Listing all stimulus spending by amount, in descending order. Return to National Park Service page
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Type | Description | Federal Dept./Agency | Date |
---|---|---|---|---|---|
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $77,609 | Contract | : Cost Estimating Quality Assurance at Denver Service Center. Provide quality assrance reviews and construction cost estimates submitted to the DSC by A/E firms at major project milestons (i.e. predesign, schematic design, design development and construct | Interior, Department of / National Park Service | 1/13/2010 |
MACTEC ENGINEERING AND CONSULTING, INC. | $809,281 | Contract | : ARCHITECTURAL & ENGINEERING DESIGN DEVELOPMENT AND CONSTRUCTION DOCUMENT SERVICES FOR THE FURNACE CREEK-DEATH VALLEY VISITOR CENTER REHABILITATION PROJECT, LOCATED AT DEATH VALLEY NATIONAL PARK, CA. | Interior, Department of / National Park Service | 1/29/2010 |
SALMON HVAC | $63,900 | Contract | : Replace 5 roof top units at Glenn Canyon National Park in Bullfrog UT. | Interior, Department of / National Park Service | 2/11/2010 |
KNIGHTO, LLC | $41,167 | Contract | : Procurement of Wood-Mizer Portable Sawmill for NCR-PRWI-Prince William Forest Park. | Interior, Department of / National Park Service | 1/08/2010 |
E-CORP. | $46,911 | Contract | : Repave Interpretive trail at Aztec Ruins National Monument | Interior, Department of / National Park Service | 3/24/2010 |
SKY CONSTRUCTION AND ENGINEERING, INC. | $90,922 | Contract | : Rehabilitate Maintenance Building - Coronado National Memorial | Interior, Department of / National Park Service | 9/14/2008 |
URS GROUP, INC. | $58,626 | Contract | : Prepare Environmental Site Assessments and provide additional environmental screening data for the LEKT Wastewater system at Olympic National Park in Port Angeles, WA for use by NPS. | Interior, Department of / National Park Service | 2/22/2010 |
BAE SYSTEMS SAN FRANCISCO SHIP REPAIR INC. | $255,290 | Contract | : The scope of work is to install auxiliary shoring and debris containment equipment on or around the historic Steam Schooner Wapama and the barge upon which she is located and to remove all objects and materials unrelated to her stabilization from the barg | Interior, Department of / National Park Service | 3/11/2010 |
ENTERPRISE RENT-A-CAR GOVERNMENT PROCUREMENT, INC | $8,774 | Contract | : TAS::14 1041::TAS RECOVERY GRSM PMIS # 90550 PARKING AREA IMPROVEMENTS AT THE SINKS GREAT SMOKY MOUNTAIN NATIONAL PARK. | Interior, Department of / National Park Service | 1/20/2010 |
COLORADO FENESTRA, INC. | $12,111 | Contract | : 37 Windows for Building Renovation | Interior, Department of / National Park Service | 2/11/2010 |
CTA INC. | $31,207 | Contract | : A/E Services-The Contractor shall provide architectural and engineering services associated with the customization and updating of proto-type construction documents for a site specific 8 unit residential facility. | Interior, Department of / National Park Service | 9/03/2009 |
TAMICO INC. | $32,600 | Contract | : Drainage repair work at the Baker Farm, Monocacy National Battlefield, Frederick, MD | Interior, Department of / National Park Service | 3/05/2010 |
HORD, COPLAN, MACHT INC | $192,340 | Contract | : This contract is to produce Bridging Documents for the DC War Memorial restoration. Tasks include the refinement and packaging the design drawings (Design Development Level) and Specifications into a bid package to be bid upon by Design-Build Contractors. | Interior, Department of / National Park Service | 3/09/2010 |
QUINN EVANS ARCHITECTS INC | $294,870 | Contract | : Preparation of contract documents for the rehabilitation of the Union Building Phase 2 Interior at Keweenaw National Historical Park, Calumet, Michigan | Interior, Department of / National Park Service | 9/10/2009 |
SCHINDLER ELEVATOR CORPORATION | $338,893 | Contract | : Perry Mounment Elevator Renovation | Interior, Department of / National Park Service | 8/12/2009 |
REILLY CONSTRUCTION, INC | $194,469 | Contract | : Furnish and install solar water heaters in four comfort stations in the Flamingo Dist. campground. | Interior, Department of / National Park Service | 1/27/2010 |
SOUTHWEST CONSERVATION CORPS | $101,870 | Grant | Conservation Activities by Youth Service Organizations: Provide the care and maintenance of the park's farm, including the fields, kitchen garden and livestock. Specifically: 1. Maintain the hayfield by irrigating, weeding and completing similar tasks to maintain a healthy source of winter feed for r the park's... Show more | Interior, Department of / National Park Service | 3/17/2010 |
SEAL MASTERS, INC. | $55,153 | Contract | : Installation of Curb, Gutter and Walkways at Buckhorn, Chickasaw National Recreation Area, Sulphur, Oklahoma | Interior, Department of / National Park Service | 2/10/2010 |
RED WILK CONSTRUCTION INC | $179,041 | Contract | : Chop Seal Park Roads | Interior, Department of / National Park Service | 9/14/2009 |
WEISZ & SONS, INC. | $86,000 | Contract | : Replace the existing sewage lift station at the Knife River Indian Villages NHS Visitor Center. The existing lift station facilities will be abandoned and a new submersible pump wet well lift station and valve vault will be constructed. | Interior, Department of / National Park Service | 2/16/2010 |
ANDREWS AND ANDERSON ARCHITECT PC | $41,043 | Contract | : This project consisted of an onsite Design Charette for Juniper Campground at Bandelier National Monument in New Mexico. Members from the A/E team travelled to the site to conduct the meeting in which discussions were held and to provide analysis of the | Interior, Department of / National Park Service | 9/04/2009 |
KPI #2 INC. | $60,518 | Contract | : Roofing replacement - Charcoal House Barns - Hopewell Furnace National Park | Interior, Department of / National Park Service | 1/28/2010 |
SKY CONSTRUCTION AND ENGINEERING, INC. | $43,136 | Contract | : Install 800Lf of electrical wire to corrals | Interior, Department of / National Park Service | 10/13/2009 |
SKY CONSTRUCTION AND ENGINEERING, INC. | $118,638 | Contract | : Re-roofing residences in three different parks. Ft. Bowie, Chiricahua, and Saguaro East. | Interior, Department of / National Park Service | 9/09/2009 |
ARCHITECTURAL RESOURCES GROUP, INC. | $57,928 | Contract | : Title 1 Preliminary Design Services - Removal of accessibility barriers to meet ADA requirements at Fort Point National Historic Site, California. | Interior, Department of / National Park Service | 3/15/2010 |
TOYOTA-LIFT OF MINNESOTA INC. | $34,223 | Contract | : Toyota 7FGKU40 forklift | Interior, Department of / National Park Service | 2/05/2010 |
SEEDS | $49,500 | Grant | Conservation Activities by Youth Service Organizations: YOUTH CORPS WORKS WITH NATIONAL PARK SERVICE PERSONNEL TO CONTROL 200 ACRES OF BABY'S BREATH. | Interior, Department of / National Park Service | 2/23/2010 |
PERRYMAN BUILDING AND CONSTRUCTION SERVICES, INC. | $427,198 | Contract | : Construction of Train Station Canopies, Valley Forge National Historical Park: Construction of two train station canopies and associated lighting. This construction shall provide two canopies adjacent tot the recently rehabilitated train station and new | Interior, Department of / National Park Service | 3/11/2010 |
CUSTOM COPPER AND SLATE LTD. | $502,747 | Contract | : Repair Longfellow Piazzas and Balustrades | Interior, Department of / National Park Service | 10/28/2009 |
PARKS AND RECREATION, CALIFORNIA DEPARTMENT OF | $809,846 | Grant | Redwood National Park Cooperative Management with the State of California: The Mill Creek Watershed Restoration Project includes road removal, culvert replacement, forest and in-stream restoration and monitoring. The project is being implemented to advance the rehabilitation of the Mill Creek Additition, a 2002 State Park's acqui... Show more | Interior, Department of / National Park Service | 1/07/2010 |
WISS, JANNEY, ELSTNER ASSOCIATES, INC. | $384,274 | Contract | : GOGA 65433 Radio Infrastructure - Construction Phase Services; Building 314, The Presidio, San Francisco | Interior, Department of / National Park Service | 3/25/2010 |
STEWART'S PROFESSIONAL TREE SERVICE & LANDSCAPING, INC. | $512,910 | Contract | : storm damage cleanup at Blue Ridge NP | Interior, Department of / National Park Service | 4/29/2009 |
PARKS AND RECREATION, CALIFORNIA DEPARTMENT OF | $40,000 | Grant | Redwood National Park Cooperative Management with the State of California: This award is for the engineering and design for the reconstruction of a failed stream crossing on Rock Creek Road in California State Park's Mill Creek Acquisition located in the North Coast Redwoods District. A December 200008 storm caused the complete f... Show more | Interior, Department of / National Park Service | 3/23/2010 |
E-SUV, LLC | $45,384 | Contract | : ELECTRIC VEHICLES FRO GILA CLIFF DWELLINGS NATIONAL MONUMENT | Interior, Department of / National Park Service | 12/03/2009 |
JAYNES CORPORATION | $2,060,649 | Contract | : This project shall design and construct two four bedroom duplexes and one three bedroom triplex, parking, site and utility work, and a grid tied photovoltaic system, complete and ready for use in the Cow Creek Housing Area at Death Valley National Park lo | Interior, Department of / National Park Service | 2/18/2010 |
SWANK ENTERPRISES | $6,282,322 | Contract | : Glacier National Park, Glacier County, Montana Correct Critical Health & Life Safety Hazards at Many Glacier Hotel | Interior, Department of / National Park Service | 2/04/2010 |
GABEL ASSOCIATES INC. | $73,117 | Contract | : Energy and Water Audits: Yosemite National Park | Interior, Department of / National Park Service | 2/23/2010 |
ALFONSO GALLEGOS INC | $330,086 | Contract | : Redwood National Park - Tree Thinning | Interior, Department of / National Park Service | 11/18/2009 |
DICK ANDERSON CONSTRUCTION, INC. | $898,844 | Contract | : CONSTRUCT A MICRO-HYDRO ELECTRIC FACILITY | Interior, Department of / National Park Service | 3/31/2010 |
SUNWIZE TECHNOLOGIES, INC. | $23,521 | Contract | : solar modules and related parts. | Interior, Department of / National Park Service | 2/01/2010 |
URS GROUP, INC. | $86,164 | Contract | : TAS::14 1041::TAS RECOVERY COLO PMIS # 152684 - CONSTRUCTION MANAGEMENT SERVICES CONSISTING OF ON-SITE INSPECTION, SPECIAL INSPECTIONS, ADMINISTRATION OF THE CONSTRUCTION CONTRACT, OFFICE SERVICES, AND SITE VISITS. Site inspection, quality assurance inspe | Interior, Department of / National Park Service | 10/26/2009 |
ANDERSON BURTON CONSTRUCTION, INC. | $488,178 | Contract | : Roof Replacement | Interior, Department of / National Park Service | 3/26/2010 |
BETTISWORTH NORTH ARCHITECTS AND PLANNERS INC. | $77,845 | Contract | : A-E Title III Construction Administration Services,DENA. Project 'Relocate Emergency Services and LE Operations. | Interior, Department of / National Park Service | 2/11/2010 |
AU AUTHUM KI, INC. | $237,543 | Contract | : CEBR Overlook Rehabilitation ARRA PROJECT. Rehabilitate North View and Chessman Overlooks at Cedar Breaks National Monument. | Interior, Department of / National Park Service | 4/09/2010 |
ANDREWS AND ANDERSON ARCHITECT PC | $382,648 | Contract | : This project will rehabilitate the failing potable water storage and distribution system and provide adequate fire protection at the Ash Mountain Headquarters and housing area in Sequoia National Park. This project will also replace one 100,000 and one 5 | Interior, Department of / National Park Service | 7/20/2009 |
SOUTHWEST CONSTRUCTION & PROPERTY MANAGEMENT | $472,402 | Contract | : The purpose of this project is to reroof numerous historic buildings within the Golden Gate Park National Recreation Area located in San Francisco County, San Francisco, CA. We are to perform the following tasks, but not limited to the buildings listed: | Interior, Department of / National Park Service | 3/18/2010 |
JOHN G. WAITE ASSOCIATES, ARCHITECTS, PLLC | $93,150 | Contract | : Title II Design and Contract documents to rehabilitate the home of Franklin Delano Roosevelt. | Interior, Department of / National Park Service | 3/05/2010 |
MUELLER,GLENN | $57,275 | Contract | : Furnish and install wheelchair lift | Interior, Department of / National Park Service | 3/15/2010 |
FORRESTER CONSTRUCTION COMPANY | $2,907,540 | Contract | : The contract award includes the following items: cleaning and restoration of the existing District of Columbia War Memorial Monument; rehabilitation and restoration of existing landscaping, bluestone walkways, and site utilities. | Interior, Department of / National Park Service | 5/05/2010 |
SOUTHEAST ALASKA GUIDANCE ASSOCIATION | $122,480 | Grant | Conservation Activities by Youth Service Organizations: National Park Service - Exotic Plant Management Team used SAGA's 8-person AmeriCorps crews to remove invasive plant species in 7 of Alaska's National Parks during the 2010 season: Denali Nat'l Park - 8wks, Glacier Bay Nat'l Park - 4wks, Katmai N Nat'l Park ... Show more | Interior, Department of / National Park Service | 9/21/2009 |
HEERY INTERNATIONAL, INC. | $55,000 | Contract | : Rehabilitate Visitor Center (West Building) and Exhibits Commissioning Authority Services | Interior, Department of / National Park Service | 3/10/2010 |
BERGMANN ASSOCIATES INC | $88,775 | Contract | : Replacement/Rehabilitation of Tinkers Creek Acqueduct - Phase 2 | Interior, Department of / National Park Service | 8/20/2009 |
YORK RIVER ELECTRIC, INC. | $540,000 | Contract | : Repainting traffic marking on various roads in Great Smoky Mountains National Park. | Interior, Department of / National Park Service | 9/22/2009 |
CREATIVE ENERGIES LLC | $492,674 | Contract | : Design and construction of the Photovoltaic Systems at Water Treatment Plant at Mesa Verde National Park, CO. | Interior, Department of / National Park Service | 1/19/2010 |
TUSCA II, INC. | $88,577 | Contract | : Provide all labor, equipment and materials to replace approximately 580 linear feet of obsolete water line and removal of 150 linear feet of abandoned water line at the Nusbaum Pass area of Mesa Verde National Park. | Interior, Department of / National Park Service | 6/11/2009 |
HAMMER LGC, INC. | $1,485,249 | Contract | : Construct Museum facility | Interior, Department of / National Park Service | 3/23/2010 |
FACILITY ENGINEERING ASSOCIATES, P.C. | $85,300 | Contract | : The primary duties of the Energy Audit Contractor shall be the furnishing of all services, labor, equipment and materials, and perform all necessary travel required to conduct energy and water related assessments and services for the National Park Service | Interior, Department of / National Park Service | 2/23/2010 |
COMPUMERIC ENGINEERING, INC. | $73,524 | Contract | : BEAR PROOF TRASH CONTAINERS AND DUMPSTERS FOR BIGHORN CANYON RECREATION AREA | Interior, Department of / National Park Service | 3/05/2010 |
TRINITY TEMPORARIES & BUSINESS SERVICES | $59,356 | Contract | : Contract Specialist Support | Interior, Department of / National Park Service | 3/05/2010 |
SARGENT CORPORATION | $3,413,058 | Contract | : This project scope of work includes roadway and parking areas improvements at 33 locations in Acadia National Park. This work entails, pavement preservations and rehabilitation, new HB pavement, base gravel and shoulder gravels, pavement markings, draina | Interior, Department of / National Park Service | 3/30/2010 |
TRAININGCORE, INC | $45,597 | Contract | : Fort Matanzas - Upgrade Water Distribution System Castillo de San Marcos, St. Augustine, FL | Interior, Department of / National Park Service | 12/22/2009 |
SKY CONSTRUCTION AND ENGINEERING, INC. | $85,808 | Contract | : Remodle of existing resisdence to law enforcement office. | Interior, Department of / National Park Service | 5/01/2009 |
LOUIS BERGER GROUP, INC., THE | $141,995 | Contract | : Steamtown National Historic Site Asbestos Project Monitoring and CM Services | Interior, Department of / National Park Service | 11/01/2009 |
