Recovery Tracker

How Much Stimulus Funding is Going to Your County?

Agricultural Research Service

Total Spending

$177,869,020

Parent agency (Agriculture, Department of )

$56,786,094,544

StateFunding
Arizona $313,947
California $16,909,424
Colorado $1,220,553
Delaware $458,254
District of Columbia $8,343,183
Florida $446,340
Georgia $6,965,350
Idaho $155,346
Illinois $14,600,443
Indiana $1,279,220
Iowa $11,948,749
Kansas $584,160
Maryland $33,420,842
Massachusetts $3,572,833
Michigan $748,676
Minnesota $2,248,268
Mississippi $38,753,198
Montana $3,226,370
Nebraska $1,758,745
New York $1,030,825
North Dakota $1,511,585
Oklahoma $158,351
Oregon $3,288,174
Pennsylvania $15,517,003
South Carolina $381,795
Texas $2,721,535
Utah $136,592
Virginia $645,964
West Virginia $1,033,824
Wisconsin $4,489,471

Showing only the top (by amount) 50 entries. Go here for the full list

Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.

Recipient Amount Type Federal Dept./Agency Date
HOAR CONSTRUCTION, LLC $32,887,274 Contract Agriculture, Department of / Agricultural Research Service 6/30/2010
: The project is a major renovation to the Jamie Whitten Delta States Research Center in Stoneville, MS to address deferred maintenance of critical architectural, mechanical, electrical, plumbing systems, repair of the deteriorated building envelope, and in
HUNTER ROBERTS CONSTRUCTION GROUP, L.L.C. $14,416,552 Contract Agriculture, Department of / Agricultural Research Service 5/25/2010
: Construction for the ERRC Site located in Wyndmoor, PA including renovations for approximately 3,815 Square Meters. The project is multi-phased, encompassing two separate buildings including Service Building #5 Power Plant and Research Laboratory Building
CORE CONSTRUCTION SERVICES OF ILLINOIS, INC. $14,378,314 Contract Agriculture, Department of / Agricultural Research Service 1/19/2010
: Major renovation to the National Center for Agricultural Utilization Research in Peoria, Illinois to address critical deferred maintenance repairs of the mechanical, Electrical, and Plumbing Systems
SWINERTON BUILDERS $13,256,187 Contract Agriculture, Department of / Agricultural Research Service 6/03/2010
: TAS Recovery - Major renovation to the Western Reginal Research Center (WRRC) to address deferred maintenance of critical mechanical, electrical, and plumbing systems, repairs. Phases 3b through 6.
WHITING-TURNER CONTRACTING COMPANY, THE $12,982,889 Contract Agriculture, Department of / Agricultural Research Service 8/10/2010
: Design-Build Services necessary for the Building 306 Renovations at the Beltsville Agricultural Research Center, Beltsville, MD.
BISCAYNE CONTRACTORS, INC. $8,343,183 Contract Agriculture, Department of / Agricultural Research Service 8/02/2010
: This contract is for critical deferred maintenance of the U.S. National Arboretum Administration Building in Washington, DC.
BAKER ELECTRIC, INC. $4,673,322 Contract Agriculture, Department of / Agricultural Research Service 4/01/2010
: Replacement of Electrical Systems in Low Containment Animal Facilities Buildings 3 and 4 at the National Animal Disease Center, Ames, IA
SOCO CONTRACTING COMPANY, INC $4,101,503 Contract Agriculture, Department of / Agricultural Research Service 7/22/2010
: Replacement of Critical Mechanical and Electrical Systems in Main Laboratory at the Southeast Poultry Research Laboratory in Athens, GA
AFFILIATED CONSTRUCTION GROUP, INCORPORATED $3,226,370 Contract Agriculture, Department of / Agricultural Research Service 1/07/2010
: Modernization of the Fort Keogh Livestock and Range Reasearch Laboratory
J. & L. MAVILIA INCORPORATED $3,138,143 Contract Agriculture, Department of / Agricultural Research Service 9/10/2010
: Replacement of Boiler System in Boiler Plant #014.
JM INDUSTRIAL SUPPLY, INC / RIVER CITY CONSTRUCTION LLC JOINT VENTURE $2,845,767 Contract Agriculture, Department of / Agricultural Research Service 9/13/2010
: The award is for construction work at the USDA - ARS - Dairy Forage Research Center, located in Madison, Wisconsin. The construction work includes: removal of the existing exterior brick, damaged exterior sheating, insulation and interior gypsum board,
VETERANS CONSTRUCTION, LLC $2,700,426 Contract Agriculture, Department of / Agricultural Research Service 1/05/2010
: Chiller, Generator and Underground Storage Tank Replacement
VIGIL CONTRACTING, INC. $2,663,096 Contract Agriculture, Department of / Agricultural Research Service 1/29/2010
: Tower window replacement, NAL Building, Beltsville, MD to include removal of all existing finishes at punch window openings; remove and replace existing punch windows and window walls; mock-up and testing of each type of window. MOD #1 dated 09/28/2010 i
