUCTION $151,584 Contract : Ft. Collins, CO. Relacing building 1 Cooling Towers for NCGRP constant temperature rooms and heat exchangers Agriculture, Department of / Agricultural Research Service 10/14/2009
BAILEY EDWARD DESIGN, INC. $71,993 Contract : Bailey Edward architecture has been contracted to perform architectural services related to the repair of the windows and replacement of the roof at the USDA facility in West Lafayette, IN. Agriculture, Department of / Agricultural Research Service 9/09/2009
BAILEY EDWARD DESIGN, INC. $43,649 Contract : Bailey Edward architecture was contracted to replace the glazing systems in Greenhouse 400-40 in St. Paul, Minnesota. Agriculture, Department of / Agricultural Research Service 9/09/2009
TOLAND & MIZELL ARCHITECTS/APPLIED ENGINEERING SOLUTIONS - JOINT VENTURE $106,543 Contract : Electrical and HVAC upgrades Building 35 and Roof Replacement various Buildings Southeast Poultry Research Laboratory, Athens, GA The purpose of this project is to address critical deferred maintenance needs at the research location. The most pressing n Agriculture, Department of / Agricultural Research Service 7/20/2009
TOLAND & MIZELL ARCHITECTS APPLIED ENGINEERING SOLUTIONS JOINT VENTURE $138,199 Contract : HVAC Upgrades Buildings 1, 4, and 34 Southeast Poultry Research Laboratory, Athens, GA CA Services for the following project designed under separate TO. SEPRL has 3 facilities that are operated as BSL-3 enhanced. Bldgs 1 & 4 are laboratory facilities o Agriculture, Department of / Agricultural Research Service 10/08/2009
PERKINS + WILL, INC. $189,132 Contract : Architectural and engineering design for the design of the replacement of standby electrical generator at the National Animal Disease Center, Ames, Iowa. Agriculture, Department of / Agricultural Research Service 7/30/2009
EWINGCOLE INC $19,273 Contract : The old existing windows at the Robert w Holley Center are difficult to maintain, energy inefficient and admit water to the interior of the building envelope. This contract will coordinate replacement windows specification by visiting the site for measur Agriculture, Department of / Agricultural Research Service 9/01/2009
JOHNSON-MCADAMS FIRM, P.A., THE $44,624 Contract : A-E design, bid phase and construction phase services to replace roofs on Buildings 1,2,4,9,12 at USDA ARS Research Facility located in Starkville, MS. Agriculture, Department of / Agricultural Research Service 7/29/2009
TECTONICS $20,067 Contract : Provide Architect-Engineer pre-design and subsequent design services for Design Replacement Roof at the Columbia Plateau Conservation Research Center, Pendleton, OR. The purpose of the award is to investigate and design solutions to repair the deteriorate Agriculture, Department of / Agricultural Research Service 8/04/2009
HDR ARCHITECTURE, INC. $373,799 Contract : A&E services to replace underground water and sanitary sewer lines Agriculture, Department of / Agricultural Research Service 7/29/2009
HDR ARCHITECTURE INC, $112,601 Contract : Architect-Engineering Services to replace roofs on large animal buildings 3 & 4, and utility building 155. Agriculture, Department of / Agricultural Research Service 7/29/2009
PERKINS + WILL, INC. $130,394 Contract : Investigative report to address replacement of boilers and steam distribution systems serving research facilities at Beltsville Agricultural Research Center, Beltsville, Maryland. Agriculture, Department of / Agricultural Research Service 7/06/2009
RMF ENGINEERING, INC. $264,001 Contract : Replacement of the deteriorated building envelope, repair of brick facade, and replacement of the plumbing systems. Agriculture, Department of / Agricultural Research Service 7/08/2009
AJC ARCHITECTS, P.C. $7,231 Contract : USDA Logan Greenhouse HVAC Renovation, Architectural & Engineering services. Agriculture, Department of / Agricultural Research Service 8/20/2009
BERNARD JOHNSON CORPORATION $2,200,928 Contract : A-E Services for the major renovation of the National Agricultural Utilization Research Center to address deferred maintenance of critical mechanical, electrical and plumbing systems, and incidental repairs (Phase 3 and 4). Services include design, bid p Agriculture, Department of / Agricultural Research Service 7/14/2009