NEXGEN ENERGY SYSTEMS, INC. | $299,520 | Contract | : The project was the design-build of a fixed 50-60 kilo-watt-hour/day PV-generator hybrid system at 90/10 ratio to power Crystal Cave Complex, Sequoia Kings Canyon National Park. The solar array system is rated for 120mph wind speeds and was installed with | Interior, Department of / National Park Service | 7/15/2009 |
HEERY INTERNATIONAL, INC. | $26,186 | Contract | : First call order from National Parks Services Blanket Purchase Agreement for Commissioing and Energy related services. This call order is to perform Energy and Water Audits at Mesa Verde National Park located in Colorado. | Interior, Department of / National Park Service | 2/23/2010 |
STEARNS, CONRAD AND SCHMIDT CONSULTING ENGINEERS, INC. | $46,525 | Contract | : Energy and Water Audits Harpers Ferry National Historical Park and Wolf Trap Farm National Center of the Performing Arts | Interior, Department of / National Park Service | 2/24/2010 |
TQM GROUP LLC | $168,700 | Contract | : Reserve and Repaint Edison House, West Orange, NJ | Interior, Department of / National Park Service | 2/02/2010 |
SUMMITT FORESTS INC | $100,944 | Contract | : Chic Hunting WUI-Chickasaw National Recreation Area- provide manual and mechanical treatment on 1026.5 acres to reduce the encroachment of Eastern red cedar and Ash Juniper | Interior, Department of / National Park Service | 2/12/2010 |
LOUIS BERGER GROUP, INC., THE | $309,276 | Contract | : This Call Order shall consist of on-site inspection, administration of the construction contract, ofiice services, and site visits. All work shall be performed under a single contract. All work performed on the facilities shall be undertaken with the utmo | Interior, Department of / National Park Service | 9/17/2009 |
HEERY INTERNATIONAL, INC. | $83,606 | Contract | : First call order from National Parks Services Blanket Purchase Agreement for Commissioing and Energy related services. This call order is to perform Energy and Water Audits at two National parks, Danali and Glacier Bay located in Alaska. | Interior, Department of / National Park Service | 2/22/2010 |
KGCI INC | $159,825 | Contract | : Repair brick walls at charlestown navy yard, Boston, MA | Interior, Department of / National Park Service | 2/09/2010 |
ONAN CORPORATION | $63,519 | Contract | : Generator Set and Associated Trailer for the National Park | Interior, Department of / National Park Service | 3/03/2010 |
R. J. THOMAS MANUFACTURING COMPANY, INC. | $47,690 | Contract | : Park Grills, 300 sq in cook grate adjust to 4 levels | Interior, Department of / National Park Service | 2/22/2010 |
HDR ENGINEERING, INC. | $29,927 | Contract | : Valley Forge National Historical Park - Perform Topographic survey for Washington's Headquarters area. Following acceptance of topographic survey, analyze data to provide an analysis of drainage patterns and flow lines using software. Compare the as-bu | Interior, Department of / National Park Service | 3/10/2010 |
CXT INCORPORATED | $35,927 | Contract | : PROVIDE DOUBLE VAULT TOILET BUILDING TO DEATH VALLEY NATIONAL PARK. | Interior, Department of / National Park Service | 2/22/2010 |
BEYER BLINDER BELLE, ARCHITECTS AND PLANNERS, LLP | $33,729 | Contract | : BBB and the Design Team have been selected to perform Construction Administration services for the Rehabilitation of Superintenedent's Lodge and Rostrum in Rock Creek Park, Washington, DC. This will include limited review of shop drawings, responses to c | Interior, Department of / National Park Service | 3/11/2010 |
COMFORTS OF HOME SERVICES, INC. | $29,999 | Contract | : One (1) Mobile Restroom with two (2) Standard Stalls and one(1) ADA compliant access delivered to the National Park Service. | Interior, Department of / National Park Service | 3/30/2010 |
J. R. CONKEY & ASSOCIATES, INC. | $57,900 | Contract | : Supply solar panels to Death Valley National park @ Stove Pipe Wells | Interior, Department of / National Park Service | 3/05/2010 |
LOUIS BERGER GROUP, INC., THE | $153,288 | Contract | : Construction Management Services: The purpose of this construction project is to remove health and safety hazards and repar structural deficiencies to enable NPS to open Castle Williams to visitors. Current conditional are accelerating the castle's deter | Interior, Department of / National Park Service | 10/08/2009 |
STEEN CANNON & ORDNANCE WORKS | $136,950 | Contract | : Cannon Carriages | Interior, Department of / National Park Service | 12/22/2009 |
RIM ARCHITECTS AK LLC | $140,891 | Contract | : This project shall consist of the preparation bid ready construction documents for a new maintenance facility in King Salmon Alaska. The design team will create detailed plans and specification including all information necessary for construction of a pr | Interior, Department of / National Park Service | 5/19/2010 |
CROUCH PLUMBING, HEATING, AND AIR CONDITIONING, INC. | $29,512 | Contract | : Replace boiler at the Guadalupe Mountains National Park | Interior, Department of / National Park Service | 3/19/2010 |
BUS SERVICES CORPORATION | $585,318 | Contract | : Mesa Verde National Park RECOVERY Biodiesel Trams MEVL | Interior, Department of / National Park Service | 3/26/2010 |
R. J. THOMAS MANUFACTURING COMPANY, INC. | $32,704 | Contract | : RECYCLED PLASTIC PLANKS FOR BADLANDS NATL PARK, INTERIOR, SD | Interior, Department of / National Park Service | 12/30/2009 |
CHEROKEE 8A GROUP INC., THE | $1,037,880 | Contract | : recovery, rehabilitation of greenhouses and potting shed at the FDR historical site | Interior, Department of / National Park Service | 3/31/2010 |
LOUIS BERGER GROUP, INC., THE | $264,484 | Contract | : Construction Management Services - Hawaii Volcanoes National Park | Interior, Department of / National Park Service | 10/16/2009 |
PORT ANGELES, CITY OF | $150,786 | Grant | Environmental Quality and Protection Resource Management: Prepare a General Sewer Plan and Facility Plan Amendment for submission to the Washington State Department of Ecology for approval and prepare associated NEPA documentation for the National Park Service review and action. | Interior, Department of / National Park Service | 11/09/2009 |
CXT INCORPORATED | $62,934 | Contract | : PRODUCE AND DELIVER PRECAST CONCRETE RESTROOM BUILDINGS TO LAKE ROOSEVELT NRA. | Interior, Department of / National Park Service | 1/12/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $40,000 | Contract | : On-site construction management services required for the construction (fit-out) of the Patchogue Ferry Terminal in the Village of Patchogue, Suffolk County, New York. This project was not originally an ARRA funded project, however 2 mods have been funde | Interior, Department of / National Park Service | 9/22/2009 |
LORD, AECK & SARGENT, INC. | $22,500 | Contract | : Examine the removal of existing asphalt/concrete paved trail and fencing installation of a boardwalk and viewing platform that meets ADA standards that will run from the parking area downhill to the river providing an aesthetic view of the waterfall. | Interior, Department of / National Park Service | 2/03/2010 |
IJC CORPORATION | $113,595 | Contract | : This project replaces the cooling tower at the Mogan Cultural Center, Lowell, MA. | Interior, Department of / National Park Service | 2/12/2010 |
HARTRAMPF, INC. | $88,381 | Contract | : Design and construction phase services for repair of Storm Damaged facilities at Buck Island Reef National Monument | Interior, Department of / National Park Service | 12/29/2009 |
ANDREWS AND ANDERSON ARCHITECT PC | $227,533 | Contract | : This project will abate dangerous working conditions, restore lost structural integrity and extend the service life of a critical 53 year-old passenger elevator system. These elevators are the primary means for visitors at Carlsbad Caverns National Park | Interior, Department of / National Park Service | 11/24/2009 |
HDR ARCHITECTURE INC, | $217,707 | Contract | : Title III services for the GRSM projects Clingmans Dome Road and Cherokee Orchard Roaring Fork. This work will include RFIs, submittal reviews, site visits and as-constructed drawings | Interior, Department of / National Park Service | 2/24/2010 |
HDR ENGINEERING, INC. | $16,942 | Contract | : Valley Forge (VAFO) National Historical Park, Visitor Center Canopy Fabrication and Erection | Interior, Department of / National Park Service | 3/30/2010 |
DE NICOLOLA DESIGN LIMITED LIABILITY COMPANY | $126,469 | Contract | : RE-ROOF FORD MANSION | Interior, Department of / National Park Service | 2/03/2010 |
ENOLA CONTRACTING SERVICES INC | $5,455,818 | Contract | : Rehabilitate Cherokee Orchard Road / Roaring Fork Motor Nature Trailat the Great Smokies National Park in Gatlinburg, TN. | Interior, Department of / National Park Service | 1/25/2010 |
CXT INCORPORATED | $62,934 | Contract | : VAULT TOILETS, COULEE DAM | Interior, Department of / National Park Service | 11/03/2009 |
FEDLIGHT SUPPLY LLC | $6,647 | Contract | : Energy Efficient Compact Fluorescent Lamps | Interior, Department of / National Park Service | 2/02/2010 |
FAREWELL MILLS GATSCH ARCHITECTS, LLC | $503,286 | Contract | : Rebuild and/or rehabilitate historic stone towpath walls located along a stretch of approximately 1.5 miles downstream of McMahon's Mill in the Big Slackwater area of the C&O Canal. | Interior, Department of / National Park Service | 7/30/2009 |
HERTZ EQUIPMENT RENTAL CORPORATION | $242,400 | Contract | : Rental of Contruction Equipment to the National Park Service. National Park Service will employ their own staff to utilize the equipment. | Interior, Department of / National Park Service | 12/22/2009 |
NUERA CORPORATION | $6,098 | Contract | : RECOVERY DENA Heater | Interior, Department of / National Park Service | 3/29/2010 |
HARTRAMPF, INC. | $29,903 | Contract | : Engineering construction phase services for installation of solar array system at the Kennesaw Mountain Visitors Center | Interior, Department of / National Park Service | 3/15/2010 |
GREENING YOUTH FOUNDATION, INC | $169,135 | Contract | : GYF in partnership with NPS IMR conducted the re-lamping of the following NPS sites, Grand Junction, Gunnison and Black Canyon. The Project was performed utilizing youth students from the Metro-Denver inner-city area. All youth were of color in an effor | Interior, Department of / National Park Service | 3/15/2010 |
HEERY INTERNATIONAL, INC. | $83,791 | Contract | : First call order from National Parks Services Blanket Purchase Agreement for Commissioing and Energy related services. This call order is to perform Energy and Water Audits at SEKI Sequoia / Kings Canyon National Park located in California. | Interior, Department of / National Park Service | 2/23/2010 |
EAGLE GROUP INC | $99,565 | Contract | : Energy efficiency upgrades to NPS owned buildings at Stehekin, WA | Interior, Department of / National Park Service | 2/09/2010 |
ELLIS FENCE CO | $30,537 | Contract | : Fence Supplies Delivered | Interior, Department of / National Park Service | 1/12/2010 |
BARGMANN HENDRIE & ARCHETYPE, INC. | $37,809 | Contract | : Design services for Recovery project to rehabilitate the Home of FDR HVAC system; LULA lift and emergency generator. | Interior, Department of / National Park Service | 12/15/2009 |
FIRVIDA CONSTRUCTION CORPORATION | $829,123 | Contract | : Road Rehabilitation Phase 2 Asphalt repair to Parking, Overlooks, and Picnic Areas. Asphalt was repaired and then overlaid. | Interior, Department of / National Park Service | 2/02/2010 |
SHOEMAKER, HARLAND J & SON INC | $44,945 | Contract | : Road Shoulder Rehabilitation along the George Washington Memorial Parkway. Schedule or services include: Excavate and remove existing soil - 35 cubic yards, Demolish and remove existing curb - 230 linear feet, Sawcut Asphalt - 230 Linear Feet, Form and P | Interior, Department of / National Park Service | 1/28/2010 |
JAMESTOWN ADVANCED PRODUCTS, CORP. | $6,217 | Contract | : 33 fire rings and 20 park grills | Interior, Department of / National Park Service | 1/25/2010 |
GILMAN CORPORATION THE | $39,598 | Contract | : BUOYS | Interior, Department of / National Park Service | 2/26/2010 |
GABEL ASSOCIATES INC. | $441,996 | Contract | : Energyand Water Audits: Glacier NP, Glen Canyon NRA, Grand Canyon NP, Grand Teton NP, Rocky Mountain NP. San Antonio NHP, and Yellowstone NP | Interior, Department of / National Park Service | 2/23/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $264,314 | Contract | : Replace Waterline: Chapin Mesa to North Park Boundary, Mesa Verde National Park, MEVE 103765 The primary waterline serving Mesa Verde National Park is beyond its useful life and must be replaced. The current waterline is exposed or in a shallow bury con | Interior, Department of / National Park Service | 3/12/2010 |
HARTRAMPF, INC. | $28,004 | Contract | : design of repairs for the fire suppression systems at Carl Sandburg Home | Interior, Department of / National Park Service | 12/04/2009 |
CORNERS CONSTRUCTION | $187,718 | Contract | : Replace Boiler and Clean HVAC for Maritime Museum Bldg E @ San Francisco National Park | Interior, Department of / National Park Service | 3/04/2010 |
YERBA BUENA ENGINEERING & CONSTRUCTION, INC. | $142,860 | Contract | : ARRA PMIS 148204 Demo 2 Houses- Demolish 2 Abandoned Houses Ft. Barry & Reveg Landscape | Interior, Department of / National Park Service | 5/06/2010 |
TAYLOR MECHANICAL CORPORATION | $152,304 | Contract | : Replace 26 HVAC Systems at the Gateway National Recreation Area, 210 New York Avenue, Staten Island, NY | Interior, Department of / National Park Service | 3/25/2010 |
HOLM, BERKLEE | $55,200 | Contract | : Gravel supply and delivery | Interior, Department of / National Park Service | 2/23/2010 |
PARKER FIRE PROTECTION, INC. | $506,032 | Contract | : Design Build and Installation Fire Sprinkler Systems @ Crater Lake National Park | Interior, Department of / National Park Service | 3/30/2010 |
CONSERVATION, CALIFORNIA DEPARTMENT OF | $2,083,670 | Grant | Abandoned Mine Hazard Mitigation: This program allows the National Park Service to maintain the thousands of buildings, roads, trails, utility systems, and other constructed assets in national parks. | Interior, Department of / National Park Service | 1/06/2010 |
RICHARD P. ARBER ASSOCIATES, INC. | $10,849 | Contract | : Lake Rossevelt National Recreation Area, Washington - Title I Preliminary Design Services for Installation of Photovoltaic System at Park Headquarters Building | Interior, Department of / National Park Service | 12/23/2009 |
RICHARD P. ARBER ASSOCIATES, INC. | $10,031 | Contract | : Lake Rossevelt National Recreation Area, Washington - Title I Preliminary Design Services for Installation of Photovoltaic System at Ft. Spokane Shop and Office Building | Interior, Department of / National Park Service | 12/23/2009 |
ERICK AMMON INC | $3,910,052 | Contract | : ASH MOUNTAIN POTABLE WATER TANKS | Interior, Department of / National Park Service | 3/08/2010 |
FORDICE CONSTRUCTION COMPANY | $760,080 | Contract | : Perform renovations to the Historic Shirley House at Vicksburg National Military Park. | Interior, Department of / National Park Service | 3/25/2010 |
E.L.C.I. CONSTRUCTION GROUP, INC. | $409,823 | Contract | : The work under this contstruction contract will consist of replacing diesel generators with solar power system for two housing units on Adams Key at Biscayne National Park Homestead, FL. | Interior, Department of / National Park Service | 3/25/2010 |
WILD ALASKA CHARTERS | $150,891 | Contract | : RE-PAINTING FOR THREE MARINE VESSELS AND PAINTING MARINE SURVEY FOR ONE FUEL BARGE USED IN PARK SERVICE OPERATIONS AT GLACIER BAY NATIONAL PARK AND PRESERVE GUSTAVUS, ALASKA The scope of work for th e3 vessels is as follows: M/V Serac: A. Sand bla | Interior, Department of / National Park Service | 1/14/2010 |
RAAD CONSTRUCTION GROUP, LLC | $352,048 | Contract | : Replace and Rehabilitate Heating System at Historic Hanger B, Floyd Bennett Field, NY Gate 110018 | Interior, Department of / National Park Service | 2/26/2010 |