BARLOW EDDY JENKINS, PA $2,570,639 Contract Agriculture, Department of / Agricultural Research Service 8/18/2010
: A/E Services for construction management phase of Jamie Whitten Delta State Research Center
MPS ENGINEERS, P.C. $2,540,808 Contract Agriculture, Department of / Agricultural Research Service 7/08/2010
: Construction services to replace underground water and sewer lines at the National Animal Disease Center (NADC) in Ames, Iowa.
PEACHTREE MECHANICAL, INC. $2,449,409 Contract Agriculture, Department of / Agricultural Research Service 10/08/2009
: Upgrade Mechanical Systems for Buildings 34, 1 and 4 at the USDA Southeast Poultry Reseach Facility Athens, GA
JACOBS ENGINEERING GROUP INC. $2,423,304 Contract Agriculture, Department of / Agricultural Research Service 7/08/2009
: Design and Design Update, Bid Phase, and Construction Phase Services for Various Projects at Western Regional Research Center, Albany, California. Jacobs will provide the design and design updates to combine phases and expedite construction for the follow
VIGIL CONTRACTING, INC. $2,391,284 Contract Agriculture, Department of / Agricultural Research Service 9/27/2010
: Replacement of all boiler systems and components (removal of three boilers and replacement with three 350 HP firetube boilers) at BARC Building 309
TRADEMASTERS SERVICE, INC. $2,313,426 Contract Agriculture, Department of / Agricultural Research Service 9/14/2010
: Decentralization of the 100 Series Area Steam Stystems of the Betlsville Agricultural Research Center in Beltsville, MD
BERNARD JOHNSON CORPORATION $2,200,928 Contract Agriculture, Department of / Agricultural Research Service 7/14/2009
: A-E Services for the major renovation of the National Agricultural Utilization Research Center to address deferred maintenance of critical mechanical, electrical and plumbing systems, and incidental repairs (Phase 3 and 4). Services include design, bid p
VIGIL CONTRACTING, INC. $2,193,985 Contract Agriculture, Department of / Agricultural Research Service 2/02/2010
: Provide all labor, material and equipment necessary to demolish and renovate designated restrooms including tile, fixtures, toilet partitions, plumbing and mechanical piping at the National Agricultural Library (NAL), Beltsville, Maryland.
BERNARD JOHNSON CORPORATION $1,914,635 Contract Agriculture, Department of / Agricultural Research Service 7/10/2009
: Design Update for Phase 8 (Power Plant Upgrade) and Phase 9A & 9B (Renovation of Pilot Plant Laboratories) at the Eastern Regional Research Center (ERRC) - Major Renovation to ERRC to address deferred maintenance of critical mechanical, electrical and plu
ABIDE INTERNATIONAL, INC. $1,778,705 Contract Agriculture, Department of / Agricultural Research Service 7/09/2010
: Repair Exterior Finishes West Annex Building and Service Building, Western Regional Research Center
WIEBOLT ELECTRIC, INC $1,716,010 Contract Agriculture, Department of / Agricultural Research Service 6/03/2010
: UPGRADE OF ELECTRICAL AND MECHANICAL EQUIPMENT AT THE CEREAL DISEASE LABORATORY
MPS ENGINEERS, P.C. $1,555,971 Contract Agriculture, Department of / Agricultural Research Service 8/26/2010
: Install Emergency Standby Generator at the National Amimal Disease Center (NADC) in Ames, Iowa.
RED WILK CONSTRUCTION, INC. $1,515,745 Contract Agriculture, Department of / Agricultural Research Service 2/18/2010
: Replacement of laboratory facilities HVAC systems and components Project at the Roman L. Hruska U.S. Meat Animal Research Center (USMARC), Clay Center, Nebraska.
PRO-MARK SERVICES, INC. $1,511,585 Contract Agriculture, Department of / Agricultural Research Service 9/29/2009
: RECOVERY PROJECT FOR REPLACEMENT OF LABORATORY FACILITIES? HVAC SYSTEMS AND COMPONENTS at the Red River Agricultural Research Center 1605 Albrecht Blvd. in Fargo, N.D.
ADVANCETECH SYSTEMS 2, INC. $1,412,369 Contract Agriculture, Department of / Agricultural Research Service 9/20/2010
: Erosion Control improvements at the ARS Facility in College Station, TX.
VIGIL CONTRACTING, INC. $1,357,177 Contract Agriculture, Department of / Agricultural Research Service 10/06/2009
: Brick Repair Phase 4 and 5 (South Face of the Tower and North, East, South and West elevations of the Admin Bldg. includes 300 SF of unsatisfactory brick replacement;
MPS ENGINEERS, P.C. $1,192,576 Contract Agriculture, Department of / Agricultural Research Service 9/14/2010
: Construction Services for replacement of underground animal waste lines connecting buildings 3, 4, 125, and 155.