BAILEY EDWARD DESIGN, INC. $46,943 Contract : Bailey Edward architure was contracted to provide architecture and engineering services related to the repair of building #17 finishes in East Lansing, MI. Agriculture, Department of / Agricultural Research Service 9/09/2009
BAILEY EDWARD DESIGN, INC. $124,421 Contract : Bailey Edward architecture has been contracted to perform architectural and engineering services related to the repair of the mechanical and electrical systems at the USDA facility in St. Paul, MN. Agriculture, Department of / Agricultural Research Service 9/10/2009
AECOM SERVICES, INC. $445,457 Contract : Design Update for Modernization fo the Laboratory/Office Building at Fort Keogh Livestock and Range Research Laboratory Agriculture, Department of / Agricultural Research Service 7/10/2009
EWINGCOLE INC $19,273 Contract : Design Replacement Windows Agriculture, Department of / Agricultural Research Service 9/01/2009
STV INCORPORATED $19,665 Contract : Add emergency generator and automatic transfer switch for an insect laboratory at the University of Delaware. Agriculture, Department of / Agricultural Research Service 9/21/2009
BAILEY EDWARD DESIGN, INC. $103,954 Contract : Bailey Edward architecture has been contracted to perform architectural and engineering services related to the repair of the mechanical systems and the repair of the greenhouse cooling systems at the Dairy Forage reseach facility in Madison, WI. Agriculture, Department of / Agricultural Research Service 9/09/2009
JOHNSON-MCADAMS FIRM, P.A., THE $12,518 Contract : A-E design, bid phase and construction phase services to replace the existing main electrical switchgear for the Harned Building located at the ARS Research Facility located in Starkville, MS. Agriculture, Department of / Agricultural Research Service 8/13/2009
ZGA ARCHITECTS AND PLANNERS, CHARTERED $53,376 Contract : Design phase services for research greenhouse mechanical systems and chiller replacement. Riverside, California. Agriculture, Department of / Agricultural Research Service 11/20/2009
JACOBS FACILITIES INC. $380,968 Contract : Design and Design Update Services for Various Projects at WRRC, Albany, California. Jacobs will provide the design and design updates to combine phases and expedite construction for the following projects at WRRC: 1. Phase 3B Food Processing Laboratory 2 Agriculture, Department of / Agricultural Research Service 3/16/2009
BAILEY EDWARD DESIGN, INC. $21,754 Contract : Bailey Edward architecture was contracted to perform architecture and engineering services related to the repair of the electrical distribution system at Building #1 in East Lansing, MI. Agriculture, Department of / Agricultural Research Service 9/10/2009
JOHNSON-MCADAMS FIRM, P.A., THE $26,900 Contract : A-E design, bid phase and construction phase services to install a new Emergency Generator and Automatic Transfer Switch for the Harned Building located at the ARS Research Facility located in Starkville, MS. Agriculture, Department of / Agricultural Research Service 8/18/2009
RMF ENGINEERING, INC. $976,642 Contract : The U.S. Department of Agriculture (USDA), Agricultural Research Service (ARS) requires the A-E contractor to perform architectural and engineering services for design update/ reduce scope, for the U.S. National Arboretum Administration Building Renovatio Agriculture, Department of / Agricultural Research Service 7/16/2009
BARLOW EDDY JENKINS, PA $740,927 Contract : Update drawings for renovation of 5- story main research facility, (Building #1) for the USDA-ARS in Stoneville, MS. Scope of the update includes: Update the specs in UFG format; Architecture and Engineerings services to: indicate staging, construction sc Agriculture, Department of / Agricultural Research Service 7/21/2009