FAREWELL MILLS GATSCH ARCHITECTS, LLC | $199,130 | Contract | : Construction observation services to reconstruct and stabilize Big Slackwater Historic Stone Wall and Towpath | Interior, Department of / National Park Service | 5/13/2010 |
FORT MYER CONSTRUCTION CORPORATION | $424,622 | Contract | : MCPHERSON SQ BETW I ST & K ST,& 15TH ST, NW, WASHINGTON, DC PARK REHAB: SIDEWALKS/CURB/STREETLIGHT/MISC | Interior, Department of / National Park Service | 5/27/2010 |
CHEMTRACK ALASKA, INC. | $104,846 | Contract | : Anaktuvuk Pass Wind Turbine Installation | Interior, Department of / National Park Service | 3/19/2010 |
EDIFICE GROUP, INC. | $1,075,383 | Contract | : Rehabilitate Historic Lodge House & Rostrum | Interior, Department of / National Park Service | 2/26/2010 |
JMR INVESTMENTS LLC | $257,032 | Contract | : Add effluent filtration equipment to the Mt. Pisgah sewage treatment plant in accordance with the drawings and specifications. | Interior, Department of / National Park Service | 5/19/2009 |
RICHCON FEDERAL CONTRACTORS, INC. | $42,828 | Contract | : Fabricate cannon carriage parts for 12 cannons at San Juan National Historic Site, Puerto Rico | Interior, Department of / National Park Service | 9/21/2009 |
DWG & ASSOCIATES, INC. | $192,268 | Contract | : Rehabilitate eight comfort stations in the Chickasaw National Recreation Area. Includes removal of fixtures, accessories, partitions, and doors. Demolition of the tile and wallboard in two of the buildings. The realignment of rough plumbing as needed for | Interior, Department of / National Park Service | 3/01/2010 |
SUNWIZE TECHNOLOGIES, INC. | $208,950 | Contract | : Installation of solar electric system Park | Interior, Department of / National Park Service | 3/22/2010 |
KGCI INC | $176,728 | Contract | : Demolish three houses for Acadia National Park,ME | Interior, Department of / National Park Service | 4/06/2010 |
ENGINEERING SOLUTIONS, INC. | $50,401 | Contract | : Design Development and Construction Documents to install a Photovoltaic system at Kilauea Visitor Center - Hawaii National Park | Interior, Department of / National Park Service | 1/08/2010 |
OREGON WOODS, INC. | $58,568 | Contract | : replacement of interior Pohaku Palaha interior boundry fence in for feral anmimal control. | Interior, Department of / National Park Service | 3/10/2010 |
CONSERVATION CORPS, CALIFORNIA | $24,606 | Grant | Conservation Activities by Youth Service Organizations: Project includes constructing an accessible trail with handrail and prepare the trail surface to insure ADA compliance at the Devil's Postpile rock formation. | Interior, Department of / National Park Service | 4/16/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $128,510 | Grant | Conservation Activities by Youth Service Organizations: This award funds services to the National Park Service Southeast Exotic Plant Management Team, based in Asheville, North Carolina, from the Student Conservation Association's youth conservation service programs. SCA is recruiting, training and l leading a N... Show more | Interior, Department of / National Park Service | 4/06/2010 |
URS GROUP, INC. | $454,884 | Contract | : The National Parks Service selected URS to provide construction management services for the replacement and renovation of the public safety radio system of the Golden Gate National Recreation Area. The project will replace the current infrastructure and r | Interior, Department of / National Park Service | 4/16/2010 |
MATTHEWS GROUP, INC., THE | $2,309,092 | Contract | : Road Rehabilitation, Phase 4: Overlooks, Parking Areas, and Picnic Grounds, Shenandoah National Park. | Interior, Department of / National Park Service | 4/20/2010 |
AIRBORNE VETERANS SERVICES, INC. | $49,454 | Contract | : Supply 93 windows | Interior, Department of / National Park Service | 5/05/2010 |
RICHARD P. ARBER ASSOCIATES, INC. | $6,533 | Contract | : Lake Rossevelt National Recreation Area, Washington - Title I Preliminary Design Services for Installation of Grid Connected Micro-hydro Power System At Fort Spokane Water System | Interior, Department of / National Park Service | 1/28/2010 |
RICHARD P. ARBER ASSOCIATES, INC. | $8,873 | Contract | : Lake Rossevelt National Recreation Area, Washington - Title I Preliminary Design Services for Performing a Energy Retrofit of Fort Spokane and Kettle Falls Buildings | Interior, Department of / National Park Service | 1/26/2010 |
REVA MURPHY ASSOCIATES, INC. | $61,253 | Contract | : Boulder Beach Housing Units Roofing | Interior, Department of / National Park Service | 1/22/2010 |
ONSITE CONSTRUCTION & ENGINEERING, INC. | $629,845 | Contract | : Rehabilitate Historic Ft. Mason Chapel | Interior, Department of / National Park Service | 5/11/2010 |
WESTLAKE, REED, LESKOSKY, LTD. | $79,247 | Contract | : Engineering Services for the Replacement of Non-theatrical Lighting in the Filene Center, Wolf Trap Farm Park for the Performing Arts, Vienna, VA. | Interior, Department of / National Park Service | 4/21/2010 |
LOUIS BERGER GROUP, INC., THE | $156,791 | Contract | : Acadia National Park (ACAD) Roads and Culverts | Interior, Department of / National Park Service | 4/05/2010 |
AMERICAN CONSERVATION EXPERIENCE | $172,800 | Grant | Conservation Activities by Youth Service Organizations: This project is a cooperative endeavor between Grand Canyon National Park and American Conservation Experience (ACE). ACE crews assist NPS staff with cyclic maintenance and rehabilitation of trails throughout the Park. Project work includes rerepair of dr... Show more | Interior, Department of / National Park Service | 1/01/2010 |
KIRBY NAGELHOUT CONSTRUCTION CO. | $294,528 | Contract | : Relocate existing house. New 725 S.F. living structure designed as a 'Zero Energy' unit using SIPS. An additional 625 S.F. support space is attached. An air-to-air heat exchanger will be installed on this super-tight house. Includes a Photvolotaic sy | Interior, Department of / National Park Service | 4/30/2010 |
CUTTING EDGE GROUP, LLC | $828,094 | Contract | : The project will consist of the design and construction of stormwater management facilities at Valley Forge National Historic Park, King of Prussia, PA. Five stormwater infiltration facilities that exist are not functioning as expected. Instead of infiltr | Interior, Department of / National Park Service | 5/11/2010 |
COOPER ZIETZ ENGINEERS, INC | $12,064 | Contract | : Construction Management Services for installation of Photovoltaic System at Headquarters Craters of the Moon National Monument PMIS # 129621 (CRMO) | Interior, Department of / National Park Service | 5/13/2010 |
HARRIS ENVIRONMENTAL GROUP | $29,995 | Contract | : To survey and assess the presence of the Mojave population of the desert tortoise at 46 mine sites within the Death Valley Greenwater Valley, California | Interior, Department of / National Park Service | 5/10/2010 |
ABIDE INTERNATIONAL, INC. | $725,670 | Contract | : The Work consists of removing several abandoned structures, building remnants, and other potentially hazardous building features from the Wawona district housing area in Yosemite National Park. Work entails complete removal of all structures, foundations | Interior, Department of / National Park Service | 4/29/2010 |
PORT ANGELES, CITY OF | $1,620,100 | Grant | Environmental Quality and Protection Resource Management: 1) Correct storm drainage problems in lieu of constructing a 430,000 gallon storage tank to prevent combined sewer overflow discharges. 2) Modify design and construction of the Dry Creek pedestrian bridge to support the Lower Elwha Klallam Triribe wastewate... Show more | Interior, Department of / National Park Service | 5/07/2010 |
COFFMAN ELECTRICAL EQUIPMENT CO. | $29,065 | Contract | : 100KW KOHLER GENERATOR AND 30KW KOHLER GENERATOR INCLUDING SHIPPING TO EVERGLADES NATIONAL PARK, HOMESTEAD, FL | Interior, Department of / National Park Service | 4/30/2010 |
ENGINEERING SOLUTIONS, INC. | $39,251 | Contract | : Construction Management Services to Install a Photovoltaic System at Kilauea Visitor Center - Hawaii National Park | Interior, Department of / National Park Service | 4/01/2010 |
LOUIS BERGER GROUP, INC., THE | $207,834 | Contract | : Construction Management Services - DC War Memorial | Interior, Department of / National Park Service | 5/11/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $28,190 | Grant | Conservation Activities by Youth Service Organizations: This award funded services to the Yellowstone National Park in Wyoming, from the Student Conservation Association's youth conservation service programs. SCA recruited, trained and led a youth crew twho learned and practiced outdoor leadership a and job ski... Show more | Interior, Department of / National Park Service | 5/14/2010 |
MONTANA CONSERVATION CORP | $40,000 | Grant | Conservation Activities by Youth Service Organizations: MCC and NPS have a mutual interest in accomplishing needed conservation and environmental restoration projects within the landscape of Yellowstone National Park Trail System. The involvement of young adults in the care and enhancement of publicic resources... Show more | Interior, Department of / National Park Service | 4/27/2010 |
RUSSELL/BRSNHN/HFFNER MLTMEDIA | $187,669 | Contract | : RBH Multimedia, Inc. shall provide the National Park Service with all labor, materials, services and facilities necessary to produce 19-Audio Programs and 10-Video Programs for the new exhibits at the Union Building Interpretive Facility the Keweenaw N | Interior, Department of / National Park Service | 4/22/2010 |
GABEL ASSOCIATES INC. | $90,824 | Contract | : Energy and Water Use Audits: Bandelier National Monument, Bryce Canyon National Park, Black Canyon of the Gunnison National Park & Curecanti National Park Recreation Area, Lyndon B. Johnson National Historical Park, Petrified Forest National Park | Interior, Department of / National Park Service | 5/14/2010 |
GROUNDWORK USA, INC. | $87,497 | Grant | Conservation Activities by Youth Service Organizations: Youth rehabilitation and preservation work to reconstruct sluices at Saugus Iron Works NHP | Interior, Department of / National Park Service | 5/06/2010 |
RIDGWAY VALLEY ENTERPRISES, INC. | $204,221 | Contract | : Remove existing decking on the Many Parks Curve Boardwalk and replace with new composite decking. To include re-leveling, cleaning and repainting of the steel superstructure. Existing wood railing will be replaced with steel railing. | Interior, Department of / National Park Service | 1/26/2010 |
C-2 CONSTRUCTION INC | $132,111 | Contract | : ADA Pathway Construction, excavation and construction to enhance trail for diverse population. | Interior, Department of / National Park Service | 4/23/2010 |
HARTRAMPF, INC. | $183,634 | Contract | : Construction Phase Services for 3rd phase of Tuskegee Airmen Moton Field Rehabilitation | Interior, Department of / National Park Service | 5/06/2010 |
ANDERSON HALLAS ARCHITECTS, PC | $251,003 | Contract | : This project will serve to rehabilitate the Many Glacier Hotel in Glacier National Park, MT. The hotel is in an advanced state of deterioration and requires immediate rehabilitation to address critical health and life-safety needs and comply with buildin | Interior, Department of / National Park Service | 6/30/2010 |
HDR ENGINEERING, INC. | $37,000 | Contract | : Title III Services for the Replacement of Primary Electrical Cables on Floyd Bennett Field GATE 77297B | Interior, Department of / National Park Service | 5/11/2010 |
MIRANDA COUNTRY STORE INC | $100,898 | Contract | : Furnish fencing materials to Hawaii Volcanoes National Park | Interior, Department of / National Park Service | 5/06/2010 |
CROUCH PLUMBING, HEATING, AND AIR CONDITIONING, INC. | $27,450 | Contract | : Provide and Install HVAC units with 10 year extended warranties on compressors, Carlsbad Caverns National Park, NM | Interior, Department of / National Park Service | 2/02/2010 |
GREAT BASIN INSTITUTE | $34,614 | Grant | Conservation Activities by Youth Service Organizations: The purpose of this project is to repair damage to the Timber Creek Trail. The project involves 1.93 miles of trail work including tread repair, clearing brush, installing erosion control structures; and minor reroutes to minimize the existing g grades. Thr... Show more | Interior, Department of / National Park Service | 5/11/2010 |
ATKINS NORTH AMERICA, INC | $181,205 | Contract | : CM Services: Replace Ash Mountain Water Tanks - Sequoia/Kings Canyon National Park | Interior, Department of / National Park Service | 6/11/2010 |
QUICKSILVER CONTRACTING COMPANY | $327,423 | Contract | : TO# 1 : REDUCTION OF FIRE HAZARD BY REMOVAL OF TREES | Interior, Department of / National Park Service | 4/06/2010 |
COLOR-AD INC | $125,997 | Contract | : FABRICATE AND INSTALL EXHIBIT ELEMENTS FOR KEWEENAW NATIONAL HISTORIC SITE. | Interior, Department of / National Park Service | 5/13/2010 |
H-K CONTRACTORS, INC. | $992,969 | Contract | : South Rim Drive-C1574105006. Rehabilatation of 1.4 miles of radway in Yellowstone National Park WY. The work includes 26,000sy asphalt milling, 26,000sy asphalt paving, 2.8 miles shoulder grading, traffic control, and striping. | Interior, Department of / National Park Service | 4/19/2010 |
LOUIS BERGER GROUP, INC., THE | $137,876 | Contract | : This project is the general construction of conduit and conductors from new uninterruptible power supplies (UPS) to perimeter locations and general construction of conduit and fiber optic cabling to perimeter locations to support data transmission on Libe | Interior, Department of / National Park Service | 5/11/2010 |
SAYBR CONTRACTORS, INC. | $1,037,481 | Contract | : Olympic National Park: Boulder Creek Trail Rehabilitation | Interior, Department of / National Park Service | 5/14/2010 |
MURDOCK FENCING INC | $134,438 | Contract | : Contract for Hagerman Fossil Bed National Monument. Removing and Installation of Fence. | Interior, Department of / National Park Service | 5/12/2010 |
QUINN EVANS ARCHITECTS INC | $154,168 | Contract | : Rehabilitate the landscape in the vicinity of Peirce Mill Complex and the c.1829 Peirce Mill Structure and allow Peirce Mill to be reopened to the public. The project will provide a water intake to power the milling apparatus; address mechanical and elec | Interior, Department of / National Park Service | 5/11/2010 |
REILLY CONSTRUCTION, INC | $80,485 | Contract | : Demolition and Debris Removal Burhnam Tract, Richmond VA | Interior, Department of / National Park Service | 5/06/2010 |
VERMONT YOUTH CONSERVATION CORPS INC | $100,000 | Grant | Conservation Activities by Youth Service Organizations: Vermont Youth Conservation Corps at Appalachian Trail | Interior, Department of / National Park Service | 5/10/2010 |
LIQUID WASTE TECHNOLOGY, LLC | $75,229 | Contract | : LWT Remote Controlled Dredge with float hose assembly, tensioning package, and cover, for Yellowstone National Park at Mammoth Supply Center, Yellowstone National Park, WY. | Interior, Department of / National Park Service | 5/11/2010 |
CONSERVATION CORPS, CALIFORNIA | $93,789 | Grant | Conservation Activities by Youth Service Organizations: Project objective is for the CCC to assist in the excavations for rehabilitation & reconstruction of the rock retaining walls and rock steps on Lassen Peak Trail, as well as assist in reconstructing the rock retaining walls and steps using dryststone masonr... Show more | Interior, Department of / National Park Service | 4/27/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $38,248 | Grant | Conservation Activities by Youth Service Organizations: This award funded services to the Sequoia and Kings Canyon National Park in Three Rivers CA, from the Student Conservation Association's youth conservation service programs. SCA recruited, trained and led youth who worked on Trail Maintenance CrCrews, resto... Show more | Interior, Department of / National Park Service | 4/27/2010 |
EDL CONSTRUCTION, INC. | $234,014 | Contract | : SUPPLY AND INSTALL PV SYSTEM AT SANTA MONICA MOUNTAINS | Interior, Department of / National Park Service | 4/23/2010 |