INTEGRIS ROOFING SERVICES LLC $1,169,543 Contract Agriculture, Department of / Agricultural Research Service 9/20/2010
: Reroof buildings 7,8,9,10,11,12,1 1A
MPS ENGINEERS, P.C. $1,100,000 Contract Agriculture, Department of / Agricultural Research Service 5/28/2010
: Replace Large Animal Building Roofs 3 & 4, and Utility Building Roof 155 at the National Animal Disease Center (NADC), Ames, Iowa
RMF ENGINEERING, INC. $976,642 Contract Agriculture, Department of / Agricultural Research Service 7/16/2009
: The U.S. Department of Agriculture (USDA), Agricultural Research Service (ARS) requires the A-E contractor to perform architectural and engineering services for design update/ reduce scope, for the U.S. National Arboretum Administration Building Renovatio
NAGEL-TVJ JV 3 $797,509 Contract Agriculture, Department of / Agricultural Research Service 5/24/2010
: DFRC Repair Mechanical Systems/CCRU Repair Greenhouse Cooling System, Madison, WI
STV INCORPORATED $790,894 Contract Agriculture, Department of / Agricultural Research Service 2/19/2010
: Provide design bridging documentation and CA Services for building 306 renovations at the BARC campus.
BARLOW EDDY JENKINS, PA $740,927 Contract Agriculture, Department of / Agricultural Research Service 7/21/2009
: Update drawings for renovation of 5- story main research facility, (Building #1) for the USDA-ARS in Stoneville, MS. Scope of the update includes: Update the specs in UFG format; Architecture and Engineerings services to: indicate staging, construction sc
TGR SERVICES, INC. $680,881 Contract Agriculture, Department of / Agricultural Research Service 5/18/2010
: Replacement of research greenhouse mechanical systems (NCGR) and replacement of chiller (USSL), in Riverside, CA
PATRIOT CONSTRUCTION, INC. $644,875 Contract Agriculture, Department of / Agricultural Research Service 10/08/2009
: Provide material, labor, and equipment for roof rehabilitation of 4-story laboratory building (Main Building - North Wing); 4-story laboratory building (West Annex Buildig, Labs); 1-story building (West Annex Building, Director's Wing); and 2-story boiler
E & E ENTERPRISES GLOBAL, INC. $628,161 Contract Agriculture, Department of / Agricultural Research Service 7/30/2010
: The project generally consists of the replacement/repairs to mechanical equipment and systems and the installation of an emergency electrical system at National Soil Erosion Laboratory located in West Lafayette, Indiana. The project components include the
TMI COATINGS, INC. $625,706 Contract Agriculture, Department of / Agricultural Research Service 8/27/2010
: Repair Water Tower at the Appalachian Fruit Research Station (AFRS)
VETERANS CONSTRUCTION, LLC $615,771 Contract Agriculture, Department of / Agricultural Research Service 9/07/2010
: Roof Replacement at the USDA Jean Mayer Human Nutrition Research Center
PERKINS & WILL GROUP, LTD., THE $588,989 Contract Agriculture, Department of / Agricultural Research Service 6/30/2010
: Recommissioning of Facility at the Southern Horticulture Laboratory in Poplarville, MS.
BLOOM COMPANIES, LLC $539,513 Contract Agriculture, Department of / Agricultural Research Service 9/20/2010
: Replace Chiller
WELCH CONSTRUCTION INC. $521,829 Contract Agriculture, Department of / Agricultural Research Service 5/14/2010
: REPLACE MAIN BUILDING HVAC, PLANT GENETIC RESOURCES UNIT, GENEVA N.Y.
JE HURLEY CONSTRUCTION, INC. $510,466 Contract Agriculture, Department of / Agricultural Research Service 6/01/2010
: Repair Building 1 HVAC Systems
IMPERIAL ROOF SYSTEMS CO. $498,895 Contract Agriculture, Department of / Agricultural Research Service 2/19/2010
: Replace roof & paint exterior building 3 at the Center for Grain & Animal Health Research -- USDA Manhattan KS
SAF, INC. $469,730 Contract Agriculture, Department of / Agricultural Research Service 5/12/2010
: Roof and Window replacement
SHELTONDEAN, INC. $446,340 Contract Agriculture, Department of / Agricultural Research Service 10/19/2009
: Replacement of Systems and Finishes in Insectary. Roof Repairs and Replacement of systems and finishes in Laboratories space
AECOM SERVICES, INC. $445,457 Contract Agriculture, Department of / Agricultural Research Service 7/10/2009
: Design Update for Modernization fo the Laboratory/Office Building at Fort Keogh Livestock and Range Research Laboratory
S&M AND ASSOCIATES, INC. $439,610 Contract Agriculture, Department of / Agricultural Research Service 2/19/2010
: Replace Roofs, Buildings No. 1,2,4,9 and 12 USDA, ARS, Mississippi State, MS One Subcontract awarded to 2SW for roofing.One modification issued for 19,623.00 for installation of backets on roof.

Showing only the top (by amount) 50 entries. Go here for the full list