TECTONICS $9,254 Contract : Provide Fire Protection Engineering services during construction, Main and West Annex Buildings Albany, California. The purpose of the award is to bring the existing fire protection standpipes to meet today's fire codes. The services performed will be to Agriculture, Department of / Agricultural Research Service 10/22/2009
PEACHTREE MECHANICAL, INC. $2,449,409 Contract : Upgrade Mechanical Systems for Buildings 34, 1 and 4 at the USDA Southeast Poultry Reseach Facility Athens, GA Agriculture, Department of / Agricultural Research Service 10/08/2009
VIGIL CONTRACTING, INC. $1,357,177 Contract : Brick Repair Phase 4 and 5 (South Face of the Tower and North, East, South and West elevations of the Admin Bldg. includes 300 SF of unsatisfactory brick replacement; Agriculture, Department of / Agricultural Research Service 10/06/2009
STV INCORPORATED $39,364 Contract : Replace roof of the Jean Mayer Human Nutrition Resource Center in Boston MA. Agriculture, Department of / Agricultural Research Service 7/02/2009
SHELTONDEAN, INC. $446,340 Contract : Replacement of Systems and Finishes in Insectary. Roof Repairs and Replacement of systems and finishes in Laboratories space Agriculture, Department of / Agricultural Research Service 10/19/2009
MCCALL & ASSOCIATES - AIA - ARCHITECTS $19,527 Contract : A-E Design and CM/CA services to replace the 10-ton and 15-ton HVAC units serving the West Lab at the East Campus at the Grazinglands Research Lab in El Reno, Oklahoma. Agriculture, Department of / Agricultural Research Service 9/29/2009
MCCALL & ASSOCIATES - AIA - ARCHITECTS $76,682 Contract : A-E Design and Cm/CA services to remove the existing roofs on eight buildings and replace them with new energy efficient roofing systems at the ARS Laboratory Facilities in College Station, Texas. Agriculture, Department of / Agricultural Research Service 9/29/2009
MAURER-STUTZ, INC. $109,337 Contract : This contract is for the engineering design and drawing preparation for bidding and construction of repairs to mechanical systems and installation of emergency electrical located at SERL, W. Lafayette, IN Agriculture, Department of / Agricultural Research Service 9/09/2009
MAURER-STUTZ, INC. $40,617 Contract : Pre-Design, Design, Bidding, & Construction Management Services for Repair Mechanical Systems, ADOL, E. Lansing, MI Agriculture, Department of / Agricultural Research Service 9/09/2009
JACOBS ENGINEERING GROUP INC. $2,423,304 Contract : Design and Design Update, Bid Phase, and Construction Phase Services for Various Projects at Western Regional Research Center, Albany, California. Jacobs will provide the design and design updates to combine phases and expedite construction for the follow Agriculture, Department of / Agricultural Research Service 7/08/2009
SERGENT MECHANICAL SYSTEMS (INC) $301,386 Contract : Fire Alarms and fire suppression Agriculture, Department of / Agricultural Research Service 10/21/2009
BB & K CONSTRUCTION, LLC $99,850 Contract : Replace electrical switchgear Harned Laboratory building Mississippi State, Mississippi Agriculture, Department of / Agricultural Research Service 12/08/2009
AIRGO USA LLC $243,000 Contract : Replace the roofs, on Buildings #1-24 and #2-24 and on the Feedmill, Building #3 at the UNITED STATES DEPARTMENT OF AGRICULTURE, Agricultural Research Service, Roman L. Hruska U.S. Meat Animal Research Center, Clay Center, Nebraska Agriculture, Department of / Agricultural Research Service 9/14/2009
ARCINI CONSTRUCTION $147,461 Contract : Replace Light Fixtures at NCGRP. Agriculture, Department of / Agricultural Research Service 10/14/2009
JOHNSON CONTROLS, INC. $46,143 Contract : Install new Metasys superviosr controller, install new computer workstation, install and commission DX9100 Controllers, replace five zone temp sensors, three humidity sensors and outside air temp sensor Agriculture, Department of / Agricultural Research Service 10/07/2009
VIGIL CONTRACTING, INC. $2,663,096 Contract : Tower window replacement, NAL Building, Beltsville, MD to include removal of all existing finishes at punch window openings; remove and replace existing punch windows and window walls; mock-up and testing of each type of window. MOD #1 dated 09/28/2010 i Agriculture, Department of / Agricultural Research Service 1/29/2010