B.C. SCHMIDT CONSTRUCTION, INC. | $76,333 | Contract | : Construction services to meet the requirements to render the mine sites safe and the declines, shafts, and adit underground pathways inaccessible to the publice by means of utilizing a bat gate design. Project includes all necessary project design and man | Interior, Department of / National Park Service | 4/01/2010 |
EINHORN YAFFEE PRESCOTT, ARCHITECTURE AND ENGINEERING, P.C. | $42,875 | Contract | : Hampton National Historic Site, Towson, MD; Provide revised drawings of floor plans and all systems (mechanical, electrical, plumbing) layouts and exterior architectural details and configurations; reorient building on site accomodating storm water drain | Interior, Department of / National Park Service | 10/28/2009 |
GCCI, INC. | $763,532 | Contract | : Construct new building at Poit Reyes Hostel, Point Reyes National Seashore, Point Reyes, Marin County, CA | Interior, Department of / National Park Service | 5/12/2010 |
HDR ENGINEERING, INC. | $157,765 | Contract | : Provide submittal reviews, office services (design of enhancements or modifications to the project, professional review of modification requests and value-engineering change proposals, responding to design clarification/variation requests); as built drawi | Interior, Department of / National Park Service | 5/04/2010 |
CIANBRO CORPORATION | $14,437,519 | Contract | : Rehabilitate the Big Slackwater Historic Towpath and Stonewall along the C&O Canal in Williamsport, MD. Contract consists of approximately 5000 linear feet of elevated towpath and approximately 3000 linear feet of reconstructing the original towpath. Am | Interior, Department of / National Park Service | 5/06/2010 |
RIDGWAY VALLEY ENTERPRISES, INC. | $401,576 | Contract | : Grand Canyon National Park North Rim Norton Campground Demo 6 cabins haul off to landfill,add gravel parking lot where cabins were removed, place log barriers at edge of gravel parking areas and clear and grub to remove 80 trees, install underground utili | Interior, Department of / National Park Service | 5/03/2010 |
FLOATING DOCK SHOP, LLC, THE | $56,250 | Contract | : docks and gangways for Big Bend National Park | Interior, Department of / National Park Service | 5/05/2010 |
CLASSIC SITE SOLUTIONS, INC. | $512,531 | Contract | : Revitilize the Buttrick Gardens including pruning, weeding and replanting historically correct plants. also clearing 10.4 acres and harrowing an additional 5 acres of farm land. Modifications1&2: added a total of 212,531.00 which comprised the acceptance | Interior, Department of / National Park Service | 5/21/2010 |
JOHN DEERE SHARED SERVICES, INC. | $31,908 | Contract | : John Deere 320 Skid Steer | Interior, Department of / National Park Service | 8/12/2009 |
TANDUS US, LLC | $28,022 | Contract | : Flooring and Flooring Installation at Fort Laramie National Historic Site | Interior, Department of / National Park Service | 4/01/2010 |
AMEC E&I, INC | $138,555 | Contract | : CONDUCT POST CLOSURE BAT SURVEYS AT ABANDONED MINE FEATURES IN DEATH VALLEY NATIONAL PARK, CA. | Interior, Department of / National Park Service | 5/12/2010 |
OTAK GROUP, INC. | $816,367 | Contract | : Remove Detritus and Debris from Bayou Coquille and Kenta Canal Bayou Coquille to Twin Canals at Jean Lafitte National Park and Preserve Barataria Unit, LA. | Interior, Department of / National Park Service | 5/03/2010 |
APERTURE FILMS, LTD. | $414,747 | Contract | : Creating Media For National Park Site In New York City | Interior, Department of / National Park Service | 5/12/2010 |
ERGON TERMINALING, INC. | $152,995 | Contract | : Repaired 160 linear feet of concrete drain, overlaid 66,000 square feet of SC-1 M-DOT approved asphalt mixture, re-paved parking lot area in front on maintenance shop (11,000 square feet), & installed 30 linear feet of bitumunous wedge sloping from 2 to 8 | Interior, Department of / National Park Service | 9/25/2009 |
DWG & ASSOCIATES, INC. | $87,580 | Contract | : The primary work of this project is to repair/replace/rehabilitate the HVAC system within the Visitor Center ot Palo Alto Battlefield National Historical Park. | Interior, Department of / National Park Service | 5/04/2010 |
LEETEX/HILL & WILKINSON IV LLC | $373,952 | Contract | : This project is to install a single array, ground mounted, minimum 58kW of electrical power at 120/208V, 3 phase, photovoltaic system on BIA lands nearby per MOU with BIA. | Interior, Department of / National Park Service | 4/15/2010 |
ENGINEERING SOLUTIONS, INC. | $42,799 | Contract | : CM Services - Install PV System at Visitor Center and Amphitheater - Amercian Memorial Park, Saipan | Interior, Department of / National Park Service | 4/01/2010 |
INTERNATIONAL MAPPING ASSOCIATES, INC. | $104,060 | Contract | : Keweenaw Interactive Kiosk: all labor, equipment, materials and services necessary to compile, design and produce an interactive kiosk program for Keweenaw National Historical Site | Interior, Department of / National Park Service | 5/11/2010 |
AMERICAN CONSERVATION EXPERIENCE | $47,000 | Contract | : The objective of this project is to participate collaboratively in conservation projects. ACE will aid in the Sequoia National Park's mission of protection and conservation efforts by expanding the Park's cyclic maintenance program. The Park is currentl | Interior, Department of / National Park Service | 4/13/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $483,712 | Contract | : Construction Managaement Services for construction to relocate West Side Maintenance & Visitor Contact Station and Replace Trailer Housing Units at Pinnacles National Monument, paicines, CA.. | Interior, Department of / National Park Service | 5/10/2010 |
QUINN EVANS ARCHITECTS INC | $86,869 | Contract | : Title III Construction Phase Services for the roof replacement on the Old Courthouse at Jefferson National Expansion Memorial in St. Louis, Missouri | Interior, Department of / National Park Service | 11/05/2009 |
EYP, INC. | $222,482 | Contract | : Governors Island National Monument, Hazmat Abatement and Sturctural Stabilization of Castle Williams. | Interior, Department of / National Park Service | 4/02/2010 |
RIDGWAY VALLEY ENTERPRISES, INC. | $105,542 | Contract | : The award of the project is a design build for the Maintenance Shop located at the Sand Dunes National Park. Upgrades will include installation of a forced-air furnace, infrared heater, garage door openers, window, window glazing, ceiling gypsum board, in | Interior, Department of / National Park Service | 5/06/2010 |
SOUTHWESTERN DAKOTAH, INC. | $1,010,249 | Contract | : The work of this contract consists of the general construction of 3,750 LF of a 10 waterline in Bunker Rd, installation of 940 LF of a 6 waterline ate the horse stables, with service to the blimp hangar, valve vault modifications at the Ft. Barry Water t | Interior, Department of / National Park Service | 5/12/2010 |
ALLIED INDUSTRIES INC. | $84,585 | Contract | : Painting of Structure | Interior, Department of / National Park Service | 4/21/2010 |
RIDGWAY VALLEY ENTERPRISES, INC. | $201,402 | Contract | : Removal of existing water tank and installation of new 5000 gallon water tank at the Green Mountain Seasonal Housing Area in Rocky Mountain National Park | Interior, Department of / National Park Service | 4/22/2010 |
HAL HAYS CONSTRUCTION, INC. | $8,772,716 | Contract | : TAS::14 1041:: TAS RECOVERY GOGA PMIS#150682 DESIGN-BUILD PHOTOVOLTAIC POWER/ ROOFING PROJECT ON ALCATRAZ ISLAND | Interior, Department of / National Park Service | 5/04/2010 |
AJC ARCHITECTS, P.C. | $118,667 | Contract | : Provide Construction Administration Commissioning Services for a Moose Maintenance Building Renovation at Grand Teton Park. | Interior, Department of / National Park Service | 4/27/2010 |
LOBINA CONSTRUCTION, LLC | $270,928 | Contract | : Buckstaff Roof Replacement | Interior, Department of / National Park Service | 5/11/2010 |
BARON + DOWDLE CONSTRUCTION, LLC | $34,987 | Contract | : Rehab Stoned Paved Ditches Meriwether Lewis Site on the Natchez Trace Parkway | Interior, Department of / National Park Service | 5/06/2010 |
LORD, AECK & SARGENT, INC. | $70,569 | Contract | : The scope of work that will be completed under Task Order T2011100404 consists of five activities related to the construction administration for Year 4 of the Preserve Fort Jefferson Phase 2 project, Dry Tortugas National Park, Garden Key, Florida. The in | Interior, Department of / National Park Service | 5/14/2010 |
REGENTS OF THE UNIVERSITY OF COLORADO, THE | $129,571 | Grant | Abandoned Mine Hazard Mitigation: Cooperative Agreement Number H2306103507 was entered into by and between the Department of the Interior, National Park Service, (NPS), and the University of Colorado Denver for the purpose of G?Development of a Spatial Data Clearinghouse and Interface for | Interior, Department of / National Park Service | 4/30/2010 |
JAS. W. GLOVER, LTD. | $194,217 | Contract | : At Kaloko-Honokohau National Historical Park we performed Installation of sewer force main, sewer manholes and pavement restoration, including materials, labor, equipment, excavation and backfill | Interior, Department of / National Park Service | 4/02/2010 |
B.C. SCHMIDT CONSTRUCTION, INC. | $126,766 | Contract | : Services relating to the mitigation of physical safety min hazards in the Parashant National Monument, Grand Canyon. Closing adits by blasting to close openings. Includes project design, management, activity analysis, accident prevention, project schedu | Interior, Department of / National Park Service | 5/10/2010 |
VINTAGE PAVING CO., INC. | $892,178 | Contract | : Design-build various pathways surrounding Great Meadow @ Fort Mason, San Francisco, CA | Interior, Department of / National Park Service | 6/22/2010 |
HEARTWOOD PACIFIC, LLC | $33,134 | Contract | : Feral animal fencing at Haleaukala National Park. | Interior, Department of / National Park Service | 5/14/2010 |
RIDGWAY VALLEY ENTERPRISES, INC. | $234,822 | Contract | : Design Build LP Gas Storage Replacement Project at Canyonlands National Park and Great Sand Dunes National Park & Preserve | Interior, Department of / National Park Service | 5/06/2010 |
LIGHTWAVE SOLAR ELECTRIC, LLC | $516,593 | Contract | : Natchez Trace Meriwether Lewis State Park: Design, furnish & installation of grid interconnected Solar PV System in conjunction with the roofing section of this project. | Interior, Department of / National Park Service | 4/29/2010 |
PARAGON INDUSTRIAL APPLICATIONS | $5,793,755 | Contract | : Design/Install Rebuild Renewable Energy Equipment at El Portal Complex | Interior, Department of / National Park Service | 5/10/2010 |
CMEC, INCORPORATED | $105,171 | Contract | : Replace Interior Carpet and Paint Interior Walls Headquarters Building, Redwood National Park. 1111 Second St. Cresent City, CA 95531 | Interior, Department of / National Park Service | 4/13/2010 |
ENGINEERING SOLUTIONS, INC. | $32,610 | Contract | : Design/demolition of the following: 6 unsafe buildings at Sacramento Landing. Drakes Bay Fish Docks. Cheda Ranch. | Interior, Department of / National Park Service | 1/07/2010 |
URS GROUP, INC. | $410,913 | Contract | : WELLS - The NPS will be undertaking a project to plug and reclaim 39 orphaned wells in Big South Fork National River and Recreation Area. These wells pose environmental risks and public safety threats. Primary threats are resource damage from the releas | Interior, Department of / National Park Service | 5/14/2010 |
EDAW, INC. | $47,945 | Contract | : Wildlife Study/ Bat Study TAS::14 1035::TAS RECOVERY GOGA PMIS #82199 BAT SURVEY | Interior, Department of / National Park Service | 4/01/2010 |
FIRESTONE AND PARSON INC | $30,000 | Contract | : Provide the National Park Service with a late 18th century epergne as described in the Scope of Work . | Interior, Department of / National Park Service | 5/13/2010 |
FLETCHER FARR AYOTTE INC. | $14,219 | Contract | : Architect-Engineer services provided to perform a variety of projects within National Park Service Units at locations primarily throughout the States of California, Nevada, Washington, Oregon, Idaho and Montana. Title I, Title II and Title III Services. | Interior, Department of / National Park Service | 4/06/2010 |
TEECOR GROUP, INC,THE | $132,940 | Contract | : Asbestos Abatement | Interior, Department of / National Park Service | 5/13/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $178,596 | Grant | Conservation Activities by Youth Service Organizations: This award provides funding for trail building and conservation projects at numerous sites within Denali National Park in Alaska. Work has included new trail construction to enhance public access through the high alpine tundra on the side of Mouount Healy, ... Show more | Interior, Department of / National Park Service | 3/04/2010 |
MACNAK CONSTRUCTION LLC | $208,326 | Contract | : ASPHALT OVERLAY AT MOUNT RAINIER NATIONAL PARK | Interior, Department of / National Park Service | 5/14/2010 |
DHM DESIGN CORPORATION | $135,701 | Contract | : Architectural and Engineering Services - Stablization of Ellis Island Baggage and Dormitory Building - Construction Management Services | Interior, Department of / National Park Service | 5/11/2010 |
GABEL ASSOCIATES INC. | $92,822 | Contract | : Energy and Water Use Audits: Crater Lake National Park, Lassen Volcanic National Park, North Cascades National Park Complex | Interior, Department of / National Park Service | 5/14/2010 |
HDR ENGINEERING, INC. | $377,481 | Contract | : Construction Management Services consist of on-site inspection, special inspections, administration of the construction contract, office services and site visits to correct critical health and life safety issues at Many Glacier Hotel. | Interior, Department of / National Park Service | 5/13/2010 |
LOUIS BERGER GROUP, INC., THE | $508,256 | Contract | : Shenandoah National Park - Multiple Road Rehabilitation. | Interior, Department of / National Park Service | 4/08/2010 |
MERIWETHER LEWIS ELECTRIC COOPERATIVE | $215,679 | Contract | : Remove overhead lines and install underground lines - Natchez Trace Parkway, TN | Interior, Department of / National Park Service | 5/14/2010 |
WESTLAKE, REED, LESKOSKY, LTD. | $59,214 | Contract | : Engineering Services for Design of Energy Monitoring System in the Filene Center, Wolf Trap Farm Park for the Performing Arts, Vienna, VA. | Interior, Department of / National Park Service | 4/21/2010 |
HYDROLYNX SYSTEMS INC | $155,675 | Contract | : Siren Flash Flood Warning System for campers at Cottonwood Cove marina in the Lake Mead Recreational Area | Interior, Department of / National Park Service | 5/12/2010 |
MILLER PETROLEUM, INC. | $1,650,348 | Contract | : Solicitation #N20511 plugging oil wells and restoring landscape in the Big South Fork National River | Interior, Department of / National Park Service | 5/13/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $183,582 | Grant | Conservation Activities by Youth Service Organizations: This award funds services to the Chesapeake and Ohio (C & O) Canal National Historic Park from the Student Conservation Association's youth conservation service programs. SCA teams, based at the Headquarters of the C & O National Historical Parkrk in Hagers... Show more | Interior, Department of / National Park Service | 1/21/2010 |
MATRIX MATERIAL HANDLING, INC. | $13,201 | Contract | : SUPPLY HANDRAIL MATERIAL AND HARDWARE FOR NER-ASIS ASSATEAGUE ISLAND NATIONAL SEASHORE - NO INSTALLATION OR LABOR INCLUDED IN THE AWARD | Interior, Department of / National Park Service | 4/13/2010 |
YALMER MATTILA CONTRACTING, INC. | $3,993,137 | Contract | : Keweenaw National Historical Park Union Building Rehabilitation - Phase II. Contract No. C2011101145 KEWE 152272. This project involves the rehabilitation of a Historic Building. The work includes interior rehabilitation of the historic Union Building to | Interior, Department of / National Park Service | 5/06/2010 |
R. J. THOMAS MANUFACTURING COMPANY, INC. | $41,244 | Contract | : GRILLS AND FIRE RINGS | Interior, Department of / National Park Service | 4/27/2010 |
ROCKY MOUNTAIN CONSTRUCTION, LLC | $72,900 | Contract | : Furnishing and delivering surfacing aggregate to the Schonchin Butte Road within Lava Beds National Monument, Siskiyou County, California. | Interior, Department of / National Park Service | 5/13/2010 |
MATTHEWS GROUP, INC., THE | $2,787,290 | Contract | : Rock Creek Park, Rehabilitation Peirce Mill Complex - ROCR, 077569 | Interior, Department of / National Park Service | 4/28/2010 |
GROUNDWORK USA, INC. | $85,000 | Grant | Conservation Activities by Youth Service Organizations: Team of youth landscape workers restoring fields and clearing land at Minute Man National Historic Park | Interior, Department of / National Park Service | 5/06/2010 |
KAPEL CONSTRUCTION INC. | $1,225,163 | Contract | : Upgrade/repair 7.9 miles of existing, native-surfaced roads within Redwood National and State Parks located near the town of Orick, CA. Entails clearing vegetation; salvaging berms of road fill material to rebuild surface elevations and road shape, instal | Interior, Department of / National Park Service | 5/13/2010 |
INNOVAR ENVIRONMENTAL INC | $1,729,167 | Contract | : Install safety closures at abandoned mines throughout the Mojave National Preserve to protect visitors and preserve resources. | Interior, Department of / National Park Service | 4/16/2010 |
MAXXUM CONSTRUCTION CORP. | $43,500 | Contract | : Remove existing wheel chair lift and install new. | Interior, Department of / National Park Service | 5/13/2010 |
URS GROUP, INC. | $158,001 | Contract | : URS has been hired to perform site inspection, quality assurance inspections, project management and coordination for the rehabilitation of the Meridian High Wall in Washington, DC. | Interior, Department of / National Park Service | 4/12/2010 |
HARTRAMPF, INC. | $46,923 | Contract | : Construction Phase services for Rehabilitation of Historic Shirley House at Vicksburg NMP | Interior, Department of / National Park Service | 4/16/2010 |
ESPINA STONE CO. | $8,816,782 | Contract | : BLRI-153096; Blue Ridge Parkway, Allegheny Co., NC. Reconstruct Historic Stone Guardwall; Re-build 30,000 lf of historic stone guardwalls to maintain their structural integrity. | Interior, Department of / National Park Service | 4/26/2010 |
LEAVENGOOD, DAVID ARCHITECT | $51,948 | Contract | : Title III-Construction Management Services - Rehabilitation and Expansion of visitor Center at Big Hole National Battlefield | Interior, Department of / National Park Service | 5/14/2010 |
ANDERSON BURTON CONSTRUCTION, INC. | $9,138,395 | Contract | : demolish and replace flood prone west side maintenance and visitor facilities and replace two trailers and ten cabin Pinnacles National Monument | Interior, Department of / National Park Service | 5/06/2010 |
CREATE GREEN ENERGY INC. | $239,545 | Contract | : Design and Install Photovoltaic Solar Energy System at Golden Gate NRA | Interior, Department of / National Park Service | 9/20/2011 |
CORMAN CONSTRUCTION, INC. | $4,185,391 | Contract | : Catoctin Aqueduct Rehabilitation | Interior, Department of / National Park Service | 4/21/2010 |
ARGENTINE PRODUCTIONS INC | $521,671 | Contract | : Production of exhibit audiovisual and multimedia programming and an optional audio description tour of the finished exhibit for new exhibits at Mammoth Cave National Park in Mammoth Cave, KY. | Interior, Department of / National Park Service | 5/12/2010 |
AJC ARCHITECTS, P.C. | $20,347 | Contract | : Provide space plans and furniture plans for the renovation of Moose Maintenance Bldg at Grand Teton Nat'l Park. | Interior, Department of / National Park Service | 4/26/2010 |
SOMERSET GROUP, INC. | $99,008 | Contract | : Develop and install three interactive multimedia progrms as part of the complete rehabilitation of Hamilton Grange National Memorial. | Interior, Department of / National Park Service | 5/12/2010 |
ENTRIX, INC. | $29,000 | Contract | : TAS::14 1030:: RECOVERY MORA PMIS #152639 & 158069A/E Services, Engineering and Construction Design Services Carbon River Entrance and Emergency Flood Protection Longmire at Milepost 6, Mount Rainier National Park | Interior, Department of / National Park Service | 4/13/2010 |
FIRVIDA CONSTRUCTION CORPORATION | $370,890 | Contract | : Preserve Restore and Protect Pennsylvania Monument in Petersburg Virginia | Interior, Department of / National Park Service | 5/05/2010 |
LOUIS BERGER GROUP, INC., THE | $719,623 | Contract | : Stabilize Ellis Island Seawall | Interior, Department of / National Park Service | 5/14/2010 |
JIM WILKIN TRUCKING LLC | $54,889 | Contract | : Crush 3000 cubic yards Type 2, Class A Aggretate Base and deliver to multiple locations at Great Basin National Park, Baker, NV | Interior, Department of / National Park Service | 5/05/2010 |
MONTANA CONSERVATION CORP | $24,000 | Grant | Conservation Activities by Youth Service Organizations: MCC and NPS, Glacier National Park, wish to build on an historically successful partnership by providing skill-building trail maintenance projects for completion by the MCC crews of young adult Americorps participants. Projects will include trtread mainte... Show more | Interior, Department of / National Park Service | 4/12/2010 |
ATKINS NORTH AMERICA, INC | $164,985 | Contract | : CM Services for Vicksburg National Military Park; Historic Shirley House | Interior, Department of / National Park Service | 4/14/2010 |
CHARLES BLALOCK & SONS, INC. | $4,449,692 | Contract | : Resurface Foothills Parkway (East). Great Smoky Mountains National Park. | Interior, Department of / National Park Service | 5/07/2010 |
PHOENIX MARINE CO. INC. | $19,388,287 | Contract | : Stabilize Ellis Island Seawall | Interior, Department of / National Park Service | 5/07/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $120,696 | Contract | : Construction Managaement Services for Visitor Access and Appreciation Improvements, New River Gorge NR, Historic Nuttalbureg Town site. | Interior, Department of / National Park Service | 5/12/2010 |
K.J. CAIN COMPANY | $219,071 | Contract | : Remove and replace specified windows and doors at Channel Islands National Park. | Interior, Department of / National Park Service | 5/26/2010 |
JOHN G. WAITE ASSOCIATES, ARCHITECTS, PLLC | $25,399 | Contract | : Title III Architectural/Engineering Services for Recovery-Rehabilitation of the Roosevelt Home, Carriage House, Laundry | Interior, Department of / National Park Service | 5/14/2010 |
AJC ARCHITECTS, P.C. | $345,863 | Contract | : Provide Architectural & Engineering Construction Administration Services for the renovation of Moose Maintenance Building at Grand Teton National Park. | Interior, Department of / National Park Service | 4/27/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $205,657 | Contract | : Construction Management for Replacement of Patchogue Bulkheads, Fire Island National Park. | Interior, Department of / National Park Service | 5/14/2010 |
GPPC INC | $742,670 | Contract | : Install Grid-Connected Solar Array at the Visitor Center and Amphitheater, American Memorial Park, Saipan | Interior, Department of / National Park Service | 4/30/2010 |
URS GROUP, INC. | $200,763 | Contract | : Construction management and administration services for the National Park Service (NPS) at Cuyahoga Valley National Park (CUVA) for the construction of a sanitary collection system and constructed wetlands treatment system replacing failing septic tanks i | Interior, Department of / National Park Service | 5/13/2010 |
COMPLETE PACKAGING & SHIPPING SUPPLIES INC. | $25,199 | Contract | : Supply 8 x 8 x 16 ft fiber boards. | Interior, Department of / National Park Service | 3/29/2010 |
DAVEY TREE EXPERT COMPANY, THE | $21,184 | Contract | : Turf care and Tree/Shrub inspection and care at Monocacy National Battlefield Visitor Center. | Interior, Department of / National Park Service | 5/11/2010 |
RIDGWAY VALLEY ENTERPRISES, INC. | $337,748 | Contract | : Demolish exisitng Comfort Station and build new Comfort Station. | Interior, Department of / National Park Service | 4/08/2010 |
RUSSELL STANDARD CORPORATION | $265,427 | Contract | : Shenandoah National Park Asphalt Surface Treatment and Restripe Skyline Drive | Interior, Department of / National Park Service | 4/09/2010 |
WESTERN BUILDING RESTORATION CO INC | $34,343 | Contract | : Restore basement floor at Lindenwald, Martin Van Buren National Historic Site | Interior, Department of / National Park Service | 4/01/2010 |
GREAT BASIN INSTITUTE | $29,178 | Grant | Conservation Activities by Youth Service Organizations: The purpose of this project is to repair approximately 0.4 miles of the Wheeler Peak Trail, including replacing/repair of approximately 500 linear feet of rubber trail surfacing material on this ADA accessible mountain-forest trail. Other projecect work wil... Show more | Interior, Department of / National Park Service | 5/11/2010 |
AAK-DE LOS SANTOS CONSTRUCTION | $169,030 | Contract | : Demolish & Replace Existing Light Towers | Interior, Department of / National Park Service | 5/04/2010 |
MODULAR GENIUS, INC. | $324,058 | Contract | : Temporary Office trailers | Interior, Department of / National Park Service | 5/13/2010 |
TEXAS RAILROAD COMM | $10,372 | Grant | Abandoned Mine Hazard Mitigation: The National Park Service and the Railroad Commission of Texas established a cooperative agreement to protect natural resources within the Big Thicket National Preserve. Two properly plugged oil wells, originally plugged on land, are now located in the | Interior, Department of / National Park Service | 5/03/2010 |
ATKINS NORTH AMERICA, INC | $767,135 | Contract | : CM Services to Stabilize Big Slackwater historic stone wall and towpath in Chesapeake and Ohio National Historic Park | Interior, Department of / National Park Service | 5/13/2010 |
POST BUCKLEY SCHUH & JERNIGAN INC | $24,163 | Contract | : CM Services Westside Levee - Olympic National Park | Interior, Department of / National Park Service | 5/10/2010 |
SYGNOS, INC. | $137,000 | Contract | : INSTALL SAFETY CLOSURES AT 12 EACH ABANDONED MINE LOCATIONS TO PROTECT VISITORS AND PRESERVE RESOURCE HABITAT AT THE YOSEMITE NATIONAL PARK. | Interior, Department of / National Park Service | 5/03/2010 |
SOUTHERN CUSTOM EXHIBITS OF ALABAMA, INC. | $402,065 | Contract | : Provide the NPS with labor, materials, services and facilities and travel necessary to detail, fabricate transport to the site and install all exhibit elements for the Visitor Center at Hamilton Grange NM | Interior, Department of / National Park Service | 4/29/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $58,774 | Grant | Conservation Activities by Youth Service Organizations: This award funded services to the National Park Service Blue Ridge Parkway near Asheville, NC, from the Student Conservation Association's youth conservation service programs. Two SCA youth crews conducted trail rehabilitation along the Abbot LaLake Trail, ... Show more | Interior, Department of / National Park Service | 5/11/2010 |
THE SHERWIN-WILLIAMS COMPANY | $73 | Contract | : Dripless caulk guns - qty 24 | Interior, Department of / National Park Service | 4/08/2010 |
GROUNDWORK USA, INC. | $99,086 | Grant | Conservation Activities by Youth Service Organizations: Restore landscaping along the GW Memorial Parkway with trained youth crews | Interior, Department of / National Park Service | 5/10/2010 |
OLSON ENTERPRISES INC | $53,990 | Contract | : Fencing | Interior, Department of / National Park Service | 5/03/2010 |
LOUIS BERGER GROUP, INC., THE | $332,980 | Contract | : Stabilize Baggage and Dormitory Building | Interior, Department of / National Park Service | 5/12/2010 |
NORTH STAR PAVING & CONSTRUCTION INC | $5,327,717 | Contract | : Replace WWTF & Rehabilitate Collection System at Denali National Park & Preserve | Interior, Department of / National Park Service | 4/26/2010 |
HDR ENGINEERING, INC. | $931,165 | Contract | : Architect/Engineering Construction Services including submittal reviews, office services, and site services for the stabilization of the Ellis Island Seawall, Statue of Liberty Monument. | Interior, Department of / National Park Service | 5/11/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $84,420 | Grant | Conservation Activities by Youth Service Organizations: This award funded services to the National Park Service, George Washington Memorial Parkway in McLean, VA, from the Student Conservation Association's youth conservation service programs. SCA recruited, trained and led a team of youth Habitat t Restoratio... Show more | Interior, Department of / National Park Service | 5/04/2010 |
JOHN G. WAITE ASSOCIATES, ARCHITECTS, PLLC | $109,757 | Contract | : Architectural/Engineering services during construction of Hamilton Grange Exhibits | Interior, Department of / National Park Service | 5/11/2010 |
SHAW LUMBER CO. | $33,999 | Contract | : NATIONAL PARK SERVICE BOARDWALK MATERIAL SUPPLIER OF MATERIAL ONLY 85919 BLUE RIDGE PARKWAY BEDFORD, VA 24523 | Interior, Department of / National Park Service | 4/26/2010 |
ABCON, INC. | $1,856,647 | Contract | : This award includes the Tinkers Creek Aqueduct Repair/Rehabilitation Phase 2 located in the Cuyahoga Valley National Park, Cuyahoga County, Ohio | Interior, Department of / National Park Service | 5/07/2010 |
DIOTTAVIO & CO., INC. | $119,025 | Contract | : restoration of doors and windows for Stirling's Quarters at Valley Forge National Historic Park | Interior, Department of / National Park Service | 4/01/2010 |
RAMSEY NORTH, INC. | $915,021 | Contract | : Project Description: The project will remove two 4,000 gallon heating oil tanks and replace them with a propane fuel system to convert the HVAC system to propane. | Interior, Department of / National Park Service | 4/07/2010 |
AAK-DE LOS SANTOS CONSTRUCTION, LLC | $973,654 | Contract | : Rehabilitate Travertine Nature Center - Chickisaw National Recreation Area | Interior, Department of / National Park Service | 5/06/2010 |
SAYBR CONTRACTORS, INC. | $235,712 | Contract | : Tenant improvements at Sunrise Visitor Center | Interior, Department of / National Park Service | 5/10/2010 |
WESTLAND RESOURCES, INC. | $988,345 | Contract | : Wildlife Exclusion and bat survey and Coronado National Memorial and Saguaro National Park. | Interior, Department of / National Park Service | 5/07/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $30,908 | Grant | Conservation Activities by Youth Service Organizations: This award funded restoration of trails at Cowpens National Battlefield in Chesnee, South Carolina, by the Student Conservation Association (SCA) youth conservation service program. Located in the foothills of Northwestern South Carolina, Cowpenens is an 84... Show more | Interior, Department of / National Park Service | 3/11/2010 |
KRAUS-ANDERSON CONSTRUCTION COMPANY | $35,121,846 | Contract | : Crow Creek Tribal School Stephan, SD | Interior, Department of / National Park Service | 4/29/2010 |
HDR ENGINEERING, INC. | $6,567 | Contract | : Olympic National Park (OLYM) NPI Outfall Miscellaneous Meetings and Tasks | Interior, Department of / National Park Service | 4/20/2010 |
CONSERVATION CORPS, CALIFORNIA | $24,606 | Grant | Conservation Activities by Youth Service Organizations: Project includes repair to the trail tread, thereby improving visitor safety on the Rainbow Falls trail and nearby overlooks. | Interior, Department of / National Park Service | 4/16/2010 |
SAN FRANCISCO CONSERVATION CORPS | $105,000 | Grant | Conservation Activities by Youth Service Organizations: Collaboration with NPS to complete on site preparation and revegetation activites at Mori Pt. National Park as needed to successfully improve endangered species habitat in and adjacent to new trail footprint and surrounding slopes. Will allow M Mori pt to ... Show more | Interior, Department of / National Park Service | 5/11/2010 |