TECTONICS $9,916 Contract : Provide services during construction including construction submittal reviews, answering and resolving field issues, and conducting site inspections. Agriculture, Department of / Agricultural Research Service 1/29/2010
E-CORP. $129,361 Contract : LOGAN - REPLACEMENT OF HVAC SYSTEMS AND COMPONENTS IN RESEARCH GREENHOUSES Agriculture, Department of / Agricultural Research Service 3/26/2010
AD VERITAS CONSTRUCTION CO. INC. $85,265 Contract : Replace the HVAC System in Building 3 Rooms 300 and 302 Agriculture, Department of / Agricultural Research Service 1/15/2010
BB & K CONSTRUCTION, LLC $99,850 Contract : Replace existing electrical switchboard at the Harned Laboratory Building in Starkville, Ms. Agriculture, Department of / Agricultural Research Service 12/08/2009
ROBBERT CONSTRUCTION, INC. $287,905 Contract : Repair Mechanical System ADOL, East Lansing, MI Agriculture, Department of / Agricultural Research Service 3/25/2010
RED WILK CONSTRUCTION, INC. $1,515,745 Contract : Replacement of laboratory facilities HVAC systems and components Project at the Roman L. Hruska U.S. Meat Animal Research Center (USMARC), Clay Center, Nebraska. Agriculture, Department of / Agricultural Research Service 2/18/2010
VIGIL CONTRACTING, INC. $2,193,985 Contract : Provide all labor, material and equipment necessary to demolish and renovate designated restrooms including tile, fixtures, toilet partitions, plumbing and mechanical piping at the National Agricultural Library (NAL), Beltsville, Maryland. Agriculture, Department of / Agricultural Research Service 2/02/2010
VETERANS CONSTRUCTION, LLC $2,700,426 Contract : Chiller, Generator and Underground Storage Tank Replacement Agriculture, Department of / Agricultural Research Service 1/05/2010
PATRIOT CONSTRUCTION, INC. $644,875 Contract : Provide material, labor, and equipment for roof rehabilitation of 4-story laboratory building (Main Building - North Wing); 4-story laboratory building (West Annex Buildig, Labs); 1-story building (West Annex Building, Director's Wing); and 2-story boiler Agriculture, Department of / Agricultural Research Service 10/08/2009
S&M AND ASSOCIATES, INC. $439,610 Contract : Replace Roofs, Buildings No. 1,2,4,9 and 12 USDA, ARS, Mississippi State, MS One Subcontract awarded to 2SW for roofing.One modification issued for 19,623.00 for installation of backets on roof. Agriculture, Department of / Agricultural Research Service 2/19/2010
TECTONICS $5,825 Contract : Provide construction support services including submittal reviews, resolving field issues and answering field questions, conduct site inspections. Agriculture, Department of / Agricultural Research Service 2/16/2010
IMPERIAL ROOF SYSTEMS CO. $498,895 Contract : Replace roof & paint exterior building 3 at the Center for Grain & Animal Health Research -- USDA Manhattan KS Agriculture, Department of / Agricultural Research Service 2/19/2010
AFFILIATED CONSTRUCTION GROUP, INCORPORATED $3,226,370 Contract : Modernization of the Fort Keogh Livestock and Range Reasearch Laboratory Agriculture, Department of / Agricultural Research Service 1/07/2010
POWER PRO INC $204,193 Contract : Provide construction services for repair/ replace roof at the main building, at the Columbia Plateau Conservation Research Center, in Pendleton, OR. Agriculture, Department of / Agricultural Research Service 2/16/2010
CORE CONSTRUCTION SERVICES OF ILLINOIS, INC. $14,378,314 Contract : Major renovation to the National Center for Agricultural Utilization Research in Peoria, Illinois to address critical deferred maintenance repairs of the mechanical, Electrical, and Plumbing Systems Agriculture, Department of / Agricultural Research Service 1/19/2010
STV INCORPORATED $790,894 Contract : Provide design bridging documentation and CA Services for building 306 renovations at the BARC campus. Agriculture, Department of / Agricultural Research Service 2/19/2010