TRI COUNTY CONTRACTORS, INC | $143,488 | Contract | : Resurface Deteriorated Maintenance Area-Oteen Blue Ridge Parkway | Interior, Department of / National Park Service | 5/06/2010 |
QUINN EVANS ARCHITECTS INC | $33,250 | Contract | : Additional Title II Design Services for interior rehabilitation of the Union Building at Keweenaw National Historical Park, Calumet, Michigan | Interior, Department of / National Park Service | 2/26/2010 |
BIOLOGICAL MEDIATION SYSTEM, INC | $71,371 | Contract | : The award covered two prefabricated restroom buildings, our model OUTBACK with aluminum base and an OUTBACK with a DEVAP 2000, our patented waterless waste treatment system. We manufactured at our plant in Ault, CO and shipped to the site by common carri | Interior, Department of / National Park Service | 5/12/2010 |
URS GROUP, INC. | $55,177 | Contract | : Engineering support during construction, including answering Contractor requests for information (RFIs), reviewing product and material information provided by the Contractor (submittals) and preparing record Drawings for the Nippon Paper Industries Water | Interior, Department of / National Park Service | 6/08/2010 |
PDI - SHEETZ CONSTRUCTION CORPORATION | $105,188 | Contract | : Rehabilitation Mt. Vernon Trail Bridge No. 7, Alexandria, VA - The work of this contract consists of providing equipment, materials, supervision, and personnel to rehabilitate Mt. Vernon trail Bridge No. 7. The work of this contract is located at MVT Brid | Interior, Department of / National Park Service | 5/13/2010 |
JOHN DEERE SHARED SERVICES, INC. | $179,725 | Contract | : John Deere 672G Motor Grader | Interior, Department of / National Park Service | 9/08/2009 |
ENYEART CEDAR PRODUCTS, LLC | $25,600 | Contract | : 3/4 x 10 Siding | Interior, Department of / National Park Service | 2/03/2010 |
GRAVES AND GRAVES CONSTRUCTION COMPANY, INC. | $271,310 | Contract | : Construct 3 Comfort Stations at the Meriwether Lewis site on the Natchez Trace Parkway. | Interior, Department of / National Park Service | 5/06/2010 |
ASH & WHITE CONSTRUCTION CO. | $4,133,011 | Contract | : Carlsbad Caverns National Park, Eddy County, NM. Structural Steel repair and Lead Based Paint Abatement in Elevator Shaft Cave 116245 | Interior, Department of / National Park Service | 5/13/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $315,205 | Contract | : Construction Management Services for the Rehabilitation of Arlington House Outbuildings and Grounds, Phase 2a and 2b. | Interior, Department of / National Park Service | 5/13/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $25,346 | Grant | Conservation Activities by Youth Service Organizations: This award funds services to the National Park Service Blue Ridge Parkway near Asheville, NC, from the Student Conservation Association's youth conservation service programs. An SCA youth crew conducted trail rehabilitation along the Richland-BaBalsam Gap T... Show more | Interior, Department of / National Park Service | 5/11/2010 |
RAZZ CONSTRUCTION, INC. | $379,127 | Contract | : C9512090116, Olympic National Park Bridge Rehabilitation | Interior, Department of / National Park Service | 4/20/2010 |
JOHN G. WAITE ASSOCIATES, ARCHITECTS, PLLC | $68,100 | Contract | : Hamilton Grange - Exhibit Production Support | Interior, Department of / National Park Service | 5/13/2010 |
C-2 CONSTRUCTION INC | $260,614 | Contract | : Install fire sprinkler and alarm system in 6 park buildings, and changed HDPE pipe to 4 pipe. Also added additional telecom lnes, trenching, conduit and wiring to phone pedestals and heat sensors. Project is complete. | Interior, Department of / National Park Service | 4/21/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $76,530 | Grant | Conservation Activities by Youth Service Organizations: This award has funded services to the Great Smoky Mountains National Park in Cherokee, NC, from the Student Conservation Association's youth conservation service programs. SCA recruited, trained and led two crews of youth, who learned green jobob skills wh... Show more | Interior, Department of / National Park Service | 5/07/2010 |
BIOHABITATS, INC. | $910,093 | Contract | : NPS Jean Lafitte invasive plant removal and hydrologic reconnection of former wetland areas. This project involves the removal of invasive Chinese Tallow from side-spoils associated with oil and gas production access channels. | Interior, Department of / National Park Service | 5/14/2010 |
FALLON & WILKINSON LLC | $286,523 | Contract | : Reproduction Furniture for Hamilton Grange The following pieces were examined, documented, and reproduced: - Armchairs, three, Louis XVI style, 1790-1795, upholstered in green silk; for the Parlor. - Chairs, side, two, Louis XVI style, 1790-1795, upholste | Interior, Department of / National Park Service | 4/28/2010 |
RIDGWAY VALLEY ENTERPRISES, INC. | $53,508 | Contract | : Replace Headquarters Building windows and exterior doors with associated flashing and trim work. | Interior, Department of / National Park Service | 4/05/2010 |
THE CHRISTMAN COMPANY | $4,372,174 | Contract | : Repairs to the existing Perry's Victory and International Peace Memorial to address the structural issues of the Observation Deck and Abacus. | Interior, Department of / National Park Service | 9/14/2009 |
DRY STONE MASONRY INSTITUTE OF AMERICA | $110,089 | Grant | Conservation Activities by Youth Service Organizations: Dry-Laid Stone Walls Bordering the Home of FDR National Historic Site. | Interior, Department of / National Park Service | 5/04/2010 |
ATLANTIC COAST DOCK BUILDING CORP | $2,747,053 | Contract | : Design - Build Replace Patchogue Bulkheads | Interior, Department of / National Park Service | 5/05/2010 |
HDR ENGINEERING, INC. | $47,615 | Contract | : A&E services during Xonstruction and Construction Management Services for the Griff Creek Replacement at Olympic National Park (OLYM) | Interior, Department of / National Park Service | 4/29/2010 |
WISS, JANNEY, ELSTNER ASSOCIATES, INC. | $26,344 | Contract | : Fort Mason - rehabilitate HVAC system | Interior, Department of / National Park Service | 4/01/2010 |
APSI CONSTRUCTION MANAGEMENT | $468,519 | Contract | : Provide Construction Management as Agent (CMa)services for the National Park Services. 1. Pinnacles National Monument (San Benito County, CA) a. 100% Construction Documents due from contractor October 8, 2010. After review, anticipate mid-November const | Interior, Department of / National Park Service | 6/01/2010 |
DWG & ASSOCIATES, INC. | $304,806 | Contract | : PMIS#128590-Rehabilitate Unsafe and Unsanitary Restroom Facilities, Recovery Project, Rehabilitate Unsafe and Unsanitary Restroom Facilities, The GC shall provide and install 8 vault toilets complete with vault evaporative system comfort station structur | Interior, Department of / National Park Service | 4/14/2010 |
ANDERSON, JEFFREY T | $18,600 | Contract | : supplied ohia poles to Hawaii Volcanoes National Park | Interior, Department of / National Park Service | 5/10/2010 |
QUINN EVANS ARCHITECTS INC | $41,321 | Contract | : The Rock Creek Park project includes improvements to the mill and its surrounding landscape, as well as parking lot modifications, a new bus stop drop-off and driveway , pedestrian path and trail reconfigurations, a new comfort station, and in consultaion | Interior, Department of / National Park Service | 3/23/2010 |
SOUTHEAST ALASKA GUIDANCE ASSOCIATION | $25,349 | Grant | Conservation Activities by Youth Service Organizations: A SAGA-AmeriCorps crew of 7-9 young people spent 37 service-days renovating a 1 mile (app.) section of the Chilkoot Historical Trail, Near Old Sheep Camp; special attention was paid to cultural historic sites along this section of the trail. Thehe project r... Show more | Interior, Department of / National Park Service | 5/11/2010 |
CUTTING EDGE GROUP, LLC | $1,430,021 | Contract | : The general construction of conduit and conductors from new uninteruptable power supplies to perimeter locations and the general construction of conduit and fiber optic cabling to perimeter locations to support data transmission on Liberty and Ellis Islan | Interior, Department of / National Park Service | 5/05/2010 |
SUMMITT FORESTS INC. | $742,822 | Contract | : CHICKASAW NAT. REC. AREA (NRA) MANUAL AND MECHANICAL TREATMENT OF 2588 ACRES | Interior, Department of / National Park Service | 6/07/2010 |
YERBA BUENA ENGINEERING & CONSTRUCTION, INC. | $762,544 | Contract | : Glaciers National Park Rehabilitate Comfort Station in Fish Creek Campground | Interior, Department of / National Park Service | 4/09/2010 |
HDR ENGINEERING, INC. | $24,633 | Contract | : Sandy Hook Photovoltaic Installation | Interior, Department of / National Park Service | 4/30/2010 |
POST BUCKLEY SCHUH & JERNIGAN INC | $228,809 | Contract | : CM Services for two paving projects in Great Smoky Mountains National Park. | Interior, Department of / National Park Service | 5/13/2010 |
TRAUTMAN'S PAINTING | $59,300 | Contract | : cover flooring ,remove lead paint ,seal walls, repaint | Interior, Department of / National Park Service | 2/22/2010 |
B.C. SCHMIDT CONSTRUCTION, INC. | $498,950 | Contract | : Due to safety concerns, the Keane Wonder Mine is closed to visitors. Construction services to provide stabilization to the Keane Wonder Mine Aerial Tramway by repaing Towers 8 and 9, the upper terminal and lower terminal. Includes project design, managem | Interior, Department of / National Park Service | 5/13/2010 |
INNOVAR ENVIRONMENTAL INC | $77,938 | Contract | : Install safety closures at abandoned mines to protect visitors and preserve resources. | Interior, Department of / National Park Service | 4/08/2010 |
J JONASSEN INC | $9,391 | Contract | : Amendment to pay for additional cargo insurance required by the National Park Service | Interior, Department of / National Park Service | 6/16/2010 |
TAB CONSTRUCTION COMPANY, INC. | $414,285 | Contract | : Repave Linville Falls and Balsam Gap Maintenance Areas | Interior, Department of / National Park Service | 5/05/2010 |
GABEL ASSOCIATES INC. | $101,214 | Contract | : Energy and Water Use Audits: Gates of the Arctic National Park and Preserve, Katarni National Park and Preserve, Klondike Gold Rush National Historical Park, Western Arctic National Park Land, and Wrangell-St. Elias National Park and Preserve | Interior, Department of / National Park Service | 5/13/2010 |
RIDGWAY VALLEY ENTERPRISES, INC. | $459,374 | Contract | : Increase Accuracy of Water Meters by Replacing Meters and Automating Meter Reading System | Interior, Department of / National Park Service | 4/28/2010 |
CREATIVE TIMES DAYSCHOOL, INC. | $351,130 | Contract | : Rehabilitate Visitor Fee Contact Station at Cedar Breaks National Monument, UT | Interior, Department of / National Park Service | 4/09/2010 |
REISINGER, DONALD E. INC. | $123,565 | Contract | : REPAIR IRONMASTER HOUSE | Interior, Department of / National Park Service | 1/14/2010 |
LYNCH CREEK QUARRY LLC | $40,492 | Contract | : Gravel backfill for trench being dug for the installation of utility line in Mt Rainier National Park | Interior, Department of / National Park Service | 4/19/2010 |
CONSERVATION CORPS | $42,000 | Grant | Conservation Activities by Youth Service Organizations: $42,000 in Recovery Act funding from the National Park Service was contracted with Minnesota Conservation Corps to engage youth (ages 15-18) in habitat restoration projects on Isle Royale. Crew of 2 AmeriCorps leaders and 7 youth will complete h hiking trai... Show more | Interior, Department of / National Park Service | 2/18/2010 |
CONSERVATION CORPS, CALIFORNIA | $112,500 | Grant | Conservation Activities by Youth Service Organizations: Project objective is to build approximately two miles of a 4-foot wide trail starting at the Lady Bird Johnson Grove. | Interior, Department of / National Park Service | 5/10/2010 |
FANT, JERRY | $36,150 | Contract | : Closure of State of Texas Abandoned Mine, protection of human health and safety, and protection of federally listed species | Interior, Department of / National Park Service | 4/19/2010 |
CTS NORTHWEST, INC. | $563,922 | Contract | : More reliable power system for the Parks Department at Hurrican Ridge | Interior, Department of / National Park Service | 5/11/2010 |
COLOR-AD INC | $297,387 | Contract | : Fabricate and Installation of exhibit components for Mount Rainier National Park | Interior, Department of / National Park Service | 4/26/2010 |
ROESLING NAKAMURA TERADA ARCHITECTS, INC | $28,317 | Contract | : Death Valley National Park, California-Specialized Review of LEED Submittals and site visits for Replacement of Twelve Deteriorated Trailers at Grapevine Housing Area, Phase II-PMIS #121639 | Interior, Department of / National Park Service | 5/18/2010 |
ENVIROTEMPS, INC. | $14,219 | Contract | : Roofing Services | Interior, Department of / National Park Service | 5/03/2010 |
CBS CONTRACTING | $31,600 | Contract | : 561730, clearing underbrush in park | Interior, Department of / National Park Service | 4/30/2010 |
ANDERSON HALLAS ARCHITECTS, PC | $80,280 | Contract | : This project will rehabilitate the failing potable water storage and distribution system and provide adequate fire protection at the Ash Mountain Headquarters and housing area in Sequoia National Park. This project will also replace one 100,000 and one 5 | Interior, Department of / National Park Service | 5/06/2010 |
MARK E RAMSEY, INC | $242,820 | Contract | : Provide all supervision, labor, materials, tools equipment and transportation necessary to replace cedar shake and standing seam metal roofing on eleven structures, one with the supply and installation of a photovoltaic system on one of the eleven structu | Interior, Department of / National Park Service | 5/01/2010 |
MARTIN MARIETTA MATERIALS, INC. | $35,972 | Contract | : Supply crushed stone for toe path resurfacing of Chesapeake and Ohio Canal | Interior, Department of / National Park Service | 6/23/2010 |
SUNWIZE TECHNOLOGIES, INC. | $139,842 | Contract | : Installation of solar electric system | Interior, Department of / National Park Service | 4/21/2010 |
GROUP14 ENGINEERING, INC. | $48,857 | Contract | : Total building commissioning for Denali ESFMB | Interior, Department of / National Park Service | 5/10/2010 |
HDR ENGINEERING, INC. | $458,278 | Contract | : Provide Connstruction Management Services for Abandoned Mine Lands (AML) for 9 Pacific West Region Parks: Mojave National Preserve, Death Valley National Park, Joshua Tree National Park, Mount Rainer National Park, Olympic National Park, Lake Mead Nation | Interior, Department of / National Park Service | 5/10/2010 |
AJC ARCHITECTS, P.C. | $109,287 | Contract | : Provide Architectural & Engineering Construction Administration Services and Commissioning Services for a new Collections Facility at Hopewell Cultural National Historic Park. | Interior, Department of / National Park Service | 4/08/2010 |
PARKS AND RECREATION, CALIFORNIA DEPARTMENT OF | $460,000 | Grant | Redwood National Park Cooperative Management with the State of California: This award is for the reconstruction and improvement of storm damaged roads in California Department of Parks and Recreation's Mill Creek Acquisition located in the North Coast Redwoods District. A December 2008 storm caused d the complete failure of a lar... Show more | Interior, Department of / National Park Service | 4/13/2010 |
JAY CASHMAN, INC. | $6,119,056 | Contract | : The project is located in a remote area of the Everglades National Park near the southwestern tip of mainland Florida in the Cape Sable area, roughly 12 miles west of Flamingo, Florida. The objective of the Project is the construction of two (2) new dam | Interior, Department of / National Park Service | 5/04/2010 |
MUIR CONTRACTING, INC. | $23,887 | Contract | : North Cascades National Park, Repair Rock Barbs, Stehekin, WA. | Interior, Department of / National Park Service | 4/14/2010 |
FLETCHER FARR AYOTTE INC. | $12,569 | Contract | : Title III Construction Management Services for Replacement of Flooring, Doors and selected furnishings at Sunrise Visitor Center, Mt. Rainier. | Interior, Department of / National Park Service | 6/17/2010 |