CONSTRUCTION SERVICE CORPORATION $274,283 Contract : Replacement of 2 roofs on 2 lab/office buildings in Corvallis, Oregon Agriculture, Department of / Agricultural Research Service 1/15/2010
ROBBERT CONSTRUCTION, INC. $94,541 Contract : Building 1-Repair Electrical Distribution System ADOL, East Lansing, MI Agriculture, Department of / Agricultural Research Service 3/24/2010
TECTONICS $5,825 Contract : Provide construction support services including submittal reviews, resolving field issues and answering field questions, conduct site inspections. Agriculture, Department of / Agricultural Research Service 2/16/2010
BAILEY EDWARD DESIGN, INC. $374,436 Contract : Bailey Edward architecture was contracted to perform architectural and engineering services related the replacement of the electrical systems in low containment animal facilities buildings #3 and #4 in Ames, IA. Agriculture, Department of / Agricultural Research Service 6/11/2010
BARLOW EDDY JENKINS, PA $148,824 Contract : Bid phase services and soil testing for hazardous substances in the area the utility tunnel will be location Agriculture, Department of / Agricultural Research Service 4/23/2010
NAGEL-TVJ JV 3 $797,509 Contract : DFRC Repair Mechanical Systems/CCRU Repair Greenhouse Cooling System, Madison, WI Agriculture, Department of / Agricultural Research Service 5/24/2010
TGR SERVICES, INC. $680,881 Contract : Replacement of research greenhouse mechanical systems (NCGR) and replacement of chiller (USSL), in Riverside, CA Agriculture, Department of / Agricultural Research Service 5/18/2010
WELCH CONSTRUCTION INC. $521,829 Contract : REPLACE MAIN BUILDING HVAC, PLANT GENETIC RESOURCES UNIT, GENEVA N.Y. Agriculture, Department of / Agricultural Research Service 5/14/2010
SAF, INC. $469,730 Contract : Roof and Window replacement Agriculture, Department of / Agricultural Research Service 5/12/2010
BAILEY EDWARD DESIGN, INC. $25,236 Contract : Bailey Edward architecture was contracted to perform architecture and engineering bidding phase services for the replacement of electrical systems in low containment animal facilities #3 and #4 at the National Animal Disease Center in Ames, IA Agriculture, Department of / Agricultural Research Service 6/11/2010
GREENLAND ENTERPRISES, INC. $363,200 Contract : Replace Multi-Zone Air Handler System at the Appalachian Fruit Research Station (AFRS) in Kearneysville, WV Agriculture, Department of / Agricultural Research Service 5/14/2010
JE HURLEY CONSTRUCTION, INC. $510,466 Contract : Repair Building 1 HVAC Systems Agriculture, Department of / Agricultural Research Service 6/01/2010
BAILEY EDWARD DESIGN, INC. $306,435 Contract : Bailey Edward architecture was contracted to perform architectural and engineering services related to the exterior brick repair and window re-sealing projects at the research facility in Madison, WI. Agriculture, Department of / Agricultural Research Service 6/03/2010
WIEBOLT ELECTRIC, INC $1,716,010 Contract : UPGRADE OF ELECTRICAL AND MECHANICAL EQUIPMENT AT THE CEREAL DISEASE LABORATORY Agriculture, Department of / Agricultural Research Service 6/03/2010
AMERICAN PLANT PRODUCTS & SERVICES INC $364,188 Contract : Greenhouse 400/401 Glazing Systems Agriculture, Department of / Agricultural Research Service 4/22/2010
MPS ENGINEERS, P.C. $1,100,000 Contract : Replace Large Animal Building Roofs 3 & 4, and Utility Building Roof 155 at the National Animal Disease Center (NADC), Ames, Iowa Agriculture, Department of / Agricultural Research Service 5/28/2010
SCHNEIDER ELECTRIC USA, INC. $35,142 Contract : Install electric panel surge protection and meter upgrade Agriculture, Department of / Agricultural Research Service 6/07/2010
ZZ-SQUARED LLC $103,200 Contract : Replace the Heating and Air conditioning system in the Annex Building Agriculture, Department of / Agricultural Research Service 5/03/2010
HOAR CONSTRUCTION, LLC $32,887,274 Contract : The project is a major renovation to the Jamie Whitten Delta States Research Center in Stoneville, MS to address deferred maintenance of critical architectural, mechanical, electrical, plumbing systems, repair of the deteriorated building envelope, and in Agriculture, Department of / Agricultural Research Service 6/30/2010
HUNTER ROBERTS CONSTRUCTION GROUP, L.L.C. $14,416,552 Contract : Construction for the ERRC Site located in Wyndmoor, PA including renovations for approximately 3,815 Square Meters. The project is multi-phased, encompassing two separate buildings including Service Building #5 Power Plant and Research Laboratory Building Agriculture, Department of / Agricultural Research Service 5/25/2010
SOCON, LLC $231,644 Contract : Replace 100 Ton Chiller/ Cooling Tower Agriculture, Department of / Agricultural Research Service 5/14/2010
COMPUCRAFT, INC. $306,994 Contract : GENERATOR INSTALLATION Agriculture, Department of / Agricultural Research Service 6/01/2010
BAKER ELECTRIC, INC. $4,673,322 Contract : Replacement of Electrical Systems in Low Containment Animal Facilities Buildings 3 and 4 at the National Animal Disease Center, Ames, IA Agriculture, Department of / Agricultural Research Service 4/01/2010
PERKINS & WILL GROUP, LTD., THE $244,299 Contract : Architectural and engineering design for the replacement of the underground contaminated waste piping system at the National Animal Disease Center, Ames, Iowa. Agriculture, Department of / Agricultural Research Service 4/29/2010
ROBBERT CONSTRUCTION, INC. $256,916 Contract : Repair Building 17 Finishes ADOL, East Lansing, MI Agriculture, Department of / Agricultural Research Service 6/04/2010
ZGA ARCHITECTS AND PLANNERS, CHARTERED $7,826 Contract : Construction support services for research greenhouse mechanical systems and chiller replacement. Riverside, California. Agriculture, Department of / Agricultural Research Service 5/21/2010
SWINERTON BUILDERS $13,256,187 Contract : TAS Recovery - Major renovation to the Western Reginal Research Center (WRRC) to address deferred maintenance of critical mechanical, electrical, and plumbing systems, repairs. Phases 3b through 6. Agriculture, Department of / Agricultural Research Service 6/03/2010
SMART LLC $354,225 Contract : FURNISH ALL LABOR, MATERIAL, EQUIP, ETC TO REPLACE STEAM AND CONDENSATE LINES, PLANT GENETIC RESOURCES UNIT, GENEVA, NY Agriculture, Department of / Agricultural Research Service 5/13/2010
HONEYWELL INTERNATIONAL INC. $313,947 Contract : Replace air handling units. Replace zone dampers with VAV boxes. Repace pneumatic controls with digital controls. Replace direct drive exhaust fans with epoxy coated fans with VFDs. Replace 4 electrical panels. Agriculture, Department of / Agricultural Research Service 9/08/2010
MPS ENGINEERS, P.C. $1,192,576 Contract : Construction Services for replacement of underground animal waste lines connecting buildings 3, 4, 125, and 155. Agriculture, Department of / Agricultural Research Service 9/14/2010
MPS ENGINEERS, P.C. $2,540,808 Contract : Construction services to replace underground water and sewer lines at the National Animal Disease Center (NADC) in Ames, Iowa. Agriculture, Department of / Agricultural Research Service 7/08/2010
KEN TILLAGE CONSTRUCTION COMPANY, LLC $117,969 Contract : Replace electrical switchgear, harned building Agriculture, Department of / Agricultural Research Service 9/09/2010
DH ORTEGA CONSTRUCTION, LLC $35,090 Contract : Repair/replace deteriorated roofing systems, Building 102 and 103, at the USDA, ARS, PWA, Small Grains and Germplasm Research Unit in Aberdeen, ID Agriculture, Department of / Agricultural Research Service 7/01/2010
J. & L. MAVILIA INCORPORATED $3,138,143 Contract : Replacement of Boiler System in Boiler Plant #014. Agriculture, Department of / Agricultural Research Service 9/10/2010
DELTA ENGINEERS, ARCHITECTS, & LAND SURVEYORS, P.C. $85,836 Contract : Item No. 0001 Construction Phase A-E Services for the HVAC Laboratory System at the Plant Genetic Resources Unit (PGRU) in Geneva, NY; Item No. 0002 Construction Phase A-E Services for the Steam and Condensate Lines (Administration Building) at the Plant Agriculture, Department of / Agricultural Research Service 9/23/2010
JOHNSON-MCADAMS FIRM, P.A., THE $44,624 Contract : Buildings No. 1,2,4,9,12 Agriculture, Department of / Agricultural Research Service 7/29/2009