SUNWIZE TECHNOLOGIES, INC. | $381,251 | Contract | : installation of solar electric systems Park | Interior, Department of / National Park Service | 4/09/2010 |
MICHAEL L. FOSTER & ASSOCIATES, INC. | $308,535 | Contract | : Replace King Salmon maintenance building | Interior, Department of / National Park Service | 5/20/2010 |
GAITHERSBURG FARMERS SUPPLY, INC. | $99,987 | Contract | : deliver tractor/mower | Interior, Department of / National Park Service | 9/22/2009 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $510,057 | Contract | : Construction Scheduling services to be provided in the National Park Service DSC offices in Lakewood, CO. | Interior, Department of / National Park Service | 5/13/2010 |
BARGMANN HENDRIE & ARCHETYPE, INC. | $34,259 | Contract | : Rehabilitate Independence Hall Tower; Additional Services relating to exterior lighting, obtaining contractor consulting for constructability issues, clock restoration consultant, bid phase services | Interior, Department of / National Park Service | 2/01/2010 |
NDL GROUP, INC. | $100,451 | Contract | : Rehabilitation/replacement of 4 fish cleaning stations at Lake Mead Recreational Area. Contract includes the purchase of 4 cleaning basins, industrial-grade disposals, electrical and plumbing installation on site. | Interior, Department of / National Park Service | 4/14/2010 |
QUINN EVANS ARCHITECTS INC | $104,292 | Contract | : Title III Construction Phase: waiting to complete as-built documentation in October 2011 | Interior, Department of / National Park Service | 5/11/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $113,181 | Grant | Conservation Activities by Youth Service Organizations: AP This award has funded services to the Marsh-Billings Rockefeller National Historic Park in Woodstock, Vermont, from the Student Conservation Association's youth conservation service programs. A team of SCA Conservation Interns worked on contntrolling in... Show more | Interior, Department of / National Park Service | 5/05/2010 |
WORCESTER EISENBRANDT, INC. | $939,265 | Contract | : RECOVERY - Stabilize Historic Culvert 182 | Interior, Department of / National Park Service | 4/30/2010 |
GRIMM, CHARLES W. CONSTRUCTION INC. | $118,424 | Contract | : Recovery, repair and weatherize three buildings for energy efficiency | Interior, Department of / National Park Service | 2/16/2010 |
R. J. THOMAS MANUFACTURING COMPANY, INC. | $132,800 | Contract | : WHEELCHAIR ACC PICNIC TABLES | Interior, Department of / National Park Service | 5/02/2010 |
GRAND PORTAGE RESERVATION TRIBAL COUNCIL | $1,083,550 | Grant | Bureau of Indian Affairs Facilities_Operations and Maintenance: On land leased by the NPS from the Grand Portage Band construct new housing or twin dormitories with associated parking lot linked to the housing with sidewalks. | Interior, Department of / National Park Service | 5/10/2010 |
WELLVILLA CONSTRUCTION, INCORPORATED | $1,603,665 | Contract | : Road Rehabiliation, Campgrounds Maintenance Areas, Shenandoah National Park | Interior, Department of / National Park Service | 6/24/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $25,000 | Grant | Conservation Activities by Youth Service Organizations: This award funds services to the Natonal Park Service Appalachian National Scenic Trail, from the Student Conservation Association's youth conservation service programs. Led by SCA staff crew Leaders, the youth crew members recieved environmentatal educatio... Show more | Interior, Department of / National Park Service | 5/10/2010 |
LOUIS BERGER GROUP, INC., THE | $229,913 | Contract | : Construction Management Services - Catoctin Aqueduct. This project will rehabiliate the aqueduct and remove the temporary bridge. The project will include repair and or reconstruction of bridge piers using injection grouting as well as new cast-in-place c | Interior, Department of / National Park Service | 4/29/2010 |
SUMERSETT CONSTRUCTION INC. | $865,345 | Contract | : Harpers Ferry National Park Service Anthony Library lanscaping renovations | Interior, Department of / National Park Service | 5/04/2010 |
NATIONVIEW, LLC | $2,438,671 | Contract | : Preservation and Rehabilitation of Moton Field, Buildings, Grounds, and Construction of Visitor Facilities, Tuskegee Airmen National Historic Site, Tuskegee, Alabama | Interior, Department of / National Park Service | 5/04/2010 |
SUNWIZE TECHNOLOGIES, INC. | $801,434 | Contract | : Installation of solar electric system.Park | Interior, Department of / National Park Service | 4/07/2010 |
YERBA BUENA ENGINEERING & CONSTRUCTION, INC. | $399,968 | Contract | : ARRA PMIS 148433 Demolish 4 houses in Camino del Canyon | Interior, Department of / National Park Service | 5/06/2010 |
REVA MURPHY ASSOCIATES, INC. | $83,525 | Contract | : Lake Mead Roofing | Interior, Department of / National Park Service | 3/25/2010 |
RIDGWAY VALLEY ENTERPRISES, INC. | $225,749 | Contract | : Installation of a new HVAC System in the Fee Management Building. Remodeling of the Shrine of the Ages building to include: renovating restrooms; new plumbing fixtures; new ceramic tile; new paint; partial carpet replacement and some electrical work. | Interior, Department of / National Park Service | 2/03/2010 |
COLORADO ASPHALT SERVICES, INC. | $31,336 | Contract | : Asphalt Cold Patch | Interior, Department of / National Park Service | 4/13/2010 |
CHESTER KING | $783,000 | Contract | : Archaeological studies related to construction of a visitor center at King Gillette Ranch SMMNRA | Interior, Department of / National Park Service | 4/16/2010 |
HDR ENGINEERING, INC. | $252,107 | Contract | : Construction Management Services for the replacement of two failed plugs (dams) at Cape Sable | Interior, Department of / National Park Service | 5/11/2010 |
WILDLANDS INC | $605,775 | Contract | : Excavation and earthwork to fill in contaminated fish ponds and soil stabilization and revegetation of disturbed areas at Great Sand Dunes National Park. | Interior, Department of / National Park Service | 5/05/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $55,000 | Grant | Conservation Activities by Youth Service Organizations: This award funded services to the National Park Service, George Washington Memorial Parkway in McLean, VA, from the Student Conservation Association's youth conservation service programs. SCA is training and leading a youth Conservation Crew, , who will l... Show more | Interior, Department of / National Park Service | 5/04/2010 |
COLF LANDSCAPE CONSTRUCTION | $227,256 | Contract | : The project is for a contractor to resurface the Spruce Mill Trail within Fort Vancouver National Historic Site in accordance with the Project Specificaitons incorporated herein. Contractor shall provide all supervision, labor, materials, tools, equipmen | Interior, Department of / National Park Service | 5/14/2010 |
COOPER ZIETZ ENGINEERS, INC | $12,064 | Contract | : Construction Management Services for installation of fire protection system System at Headquarters Craters of the Moon National MonumentPMIS # 129621 (CRMO) | Interior, Department of / National Park Service | 5/13/2010 |
WALSTEN'S GARAGE DOORS INC | $28,322 | Contract | : garage doors and openers | Interior, Department of / National Park Service | 5/14/2010 |
HARBOR OFFSHORE, INC. | $1,863,033 | Contract | : Olympic National Park, WA NPI Outfall | Interior, Department of / National Park Service | 5/13/2010 |
APAC-ATLANTIC, INC. | $3,727,757 | Contract | : Great Smoky Mountains National Park - Repave Heintooga Rd including the following shallow depth, full depth, and geo-grid patching, resurfacing of Heintooga Ridge Road, culvert repairs, and various concrete repair items | Interior, Department of / National Park Service | 5/07/2010 |
HARRIS ENVIRONMENTAL GROUP | $81,013 | Contract | : Work involves performing project management to ensure compliance of the NPS?s construction contract for the construction of closures at AMLs in Coronado National Memorial and Saguaro National Park. Work under this contract requires a biological monitor f | Interior, Department of / National Park Service | 5/12/2010 |
GANAHL LUMBER COMPANY | $8,390 | Contract | : Fencing materials | Interior, Department of / National Park Service | 5/12/2010 |
CARVELL, KENT CONSTRUCTION CO, INC | $631,260 | Contract | : Meriwether Lewis Site Utilities | Interior, Department of / National Park Service | 5/06/2010 |
MIDWEST WELDING & MACHINE, INC. | $73,390 | Contract | : 0001 Troughs, Weirs, etc. 0002 Modification #1 | Interior, Department of / National Park Service | 5/06/2010 |
CONSERVATION, MAINE DEPARTMENT OF | $25,000 | Grant | Conservation Activities by Youth Service Organizations: Support for the maintenance and rehabilitation of the Appalachian Trail and associated facilities in Maine through youth serving programs. | Interior, Department of / National Park Service | 5/12/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $31,603 | Grant | Conservation Activities by Youth Service Organizations: This award funded restoration of the environment and public areas at Cowpens National Battlefield in Chesnee, South Carolina, from the Student Conservation Association (SCA) youth conservation service program. Located in the foothills of Northwewestern Sout... Show more | Interior, Department of / National Park Service | 2/19/2010 |
INSTITUTE FOR WILDLIFE STUDIES INC | $96,402 | Contract | : In 1985, Pinnacles National Monument (PNM) began construction of a perimeter fence to keep out feral pigs. The fence enclosing 14,500 acres was completed in 2003. Pig eradication efforts ensued from 2003 to 2006, creating a pig free zone within the enclos | Interior, Department of / National Park Service | 4/25/2010 |
KADON TRUCKING, INC. | $34,496 | Contract | : Trucking and Material | Interior, Department of / National Park Service | 9/23/2009 |
NOR-CAL PUMP & WELL DRILLING, INC | $153,700 | Contract | : Abandonment of 15 water wells within Pt. Reyes National Seashore Park. | Interior, Department of / National Park Service | 5/14/2010 |
ANDERSON BURTON CONSTRUCTION, INC. | $488,178 | Contract | : CONSTRUCT EGRESS OFF OF RAISED REAR PORCHES (CONSTRUCTION OF STAIRS/HANDRAILS AND CUT THROUGH EXISTING RAILING) AND CONSTRUCT EXTENSIONS OF EXISTING ROOFLINES OVER HVAC EQUIPMENT TO MATCH EXISTING ROOFLINES OF FOUR SINGLE FAMILY HOUSES AND FIVE DUPLEX UNI | Interior, Department of / National Park Service | 3/26/2010 |
ROC R CAIVANO | $319,143 | Contract | : Contract supervision of rehabilitation of roads, grounds, building renovations at Schoodic Education & Research Center | Interior, Department of / National Park Service | 5/13/2010 |
SOUTHERN CUSTOM EXHIBITS OF ALABAMA, INC. | $1,534,553 | Contract | : Provide the NPS with labor, materials, services and facilities and travel necessary to detail, fabricate and install all exhibit elements for the Visitor Center at Mammoth Cave NP | Interior, Department of / National Park Service | 5/13/2010 |
DANIEL J. KEATING COMPANY | $4,394,000 | Contract | : Rehabilitate Independence Hall Tower | Interior, Department of / National Park Service | 5/04/2010 |
KGCI INC | $176,728 | Contract | : Recovery ACAD Demo Bldgs | Interior, Department of / National Park Service | 4/09/2010 |
WATERSHED ENVIRONMENTAL SOLUTIONS LLC | $776,512 | Contract | : The purpose of this project is to replace the existing culvert with a bottomless fish friendly culvert for permanent fish passage. The present culvert is a barrier for fish passage. This has affected the endangered Bull Trout species. This new culvert | Interior, Department of / National Park Service | 5/05/2010 |
CTA INC. | $63,341 | Contract | : Construction Administration and commissioing for the construction of a heating and air conditioning upgrade at Glacier National Park Headquarters. | Interior, Department of / National Park Service | 6/03/2010 |
TRIAD WESTERN CONSTRUCTORS, INC. | $7,222,347 | Contract | : Design and construction of approximately 31,640 linear feet (6 miles) of 6 inch stainless steel main water line and various components between the existing Chapin Mesa water tanks and the Park's north boundary in the Montezuma Valley. The new line will be | Interior, Department of / National Park Service | 2/26/2010 |
STANDARD RESTORATION AND WATERPROOFING COMPANY, INC. | $57,159 | Contract | : The contract is for Wolf Trap National Park for the Performing Arts Filene Center. This facility has experienced a failure of the siding, flashing, vapor barrier and sealant in the parapet wall above the stage. The purpose of this project is to replace th | Interior, Department of / National Park Service | 1/29/2010 |
ANDERSON HALLAS ARCHITECTS, PC | $252,410 | Contract | : The Quarry Visitor Center (QVC) was constructed in 1956-57 to protect and provide visitor access and interpretation of the greatest quarry of Jurassic dinosaurs in the world. The QVC was closed in 2006 after a condition assessment identified some previou | Interior, Department of / National Park Service | 3/14/2010 |
AES PRECAST COMPANY, INC. | $33,850 | Contract | : 13' x 15' Precast Concrete Storage Building. | Interior, Department of / National Park Service | 10/23/2009 |
QUINN EVANS ARCHITECTS INC | $43,726 | Contract | : The Catoctin Aqueduct will be repaired and or reconstructed of bridge piers using injection grouting as well as new cast-in-place concrete. The rehabilitation will use recovered arch stone as well as newly quarried stone to complete the structure. This p | Interior, Department of / National Park Service | 5/06/2010 |
SHOOP AND SONS | $56,985 | Contract | : Provide and deliver to Chickamauga & Chattanooga NMP 3370 LaFayette Road Ft. Oglethorpe, GA 30742 8,700 Western Split Cedar Fence Rails 10 ft. long and stackable. With no tenons. | Interior, Department of / National Park Service | 5/19/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $28,672 | Grant | Conservation Activities by Youth Service Organizations: The award provided funding for repair and reconditioning of trails at the Isle Royale National Park in Michigan, from the Student Conservation Association's youth conservation service program. The work helped to improve and maintain public trailil systems u... Show more | Interior, Department of / National Park Service | 3/02/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $240,898 | Contract | : On-site construction management services required for the construction of a new collection facility (approximately 2300 SF) attached to the existing Resource Management Building. at the Hopewell Culture Museum at the Hopewell Culture NHP. the contract ha | Interior, Department of / National Park Service | 4/05/2010 |
RAILROAD CONSTRUCTORS, INC. | $3,618,971 | Contract | : Valley Railway - Rail Rehabilitation, crosstie replacement and SR 303 crossing surface replacement at Cuyahoga Valley National Park, Guyahoga and Summit Counties, Ohio | Interior, Department of / National Park Service | 5/07/2010 |
JC MILLBANK CONSTRUCTION CO INC | $1,087,000 | Contract | : Rehabilitaion of the Carriage house and Laundry buildings at the Franklin D Roosevelt Home in Hyde Park NY. Work to be done includes masonry,paver and cement work, roofing and siding, plumbing, electrical, painting and also extensive carpentry repairs. | Interior, Department of / National Park Service | 4/27/2010 |
JOHNSON, MIRMIRAN & THOMPSON, INC. | $341,748 | Contract | : On-call construction management and inspection services for NPS facilities nationwide. Per the RFP, typical assignments range from conventional to complex construction projects, usually interdisciplinary in nature, such as water supply, treatment and dis | Interior, Department of / National Park Service | 6/02/2010 |
QUINN EVANS ARCHITECTS INC | $53,535 | Contract | : Meridian Hill Park is part of Rock Creek Park. Two main areas of concern; stabilize the wall movement and address the low design bearing pressure assigned to the soils supporting the wall. To correctthese issuest, grouted tiebacks will be installed along | Interior, Department of / National Park Service | 4/27/2010 |
CXT INCORPORATED | $51,181 | Contract | : TAS::14 1035 RECOVERY LARO PMIS # 154746 SUPPLY AND DELIVER VAULT TOILETS TO LAKE ROOSEVELT, WA. JONES BAY, KELLER FERRY, SEVEN BAYS, FT. SPOKANE. | Interior, Department of / National Park Service | 5/06/2010 |
ONSSI ENTERPRISES | $65,500 | Contract | : Painting historical signs | Interior, Department of / National Park Service | 4/09/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $227,445 | Contract | : Construction Management Services to rehabilitate the landscape in the vicinity of the Peirce Mill complex and the c.1829 Peirce Mill Structure to all it to be reopened to the public. The project will provide a water intake to power the mill; address mech | Interior, Department of / National Park Service | 5/13/2010 |
BELL/BISCAYNE JV, LLC | $3,170,578 | Contract | : Rehabilitate Arlington House, Outbuildings and Grounds, Phase 2a and 2b GWMP-150123. | Interior, Department of / National Park Service | 5/13/2010 |
DEERE & COMPANY | $39,281 | Contract | : Purchase of a front mower. | Interior, Department of / National Park Service | 1/07/2010 |
AMERICAN CONSERVATION EXPERIENCE | $44,400 | Contract | : The objective of this project is to participate collaboratively in conservation activities to install fences, gates, and associated barriers to relieve trespass motor vehicle problems, which are damaging the resource. The project will provide for insalla | Interior, Department of / National Park Service | 4/26/2010 |
COOPER ZIETZ ENGINEERS, INC | $6,446 | Contract | : Construction Management Services for replacemnt of path to Campground to meet ADA requirements Headquarters Craters of the Moon National Monument PMIS # 138998 (CRMO) | Interior, Department of / National Park Service | 5/13/2010 |
DATALED TECHNOLOGIES, INC. | $29,000 | Contract | : T-8 LED TUBES | Interior, Department of / National Park Service | 2/04/2010 |
BEYER BLINDER BELLE, ARCHITECTS AND PLANNERS, LLP | $139,945 | Contract | : Title III Construction Administration Services for the Rehabilitation of Arlington House, Outbuildings and Grounds, Phase 2a and 2b. | Interior, Department of / National Park Service | 5/13/2010 |
HDR ENGINEERING, INC. | $62,728 | Contract | : Replace Frontcountry Wastewater Facility and Rehabilitate Collection System | Interior, Department of / National Park Service | 4/19/2010 |
NFIRMC JOINT VENTURE | $299,659 | Contract | : Install Safety Closures at Abandoned Mines to Protect Visitors and Preserve Resources at Lake Mead along the AZ/NV border. | Interior, Department of / National Park Service | 4/08/2010 |
TRI STATE HOME SERVICES LLC | $99,999 | Contract | : Replacement of multiple HVAC units for National Park Service in Harpers Ferry, West Virginia. | Interior, Department of / National Park Service | 5/12/2010 |
HEARTWOOD PACIFIC, LLC | $482,994 | Contract | : Replace roof and install photovoltaic system at Hawaii Volcanoes National Park. | Interior, Department of / National Park Service | 4/29/2010 |
SUNWIZE TECHNOLOGIES, INC. | $82,983 | Contract | : Installatin of a Photovoltaic electric system. | Interior, Department of / National Park Service | 4/16/2010 |
ONAN CORPORATION | $31,857 | Contract | : 50 Kw Generator set and spare parts for the Cuyahoga Vally National Park | Interior, Department of / National Park Service | 5/16/2010 |
ATKINS NORTH AMERICA, INC | $117,958 | Contract | : CM Services Mint Springs Bluff Stabilization Vicksburg National Military Park | Interior, Department of / National Park Service | 4/30/2010 |
MSC DESIGN BUILD LLC | $1,799,858 | Contract | : construction of a new 8 plex living quarters at Yellowstone National park, includes site grading, foundation, wood framed construction, new sidewalks, heating systems, landscape restroation | Interior, Department of / National Park Service | 5/13/2010 |
GLUTH BROTHERS ROOFING CO., INC. | $102,026 | Contract | : Install Green Roof at Indiana Dunes National Lakeshore, IN | Interior, Department of / National Park Service | 6/25/2010 |
MATHEUS LUMBER COMPANY, INC. | $6,851 | Contract | : Boardwalk Materials | Interior, Department of / National Park Service | 4/27/2010 |
A P S CONTRACTORS, INC. | $5,347,724 | Contract | : Contract No. 1443C2011100073, Ellis Island Stabilization of the Baggage and Dormitory Building | Interior, Department of / National Park Service | 5/04/2010 |
THE STUDENT CONSERVATION ASSOCIATION INC | $35,178 | Grant | Conservation Activities by Youth Service Organizations: This award funded services to the Minuteman National Historical Park in Concord, MA, from the Student Conservation Association's youth conservation service programs. SCA Community Crew participants gained job skills and expereince while restorining trails a... Show more | Interior, Department of / National Park Service | 5/10/2010 |
PCC PREFERRED CONTRACTING & CONSULTING LLC | $458,570 | Contract | : Tram Shelter and Fueling Station Design Build Construction of prefabricated steel shade shelter and biodiesel fueling system. | Interior, Department of / National Park Service | 5/12/2010 |
RIDGWAY VALLEY ENTERPRISES, INC. | $93,138 | Contract | : Rehabilitation of Moraine Park Campground Sewer at Rocky Mtn National Park | Interior, Department of / National Park Service | 4/20/2010 |
RICHARD P. ARBER ASSOCIATES, INC. | $67,546 | Contract | : Title III A/E Construction Management Services Task Order for Solar Equipment at El Portal Complex, Yosemite National Park | Interior, Department of / National Park Service | 5/13/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $498,850 | Contract | : Construction Management Services for the Rehabilitation of Independence Hall Tower in Philadelphia, PA | Interior, Department of / National Park Service | 5/14/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $53,733 | Contract | : Construction Management Services for small scale design-build projects to include: 1) Repair and replacement of an existing heating system within Hangar B at Floyd Bennett Field, Brooklyn, NY; 2) furnish and install switchgear at FBF. | Interior, Department of / National Park Service | 4/30/2010 |
FORD LOGGING INC | $290,092 | Contract | : Watershed restoration work to remove abandoned roads in Redwood National and State Parks. | Interior, Department of / National Park Service | 4/29/2010 |
WILDLANDS INC | $949,609 | Contract | : Revegetation Services to stabilize actively eroding areas at the Crystal Creek Quarry, Whiskeytown National Recreation Area, CA | Interior, Department of / National Park Service | 5/07/2010 |
OTIS ELEVATOR COMPANY | $290,000 | Contract | : rehabilitation of elevator | Interior, Department of / National Park Service | 5/10/2010 |
WISS, JANNEY, ELSTNER ASSOCIATES, INC. | $36,925 | Contract | : San Francisco Maritime National Historic Park - Survey and design services | Interior, Department of / National Park Service | 4/26/2010 |
HDR ENGINEERING, INC. | $406,664 | Contract | : Provide a full-time senior cost estimator to support the in-house staff at the National Park Service, Denver Service Center, for two years. | Interior, Department of / National Park Service | 5/25/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $742,544 | Contract | : On-site construction management services required for the Rehabilitation of the Mammoth Cave Visitor Center. | Interior, Department of / National Park Service | 4/05/2010 |
J JONASSEN INC | $101,901 | Contract | : Raise and install new foundation under the Glen Haven Cannery in the Sleeping Bear National Lakeshore in Empire, MI. | Interior, Department of / National Park Service | 5/17/2010 |
SUMMITT FORESTS INC | $32,288 | Contract | : CHIKASAW NAT. REC. AREA MANUAL AND MECHANICAL TREATMENT OF 142.1 ACRES | Interior, Department of / National Park Service | 6/08/2010 |
F&D INTERNATIONAL, LLC | $25,570 | Contract | : Construction Inspection Services for the restoration of the Sand Creek Gravel pits in the Great Sand Dune National Park. | Interior, Department of / National Park Service | 5/07/2010 |
AMEC ENVIRONMENT & INFRASTRUCTURE, INC. | $160,664 | Contract | : Replace Pump at Point X Lift station at Mammoth Cave National Park, KY. | Interior, Department of / National Park Service | 5/13/2010 |
CONSUMERS ENERGY COMPANY | $91,322 | Contract | : The purpose of this award is to provide payment for conversion of existing overhead electrical service to underground electric service in Glen Haven Historic Village, Empire, MI. Specific requirements are contained in Consumers Energy Agreement for Insta | Interior, Department of / National Park Service | 4/07/2010 |
HDR ENGINEERING, INC. | $795,726 | Contract | : Construction Management Services, Rehabilitation of Moose Maintenance Building, Grand Teton National Park | Interior, Department of / National Park Service | 5/14/2010 |
NOBLE SALES CO., INC. | $32,073 | Contract | : TREX DECKING FOR NPS | Interior, Department of / National Park Service | 12/21/2009 |
UNITED CONSTRUCTION COMPANY | $379,677 | Contract | : The project for the National Park Service at the Lake Mead National Recreation Area is being completed per CLIN 3 and 4 of the contract documents including changes received in contract modifications. United Construction will construct the Northern and Sou | Interior, Department of / National Park Service | 5/10/2010 |
SUMERSETT CONSTRUCTION INC. | $1,630,413 | Contract | : Harpers Ferry National Park Service Anthony Library interior renovations | Interior, Department of / National Park Service | 5/04/2010 |
APPALACHIAN TRAIL CONSERVANCY | $306,834 | Grant | National Trails System Projects: Trail & overnight Site Rehabilitation Park Location - Appalachian Trail Park Office located in Harpers Ferry, WV | Interior, Department of / National Park Service | 5/12/2010 |
MARTEL CONSTRUCTION, INC. | $618,616 | Contract | : Consists of minor demolition of existing building, new fire sprinklers and fire protection system and new metal roof with structural trusses. New atrium corridor with entrance vestibule, related grading, utilities, exterior aprons, walks and finish landsc | Interior, Department of / National Park Service | 5/11/2010 |
C-2 CONSTRUCTION INC | $473,512 | Contract | : Design and install Photovoltaic System in park building | Interior, Department of / National Park Service | 5/11/2010 |
HOWELL-OREGON ELECTRIC COOPERATIVE, INC. | $1,178,355 | Contract | : Replacing underground 3 phase power at Alley Springs and Round Springs Parks. | Interior, Department of / National Park Service | 5/14/2010 |
GLOBAL CONSTRUCTION GROUP INC | $7,981 | Contract | : Delivery of Concrete Piers, Pins and Caps to: PWR - LEWI Lewis and Clark NHP | Interior, Department of / National Park Service | 5/06/2010 |
B.C. SCHMIDT CONSTRUCTION, INC. | $82,249 | Contract | : Construction services to meet the requirements to render the mine sites safe with designs to enable bats and desert tortoises to thrive. Project includes all necessary project design and management, scheduling, activity hazard analysis, accident prevent | Interior, Department of / National Park Service | 4/01/2010 |
SUNWIZE TECHNOLOGIES, INC. | $158,748 | Contract | : installation of solar electric system Park | Interior, Department of / National Park Service | 4/21/2010 |
ALPHA CONSTRUCTION AND ENGINEERING CORPORATION | $234,316 | Contract | : Construction Management Services for various projects at Meriwether Lewis N.M. | Interior, Department of / National Park Service | 5/13/2010 |
HDR ENGINEERING, INC. | $1,727,005 | Contract | : Provide Construction Management Services for the design-build of a new Crow Creek Tribal School in Stephan, SD. | Interior, Department of / National Park Service | 5/12/2010 |
BARGMANN HENDRIE & ARCHETYPE, INC. | $26,741 | Contract | : FIIS Fire Island National Seashore / Bulkhead / Title III services for design/build contract for river bulkhead replacement. | Interior, Department of / National Park Service | 5/14/2010 |
ROGNLIN'S, INC. | $920,154 | Contract | : Supply and construct vaious elements to increase the capacity of the sanitary sewer treatment system within the Hoh Rainforest in Olympic National Park. The work includes removal of existing septic tanks, installation of new pumps, septic tanks, sanitary | Interior, Department of / National Park Service | 5/12/2010 |
INNOVAR ENVIRONMENTAL INC | $1,082,358 | Contract | : Install safety closures at abandoned mines throughout the Mojave National Preserve to protect visitors and preserve resources. | Interior, Department of / National Park Service | 4/01/2010 |
HDR ENGINEERING, INC. | $21,805 | Contract | : Architectural / Engineering Construction Services for MINT SPRINGS BLUFF STABILIZATION, VICKSBURG NATIONAL MILITARY PARK, VICKSBURG, MS | Interior, Department of / National Park Service | 5/06/2010 |
TORGERSON FOREST PRODUCTS, INC. | $49,467 | Contract | : Cedar Blanks | Interior, Department of / National Park Service | 4/09/2010 |
DESCHAMPS MATS SYSTEMS INC. | $94,718 | Contract | : Polyester Mats | Interior, Department of / National Park Service | 4/21/2010 |
N-POWELL COMPANY, INC. | $3,550,010 | Contract | : Stabilize Historic Nuttall Mine Structures at the New River Gorge National River | Interior, Department of / National Park Service | 4/06/2010 |
N-POWELL COMPANY, INC. | $1,563,032 | Contract | : Visitor Access and Appreciation Improvements at the New River Gorge National River Fayette County, West Virginia | Interior, Department of / National Park Service | 5/11/2010 |
GROUNDWORK USA, INC. | $57,336 | Grant | Conservation Activities by Youth Service Organizations: Youth preservation - rebuilding the historic dry stone walls at FDR presidential homestead | Interior, Department of / National Park Service | 4/28/2010 |
AEG POWER SOLUTIONS USA, INC. | $701,595 | Contract | : Facility Modifications to Kennesaw National Battlefield Park Visitor's Center, including replacement of roof, interior lighting upgrades, and installation of a Solar PV system on the roof. Original Award is $673,970, change order recevied on 8/31/2010 fo | Interior, Department of / National Park Service | 5/11/2010 |
NICKERSON & O'DAY, INC. | $7,352,292 | Contract | : Renovate former Navel Base-Schoodic buildings and site work at Acadia National Park, Winter Harbor, Maine into an education and research center. | Interior, Department of / National Park Service | 4/22/2010 |
DWG & ASSOCIATES, INC. | $115,331 | Contract | : REHABILITATE AGING MISSION 66 QUARTERS. This project will rehabilitate Quarters #4, a single family house built in the 1960?s of about 1700sf. Updating wiring to meet current codes is one goal of the project. Another is improving energy efficiency. Wa | Interior, Department of / National Park Service | 4/27/2010 |
ATKINS NORTH AMERICA, INC | $676,408 | Contract | : CM Services - Reconstruct Historic Stone Guardwalls along the Blue Ridge Parkway | Interior, Department of / National Park Service | 5/05/2010 |
MCDONOUGH BOLYARD PECK, INC. | $404,949 | Contract | : Assist project teams in managing NPS construction projects such as providing guidance to enhance quality and timely delivery; evaluate existing project documents for constructability issues; participate in weekly progress meetings; provide scope requireme | Interior, Department of / National Park Service | 6/02/2010 |
C3 LIMITED LIABILITY COMPANY | $682,787 | Contract | : INCREASING ENERGY EFFICIENCIES AT FACILITIES AT EVERGLADES NATL PARK, MAMMOTH CAVE NATL PARK, MARTIN LUTHER KING NATL HISTORIC SITE AND TIMUCUAN ECOLOGICAL PRESERVE | Interior, Department of / National Park Service | 5/05/2010 |
EVERGREEN TRACTOR LLC | $32,457 | Contract | : Rent Hitachi ZX450LC Hydraulic Excavator w/ Thumb and Biodegradable Hydraulic Fluid, Hitachi/Komatsu 350 Hydraulic Excavator w/ Thumb and Biodegradable Hydraulic Fluid, Delivery and Pick up Fees for Both Units | Interior, Department of / National Park Service | 8/03/2009 |
CLOPTON CONTRACTORS INC | $381,726 | Contract | : construction/renovation at Meriwether Lewis Park | Interior, Department of / National Park Service | 5/14/2010 |