AMERICAN CONTRACTING, LLC $135,443 Contract : Replace Windows at the Central Great Plains Research Station in Akron, Colorado. Agriculture, Department of / Agricultural Research Service 7/22/2010
MERRICK & COMPANY $24,828 Contract : Akron CO Building 1 HVAC Repairs - Construction Administration Agriculture, Department of / Agricultural Research Service 7/26/2010
VIGIL CONTRACTING, INC. $355,054 Contract : Install Emeregency Generator at the Beneficial Insects Introduction Research Unit (BIIRU), Newark, DE Agriculture, Department of / Agricultural Research Service 9/24/2010
MISSISSIPPI POWER COMPANY $177,942 Contract : Provide recommission measures on bldg. HVAC, energy controls, and emergency stand-by electric generation for the Southern Lab. Research Center. Agriculture, Department of / Agricultural Research Service 9/16/2010
JOHNSON-MCADAMS FIRM, P.A., THE $28,838 Contract : A-E design services to repair/replace the MS State 100-ton air conditioner and cooling tower Agriculture, Department of / Agricultural Research Service 8/18/2009
PERKINS & WILL GROUP, LTD., THE $154,350 Contract : Decentralization of the steam plant and distribution system serving the 100 Area research facilities at BARC Agriculture, Department of / Agricultural Research Service 9/20/2010
VIGIL CONTRACTING, INC. $2,391,284 Contract : Replacement of all boiler systems and components (removal of three boilers and replacement with three 350 HP firetube boilers) at BARC Building 309 Agriculture, Department of / Agricultural Research Service 9/27/2010
JM INDUSTRIAL SUPPLY, INC / RIVER CITY CONSTRUCTION LLC JOINT VENTURE $2,845,767 Contract : The award is for construction work at the USDA - ARS - Dairy Forage Research Center, located in Madison, Wisconsin. The construction work includes: removal of the existing exterior brick, damaged exterior sheating, insulation and interior gypsum board, Agriculture, Department of / Agricultural Research Service 9/13/2010
ABIDE INTERNATIONAL, INC. $1,778,705 Contract : Repair Exterior Finishes West Annex Building and Service Building, Western Regional Research Center Agriculture, Department of / Agricultural Research Service 7/09/2010
SOCO CONTRACTING COMPANY, INC $4,101,503 Contract : Replacement of Critical Mechanical and Electrical Systems in Main Laboratory at the Southeast Poultry Research Laboratory in Athens, GA Agriculture, Department of / Agricultural Research Service 7/22/2010
JOHNSON-MCADAMS FIRM, P.A., THE $28,899 Contract : A-E design services to install an emergency generator at MS State Agriculture, Department of / Agricultural Research Service 8/18/2009
PERKINS & WILL GROUP, LTD., THE $252,980 Contract : A-E servies to provide construction management in support of replacement of boiler systems in BLDG 309. Agriculture, Department of / Agricultural Research Service 9/23/2010
VETERANS CONSTRUCTION, LLC $615,771 Contract : Roof Replacement at the USDA Jean Mayer Human Nutrition Research Center Agriculture, Department of / Agricultural Research Service 9/07/2010
MPS ENGINEERS, P.C. $1,555,971 Contract : Install Emergency Standby Generator at the National Amimal Disease Center (NADC) in Ames, Iowa. Agriculture, Department of / Agricultural Research Service 8/26/2010
BISCAYNE CONTRACTORS, INC. $8,343,183 Contract : This contract is for critical deferred maintenance of the U.S. National Arboretum Administration Building in Washington, DC. Agriculture, Department of / Agricultural Research Service 8/02/2010
BLOOM COMPANIES, LLC $539,513 Contract : Replace Chiller Agriculture, Department of / Agricultural Research Service 9/20/2010
PATRIOT COMPANY, INC $17,189 Contract : Install replacement windows at the robert Holley Center for Agriculture and Health, Ithaca, NY Agriculture, Department of / Agricultural Research Service 9/01/2010
PERKINS & WILL GROUP, LTD., THE $225,002 Contract : Construction Management support to address replacement of boilers, electrical and steam distribution system serving the Beltsville research campus Agriculture, Department of / Agricultural Research Service 9/09/2010
PERKINS & WILL GROUP, LTD., THE $296,811 Contract : Re-Commissioning, to Inspect Mechanical System Deficiencies at Plant Science Institute on the BARC campus. Agriculture, Department of / Agricultural Research Service 7/01/2010
BARLOW EDDY JENKINS, PA $2,570,639 Contract : A/E Services for construction management phase of Jamie Whitten Delta State Research Center Agriculture, Department of / Agricultural Research Service 8/18/2010
PERKINS & WILL GROUP, LTD., THE $34,715 Contract : Construction management services for repair of water tower at Appalachian Fruit Research Station. Agriculture, Department of / Agricultural Research Service 9/24/2010
STV INCORPORATED $84,000 Contract : Construction administration to replace roof of the Jean Mayer Human Nutrition Research Center in Boston, MA. Agriculture, Department of / Agricultural Research Service 9/13/2010
STV INCORPORATED $44,918 Contract : Construction administration for replacement of multi-zone air handling system in Kearneysville, WV. Agriculture, Department of / Agricultural Research Service 9/24/2010
RD SUMNER INC $158,351 Contract : Replace HVAC System and components in campus west laboratory facility in El Reno, OK. Agriculture, Department of / Agricultural Research Service 9/15/2010
STV INCORPORATED $32,000 Contract : Construction administration for installation of emergency generator for BIIRU in Newark, DE. Agriculture, Department of / Agricultural Research Service 9/22/2010
E & E ENTERPRISES GLOBAL, INC. $628,161 Contract : The project generally consists of the replacement/repairs to mechanical equipment and systems and the installation of an emergency electrical system at National Soil Erosion Laboratory located in West Lafayette, Indiana. The project components include the Agriculture, Department of / Agricultural Research Service 7/30/2010
ADVANCETECH SYSTEMS 2, INC. $1,412,369 Contract : Erosion Control improvements at the ARS Facility in College Station, TX. Agriculture, Department of / Agricultural Research Service 9/20/2010
PERKINS & WILL GROUP, LTD., THE $588,989 Contract : Recommissioning of Facility at the Southern Horticulture Laboratory in Poplarville, MS. Agriculture, Department of / Agricultural Research Service 6/30/2010
MCCALL & ASSOCIATES - AIA - ARCHITECTS $43,414 Contract : A/E Construction Phase Inspection Services. Agriculture, Department of / Agricultural Research Service 9/28/2010
INTEGRIS ROOFING SERVICES LLC $1,169,543 Contract : Reroof buildings 7,8,9,10,11,12,1 1A Agriculture, Department of / Agricultural Research Service 9/20/2010
TRADEMASTERS SERVICE, INC. $2,313,426 Contract : Decentralization of the 100 Series Area Steam Stystems of the Betlsville Agricultural Research Center in Beltsville, MD Agriculture, Department of / Agricultural Research Service 9/14/2010
TOLAND & MIZELL ARCHITECTS APPLIED ENGINEERING SOLUTIONS JOINT VENTURE $169,696 Contract : CA Services for Building 35 Southeast Poultry Research Laboratory, Athens, GA The A/E will provide all services associated with bid phases services and construction administration as required for the construction associated with the Electrical and HVAC up Agriculture, Department of / Agricultural Research Service 7/29/2010
WHITING-TURNER CONTRACTING COMPANY, THE $12,982,889 Contract : Design-Build Services necessary for the Building 306 Renovations at the Beltsville Agricultural Research Center, Beltsville, MD. Agriculture, Department of / Agricultural Research Service 8/10/2010
TMI COATINGS, INC. $625,706 Contract : Repair Water Tower at the Appalachian Fruit Research Station (AFRS) Agriculture, Department of / Agricultural Research Service 8/27/2010
EWING COLE, INC. $13,200 Contract : Construction management services for installation of replacement windows. Agriculture, Department of / Agricultural Research Service 9/30/2010
MISSISSIPPI POWER COMPANY $177,942 Contract : Provide recommission measures on bldg. HVAC, energy contols, and emergency stand-by electric generation for the Southern Lab. Research Center. Agriculture, Department of / Agricultural Research Service 9/16/2010